Construction unit costs in Ohio

Median awarded unit prices for the 41 most-bid items on Ohio public projects, from winning bids in agency bid tabulations.

Cost by state › Ohio

ItemPerMedianMiddle halfWinning bids
Aggregate Basecubic yard$88.80$63.50 – $145.9578
Walk Removedsquare foot$3.00$1.75 – $7.8565
Asphalt Concrete Surface Course, Type 1, (449), Pg64-22cubic yard$298.80$243.50 – $423.7663
Aggregate Base, As Per Plancubic yard$65.50$50.00 – $80.0062
Seeding And Mulching, Class 1, As Per Plansquare yard$4.42$2.92 – $7.0058
Subgrade Compaction, As Per Plansquare yard$3.00$1.00 – $5.0058
Non-Tracking Tack Coat, 0.06 Gal/S.Y.gallon$10.00$5.25 – $17.0057
Erosion Controleach$1.00$1.00 – $1.0053
Stabilized Crushed Aggregatecubic yard$62.50$46.40 – $95.8848
Curb Ramp, As Per Plansquare foot$18.95$13.90 – $30.0048
Asphalt Concrete Intermediate Course, Type 2, (449)cubic yard$331.04$255.50 – $442.5746
Curb Removedlinear foot$8.00$5.00 – $10.0045
Curb And Gutter Removedlinear foot$10.00$7.88 – $11.6043
Pipe Removed, 24" And Underlinear foot$22.04$10.00 – $30.0042
4" Concrete Walksquare foot$12.94$9.00 – $16.0041
Non-Tracking Tack Coatgallon$3.74$2.34 – $5.0040
Pavement Planing, Asphalt Concrete, As Per Plansquare yard$4.00$2.56 – $6.0039
Subgrade Compactionsquare yard$2.00$1.03 – $3.9038
4" Conduit, Type B, 707.45, Storm Repairlinear foot$11.00$5.21 – $23.7538
Asphalt Concrete Base, Pg64-22, (449)cubic yard$265.25$208.93 – $389.3838
6" Conduit, Type B, 707.45, Storm Repairlinear foot$16.00$11.16 – $30.0037
Valve Box Adjusted To Gradeeach$300.00$197.60 – $550.0037
8" Conduit, Type B, 707.45, Storm Repairlinear foot$22.50$18.89 – $36.2536
Manhole Adjusted To Gradeeach$715.27$499.50 – $1,07936
Removal Of Ground Mounted Sign And Reerectioneach$100.00$69.26 – $200.0036
Seeding And Mulching, As Per Plansquare yard$4.28$2.00 – $9.0234
6" Fire Hydrant Assembly, As Per Planeach$8,300$7,000 – $9,50033
Valve Box Removedeach$160.15$100.00 – $300.0032
Catch Basin Removedeach$350.00$219.66 – $594.1532
Stop Linelinear foot$11.00$9.19 – $16.0032
Excavationcubic yard$35.00$25.00 – $54.0831
Embankmentcubic yard$30.00$24.25 – $50.0030
Pavement Removedsquare yard$18.25$12.14 – $25.0029
4" Concrete Walk, As Per Plansquare foot$9.95$8.81 – $12.5029
Center Linemile$7,000$4,085 – $12,42527
Tack Coatgallon$3.25$3.00 – $4.5025
Asphalt Concrete Base, Pg64-22cubic yard$368.00$220.00 – $550.0025
8" Gate Valveeach$2,676$2,500 – $2,89824
Asphalt Concrete Surface Course, Type 1, (448), Pg64-22cubic yard$385.00$268.03 – $587.5023
Curb Rampsquare foot$20.00$15.59 – $33.0018
Guardrail Removedlinear foot$4.00$3.08 – $8.2115