| 8 inch conduit, type b, 707.45, storm repair | linear foot | 3 | — | $30.00 | $20.85 – $35.00 | Apr 2, 2025, Open bid tab, bidtabdefhic1903pdf ↗ |
| 6 inch conduit, type b, 707.45, storm repair | linear foot | 3 | — | $20.50 | $12.41 – $25.00 | Apr 2, 2025, Open bid tab, bidtabdefhic1903pdf ↗ |
| 4 inch conduit, type b, 707.45, storm repair | linear foot | 3 | — | $16.75 | $5.59 – $16.75 | Apr 2, 2025, Open bid tab, bidtabdefhic1903pdf ↗ |
| Maintaining Traffic | ls | 3 | — | $5,000 | $5,000 – $8,000 | Apr 2, 2025, Open bid tab, bidtabdefhic1903pdf ↗ |
| Aggregate Base, As Per Plan | cubic yard | 3 | — | $45.00 | $30.00 – $45.00 | Apr 2, 2025, Open bid tab, bidtabdefhic1903pdf ↗ |
| Removed, As Per Plan | ls | 3 | — | $2,500 | $2,500 – $5,891 | Apr 2, 2025, Open bid tab, bidtabdefhic1903pdf ↗ |
| Seeding And Mulching, Class 1, As Per Plan | square yard | 2 | — | $6.10 | $6.10 – $6.50 | Apr 2, 2025, Open bid tab, bidtabdefhic1903pdf ↗ |
| Subgrade Compaction | square yard | 2 | — | $19.00 | $1.00 – $19.00 | Apr 2, 2025, Open bid tab, bidtabdefhic1903pdf ↗ |
| Non-Tracking Tack Coat, 0.06 Gal/S.Y. | gallon | 2 | — | $33.33 | $3.00 – $33.33 | Apr 2, 2025, Open bid tab, bidtabdefhic1903pdf ↗ |
| Removed And Reset Mailbox | each | 1 | — | $100.00 | $100.00 | Jan 26, 2023, Open bid tab, bidtabdefhic2203pdf ↗ |
| Storm Manhole, No.3, As Per Plan | each | 1 | — | $3,750 | $3,750 | Jan 26, 2023, Open bid tab, bidtabdefhic2203pdf ↗ |
| 15 inch cpslp storm, as per plan | linear foot | 1 | — | $92.00 | $92.00 | Jan 26, 2023, Open bid tab, bidtabdefhic2203pdf ↗ |
| 12 inch cpslp storm, as per plan | linear foot | 1 | — | $60.00 | $60.00 | Jan 26, 2023, Open bid tab, bidtabdefhic2203pdf ↗ |
| 1-1/2 inch pavement planning | square yard | 1 | — | $3.00 | $3.00 | Jan 26, 2023, Open bid tab, bidtabdefhic2203pdf ↗ |
| Asphalt Concrete, Intermediate Course, Type 2 (449) Pg64-22 | cubic yard | 1 | — | $600.59 | $600.59 | Sep 28, 2023, Open bid tab, bidtabdefhic2202pdf ↗ |
| Tack Coat, Applied At 0.06 Gal/S.Y. | gallon | 1 | — | $2.83 | $2.83 | Sep 28, 2023, Open bid tab, bidtabdefhic2202pdf ↗ |
| Lift Station Electric Service | ls | 1 | — | $17,500 | $17,500 | Apr 2, 2025, Open bid tab, bidtabdefhic1903pdf ↗ |
| Lift Station | ls | 1 | — | $343,320 | $343,320 | Apr 2, 2025, Open bid tab, bidtabdefhic1903pdf ↗ |
| Existing lift station remove | ls | 1 | — | $9,365 | $9,365 | Apr 2, 2025, Open bid tab, bidtabdefhic1903pdf ↗ |
| 6 inch hdpe dr-11 (dips) forcemain, as per plan | linear foot | 1 | — | $100.00 | $100.00 | Apr 2, 2025, Open bid tab, bidtabdefhic1903pdf ↗ |
