| Contingency/Discretionary Allowance | ls | 14 | — | $20,000 | $5,000 – $100,000 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| Special - Miscellaneous Metal | pound | 11 | $1.60 | $5.00 | $0.5 – $5.00 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| CATCH BASIN ADJUSTED TO GRADE, METHOD D.1 (brick), AS PER PLAN | each | 10 | $950.00 | $1,000 | $400.00 – $1,300 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| Valve Box Adjusted To Grade, As Per Plan | each | 10 | $500.00 | $985.00 | $100.00 – $1,100 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| Full deep pavement remove and rigid replace, class qc ms, t=8 inch, as per plan | square yard | 9 | $125.00 | $185.00 | $75.00 – $185.00 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| Special - concrete seal surface treatment, sinak, as per plan | square yard | 9 | $6.25 | $0.5 | $0.5 – $14.00 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| Lawn Restoration Incl. Lineal Grading & Topsoil, As Per Plan | ls | 9 | $9,000 | $5,000 | $1,000 – $45,020 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| MANHOLE ADJUSTED TO GRADE, METHOD D.1 (brick), AS PER PLAN | each | 9 | $1,000 | $1,000 | $250.00 – $1,200 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| Curb, type 6, including remove, as per plan | linear foot | 8 | $54.23 | $45.00 | $29.00 – $100.00 | Sep 12, 2025, Open bid tab, 0000032252 ↗ |
| Temporary Sediment And Erosion Control, As Per Plan | ls | 8 | $1,450 | $2,000 | $500.00 – $3,558 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| Geotextile Fabric, As Per Plan | square yard | 8 | $3.00 | $2.00 | $1.00 – $5.00 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| Tack Coat, Trackless Tack | gallon | 8 | $3.06 | $2.00 | $2.00 – $7.00 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| Special - Void Reducing Asphalt Membrane (Vram) | linear foot | 7 | $2.90 | $2.50 | $2.10 – $6.95 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| Asphalt Concrete Intermediate Course, Type 1, (448), As Per Plan | cubic yard | 7 | $215.00 | $215.00 | $155.00 – $260.00 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| Pavement milling, asphalt concrete, as per plan | square yard | 7 | $4.20 | $7.00 | $2.25 – $7.00 | Sep 12, 2025, Open bid tab, 0000032252 ↗ |
| Preconstruction Video Documentation | ls | 7 | $1,000 | $1,200 | $519.00 – $2,000 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| Maintaining Traffic, As Per Plan | ls | 7 | — | $72,545 | $3,000 – $100,000 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| Special - pavement reinforced fabric - fiberglass/polyester blend, as per plan | square yard | 5 | $5.20 | $5.20 | $3.30 – $9.00 | May 31, 2024, Open bid tab, 240262 ↗ |
| Asphalt Preservative Seal, As Per Plan | square yard | 5 | $1.15 | $1.20 | $1.00 – $1.50 | Aug 12, 2022, Open bid tab, 220262 ↗ |
| Partial deep pavement joint repair, as per plan | cubic yard | 5 | $1,500 | $1,000 | $950.00 – $1,846 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| Excavation Of Subgrade And Embankment With Granular Material, Ccs, As Per Plan, Contingency | cubic yard | 5 | $60.00 | $120.00 | $25.00 – $120.00 | May 31, 2024, Open bid tab, 240262 ↗ |
| 4 inch concrete walk, including remove, as per plan | square foot | 5 | $13.00 | $13.00 | $6.50 – $14.00 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| Asphalt Concrete Surface Course, Type 1, (448), Pg64-22, As Per Plan | cubic yard | 5 | $225.00 | $225.00 | $210.00 – $300.00 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| Catch Basin With Sump & Trap, As Per Plan | each | 4 | — | $4,740 | $2,979 – $8,500 | Sep 12, 2025, Open bid tab, 0000032252 ↗ |
| Partial deep pavement repair, as per plan | cubic yard | 4 | — | $780.00 | $420.00 – $1,250 | May 22, 2026, Open bid tab, 0000044497 ↗ |
| Monument Assembly Adjusted To Grade | each | 4 | — | $1,000 | $500.00 – $1,100 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| 4 Inch Unclassified Pipe Underdrains, With Geotextile Fabric, As Per Plan | linear foot | 4 | — | $8.00 | $8.00 – $26.00 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| Crosswalk Line | linear foot | 4 | — | $5.80 | $3.00 – $10.00 | Sep 12, 2025, Open bid tab, 0000032252 ↗ |
| Stop Line | linear foot | 4 | — | $9.25 | $6.00 – $10.00 | Sep 12, 2025, Open bid tab, 0000032252 ↗ |
| Conduit Point Repairs, Lateral Reconnection, As Per Plan | each | 3 | — | $4,769 | $4,003 – $9,456 | Sep 12, 2025, Open bid tab, 0000032252 ↗ |
| Mobilization, Maintaining Traffic, Erosion Control, Bonds And Insurances And Other Overhea | ls | 3 | — | $1,318 | $1,318 – $195,000 | Oct 21, 2022, Open bid tab, 22026201 ↗ |
| Loop detector replace | each | 3 | — | $1,700 | $1,150 – $2,000 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| Special - Asphalt Preservative Seal | square yard | 3 | — | $2.00 | $1.20 – $2.45 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| 6 inch concrete walk or drive apron, including remove, as per plan | square foot | 3 | — | $16.00 | $12.00 – $16.00 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| Excavation Of Subgrade And Embankment With Granular Material, Ccs, As Per Plan, Contin | cubic yard | 3 | — | $80.00 | $5.00 – $80.00 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| Monument Box Adjusted To Grade | each | 3 | — | $500.00 | $350.00 – $575.00 | Jul 1, 2022, Open bid tab, 220262 ↗ |
| Bonds And Insurances, As Per Plan | ls | 3 | — | $8,450 | $5,178 – $15,000 | Jun 17, 2026, Open bid tab, 0000044497 ↗ |
| 12 inch storm sewer, as per plan | linear foot | 3 | — | $100.00 | $100.00 – $379.65 | Sep 12, 2025, Open bid tab, 0000032252 ↗ |
| Work Zone Channelizing Line, Class I, 642 Paint | linear foot | 2 | — | $3.00 | $2.00 – $3.00 | Aug 12, 2022, Open bid tab, 220261 ↗ |
| 10 Inch Conduit Point Repair, As Per Plan | each | 2 | — | $10,539 | $9,405 – $10,539 | Sep 12, 2025, Open bid tab, 0000032252 ↗ |