Skip to content
Hubstake

Agency · awarded bid prices

Boardman Township, OH: awarded unit prices

26 winning bid prices read from 1 source documents, 2026. The table lists the 26 items this agency awarded most often. Winning bids only; every row links to a bid tabulation.

Cost by state › Agencies › Boardman Township, OH

ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
6 inch water main ductile iron pipe ansi class 52, mechanical joint and fitting, as per plalinear foot1—$693.00$693.00Jun 12, 2026, Open bid tab, 0000039498 ↗
Mobilization, As Per Planls1—$9,950$9,950Jun 12, 2026, Open bid tab, 0000039498 ↗
Junction Chamber, As Per Planeach1—$67,952$67,952Jun 12, 2026, Open bid tab, 0000039498 ↗
Conduit, Misc.: Concrete Encasement - Single Conduitlinear foot1—$285.00$285.00Jun 12, 2026, Open bid tab, 0000039498 ↗
3.5' x 9.0' CONDUIT, TYPE A, 706.05, AS PER PLANlinear foot1—$1,425$1,425Jun 12, 2026, Open bid tab, 0000039498 ↗
22 inch sanitary sewer, as per planlinear foot1—$218.00$218.00Jun 12, 2026, Open bid tab, 0000039498 ↗
Concrete walk, including remove, as per plansquare foot1—$25.00$25.00Jun 12, 2026, Open bid tab, 0000039498 ↗
Vault Removed, As Per Planeach1—$4,500$4,500Jun 12, 2026, Open bid tab, 0000039498 ↗
Lawn Restoration, As Per Planls1—$6,695$6,695Jun 12, 2026, Open bid tab, 0000039498 ↗
48 Inch Sanitary Manhole, As Per Planeach1—$5,801$5,801Jun 12, 2026, Open bid tab, 0000039498 ↗
Temporary Sediment And Erosion Control, As Per Planls1—$1,958$1,958Jun 12, 2026, Open bid tab, 0000039498 ↗
Concrete apron or drive replace, as per plansquare yard1—$310.00$310.00Jun 12, 2026, Open bid tab, 0000039498 ↗
Bonds And Insurances, As Per Planls1—$3,938$3,938Jun 12, 2026, Open bid tab, 0000039498 ↗
Preconstruction Video Documentationls1—$500.00$500.00Jun 12, 2026, Open bid tab, 0000039498 ↗
Bypass Pumping, As Per Planls1—$11,300$11,300Jun 12, 2026, Open bid tab, 0000039498 ↗
15 inch conduit, type blinear foot1—$138.00$138.00Jun 12, 2026, Open bid tab, 0000039498 ↗
18 inch conduit, type blinear foot1—$190.00$190.00Jun 12, 2026, Open bid tab, 0000039498 ↗
8 inch sanitary sewer, as per planlinear foot1—$213.00$213.00Jun 12, 2026, Open bid tab, 0000039498 ↗
Pavement Removed, As Per Plansquare yard1—$46.00$46.00Jun 12, 2026, Open bid tab, 0000039498 ↗
Manhole Removedeach1—$500.00$500.00Jun 12, 2026, Open bid tab, 0000039498 ↗
Maintaining Traffic, As Per Planls1—$1,500$1,500Jun 12, 2026, Open bid tab, 0000039498 ↗
Construction Layout Stakes And Surveyingls1—$1,500$1,500Jun 12, 2026, Open bid tab, 0000039498 ↗
Catch Basin, No. 3A, As Per Planeach1—$3,050$3,050Jun 12, 2026, Open bid tab, 0000039498 ↗
Catch Basin Removedeach1—$300.00$300.00Jun 12, 2026, Open bid tab, 0000039498 ↗
Pipe removed, 24 inch and underlinear foot1—$10.00$10.00Jun 12, 2026, Open bid tab, 0000039498 ↗
Clearing and Grubbingls1—$9,500$9,500Jun 12, 2026, Open bid tab, 0000039498 ↗

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.