| 4 inch asphalt concrete base (449) pg 64-22 | cubic yard | 1 | — | $500.00 | $500.00 | Apr 2, 2025, Open bid tab, bidtabdefhic1903pdf ↗ |
| Pipe removed, 24 inch diameter. and under | linear foot | 1 | — | $100.00 | $100.00 | Apr 2, 2025, Open bid tab, bidtabdefhic1903pdf ↗ |
| Pavement Removed, Gravel | square yard | 1 | — | $77.00 | $77.00 | Apr 2, 2025, Open bid tab, bidtabdefhic1903pdf ↗ |
| Asphalt Concrete Base | cubic yard | 1 | — | $398.10 | $398.10 | Sep 28, 2023, Open bid tab, bidtabdefhic2202pdf ↗ |
| Seeding And Mulching, Type 1, As Per Plan | square yard | 1 | — | $7.28 | $7.28 | Sep 28, 2023, Open bid tab, bidtabdefhic2202pdf ↗ |
| 15 inch sanitary sewer, as per plan | linear foot | 1 | — | $110.00 | $110.00 | Apr 2, 2025, Open bid tab, bidtabdefhic1903pdf ↗ |
| Type 2-2C Catch Basin, As Per Plan | each | 1 | — | $2,400 | $2,400 | Jan 26, 2023, Open bid tab, bidtabdefhic2203pdf ↗ |
| 1-1/2 inch asphalt concrete surface course, type 1, (449), pg64-22 | cubic yard | 1 | — | $2,500 | $2,500 | Apr 2, 2025, Open bid tab, bidtabdefhic1903pdf ↗ |
| Sanitary Sewer Manhole, Type 3, As Per Plan | each | 1 | — | $6,000 | $6,000 | Apr 2, 2025, Open bid tab, bidtabdefhic1903pdf ↗ |
| 3/4 inch water service branch, as per plan (type k copper) | linear foot | 1 | — | $70.06 | $70.06 | Sep 28, 2023, Open bid tab, bidtabdefhic2202pdf ↗ |
| Type 2-2B Catch Basin, As Per Plan | each | 1 | — | $2,200 | $2,200 | Jan 26, 2023, Open bid tab, bidtabdefhic2203pdf ↗ |
| 6 inchx6 inch tapping sleeve and valve | each | 1 | — | $4,760 | $4,760 | Sep 28, 2023, Open bid tab, bidtabdefhic2202pdf ↗ |
| 2-1/2 inch asphalt concrete intermediate course, type 2, (449) | cubic yard | 1 | — | $515.00 | $515.00 | Jan 26, 2023, Open bid tab, bidtabdefhic2203pdf ↗ |
| 1-1/2 inch asphalt concrete surface course, type 1, pg 64-22, (449) | cubic yard | 1 | — | $305.00 | $305.00 | Jan 26, 2023, Open bid tab, bidtabdefhic2203pdf ↗ |
| Special - Cut And Plug Existing Water Line | each | 1 | — | $877.54 | $877.54 | Sep 28, 2023, Open bid tab, bidtabdefhic2202pdf ↗ |
| Manhole Removed | each | 1 | — | $2,000 | $2,000 | Apr 2, 2025, Open bid tab, bidtabdefhic1903pdf ↗ |
| 6 inch water main, as per plan (c900, dr18) | linear foot | 1 | — | $82.09 | $82.09 | Sep 28, 2023, Open bid tab, bidtabdefhic2202pdf ↗ |
| Asphalt Concrete Surface Course, Type 1, (449), Pg64-22 | cubic yard | 1 | — | $305.96 | $305.96 | Sep 28, 2023, Open bid tab, bidtabdefhic2202pdf ↗ |
| 8 inch pvc sdr-35 sanitary sewer, as per plan | linear foot | 1 | — | $65.00 | $65.00 | Jan 26, 2023, Open bid tab, bidtabdefhic2203pdf ↗ |
| Catch Basin Removed | each | 1 | — | $175.00 | $175.00 | Jan 26, 2023, Open bid tab, bidtabdefhic2203pdf ↗ |