30 winning bid prices read from 1 source documents, 2025. The table lists the 30 items this agency awarded most often. Winning bids only; every row links to a bid tabulation.

Cost by state › Agencies › City of Mentor PROJECT NO.: 241484

ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Sharrow Bike Lane Lane Symbol Marking, Type A1each1—$525.00$525.00May 9, 2025, Open bid tab, 241484 ↗
Bike Lane Symbol Marking, Type A1each1—$225.00$225.00May 9, 2025, Open bid tab, 241484 ↗
Portable Changeable Message Sign, As Per Planmnth1—$900.00$900.00May 9, 2025, Open bid tab, 241484 ↗
Law Enforcement Officer With Patrol Car For Enforcement, As Per Planhour1—$100.00$100.00May 9, 2025, Open bid tab, 241484 ↗
Guardrail and rubrail rebuilt, type 5, using 9 foot postlinear foot1—$49.20$49.20May 9, 2025, Open bid tab, 241484 ↗
Guardrail Rubrail Rebuiltlinear foot1—$21.60$21.60May 9, 2025, Open bid tab, 241484 ↗
Guardrail, type 5, rail replacelinear foot1—$17.20$17.20May 9, 2025, Open bid tab, 241484 ↗
Dumped Rock Fill, Type Dcubic yard1—$158.00$158.00May 9, 2025, Open bid tab, 241484 ↗
Partial deep pavement joint repair, as per planlinear foot1—$10.00$10.00May 9, 2025, Open bid tab, 241484 ↗
Partial deep pavement repair (asphalt concrete base)cubic yard1—$600.00$600.00May 9, 2025, Open bid tab, 241484 ↗
Rub Rail Removedlinear foot1—$6.40$6.40May 9, 2025, Open bid tab, 241484 ↗
Guardrail And Rubrail Removed For Reuse, As Per Planlinear foot1—$7.60$7.60May 9, 2025, Open bid tab, 241484 ↗
Asphalt Concrete Intermediate Course, Type 2, (448), As Per Plancubic yard1—$186.00$186.00May 9, 2025, Open bid tab, 241484 ↗
Valve Box Adjusted To Grade, As Per Planeach1—$1,000$1,000May 9, 2025, Open bid tab, 241484 ↗
Asphalt Concrete Surface Course, Type 1, (448), Pg64-22, As Per Plancubic yard1—$192.00$192.00May 9, 2025, Open bid tab, 241484 ↗
Pavement milling, asphalt concrete, as per plansquare yard1—$2.55$2.55May 9, 2025, Open bid tab, 241484 ↗
Contingency/Discretionary Allowancels1—$10,000$10,000May 9, 2025, Open bid tab, 241484 ↗
Bonds And Insurances, As Per Planls1—$2,000$2,000May 9, 2025, Open bid tab, 241484 ↗
Preconstruction Video Documentationls1—$600.00$600.00May 9, 2025, Open bid tab, 241484 ↗
Tack Coat, Trackless Tackgallon1—$2.75$2.75May 9, 2025, Open bid tab, 241484 ↗
Guardrail Removed, As Per Planlinear foot1—$4.60$4.60May 9, 2025, Open bid tab, 241484 ↗
Manhole Adjusted To Grade, As Per Planeach1—$1,000$1,000May 9, 2025, Open bid tab, 241484 ↗
Edge line, 6 inchmile1—$1,025$1,025May 9, 2025, Open bid tab, 241484 ↗
Edge line, 4 inchmile1—$725.00$725.00May 9, 2025, Open bid tab, 241484 ↗
Asphalt Concrete Base, Pg64-22cubic yard1—$198.00$198.00May 9, 2025, Open bid tab, 241484 ↗
Center Linemile1—$1,300$1,300May 9, 2025, Open bid tab, 241484 ↗
Maintaining Trafficls1—$18,000$18,000May 9, 2025, Open bid tab, 241484 ↗
Aggregate Basecubic yard1—$146.00$146.00May 9, 2025, Open bid tab, 241484 ↗
Mobilizationls1—$20,000$20,000May 9, 2025, Open bid tab, 241484 ↗
Excavationcubic yard1—$88.00$88.00May 9, 2025, Open bid tab, 241484 ↗

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.