Village Of Genoa: awarded unit prices

30 winning bid prices read from 3 source documents, 2022. The table lists the 16 items this agency awarded most often. Winning bids only; every row links to a bid tabulation.

Cost by state › Agencies › Village Of Genoa

ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Sawing and seal asphalt concrete pavement joint, as per planlinear foot3—$2.10$2.10Mar 16, 2022, Open bid tab, 220121 ↗
Pavement milling, asphalt concretesquare yard3—$5.80$5.80 – $12.50Mar 16, 2022, Open bid tab, 220121 ↗
Maintaining Traffic, As Per Planls3—$4,500$1,000 – $4,500Mar 16, 2022, Open bid tab, 220121 ↗
Asphalt Concrete Surface Course, Type 1, (449), Pg64-22cubic yard3—$220.00$220.00 – $400.00Mar 16, 2022, Open bid tab, 220121 ↗
Non-Tracking Tack Coatgallon3—$2.25$2.25Mar 16, 2022, Open bid tab, 220121 ↗
Granular Embankment, As Per Plancubic yard2—$35.00$35.00 – $50.00Mar 16, 2022, Open bid tab, 220121 ↗
Proof Rollinghour2—$104.00$104.00Mar 16, 2022, Open bid tab, 220121 ↗
Excavation Of Subgradecubic yard2—$24.00$24.00 – $37.00Mar 16, 2022, Open bid tab, 220121 ↗
Subgrade Compactionsquare yard2—$0.4$0.4Mar 16, 2022, Open bid tab, 220121 ↗
Grading And Compacting Existing Base Material (Below Milled Surface)square yard1—$2.90$2.90Mar 16, 2022, Open bid tab, 220121 ↗
Temporary Erosion Control, As Per Planls1—$1,250$1,250Mar 16, 2022, Open bid tab, 220121 ↗
Seeding And Mulching, Class 1, As Per Planls1—$2,600$2,600Mar 16, 2022, Open bid tab, 220121 ↗
Asphalt Concrete Intermediate Course, Type 1, (449)cubic yard1—$220.00$220.00Mar 16, 2022, Open bid tab, 220121 ↗
Asphalt Concrete Base, Pg64-22, (449)cubic yard1—$190.00$190.00Mar 16, 2022, Open bid tab, 220121 ↗
Asphalt Concrete Intermediate Course, Type 2, (449)cubic yard1—$195.00$195.00Mar 16, 2022, Open bid tab, 220121 ↗
Mobilizationls1—$6,500$6,500Mar 16, 2022, Open bid tab, 220121 ↗

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.