| Asphalt Concrete Intermediate Course, Type 2, Pg64-22, As Per Plan | cubic yard | 2 | — | $195.00 | $195.00 | Mar 17, 2022, Open bid tab, 210427 ↗ |
| Excavation Of Subgrade And Embankment With Granular Material, As Per Plan, Contingency | cubic yard | 2 | — | $138.00 | $108.00 – $138.00 | Mar 17, 2022, Open bid tab, 210427 ↗ |
| Asphalt Concrete Surface Course, Type 1, Pg64-22, As Per Plan | cubic yard | 2 | — | $208.00 | $208.00 | Mar 17, 2022, Open bid tab, 210427 ↗ |
| Non-Tracking Tack Coat, As Per Plan | gallon | 2 | — | $4.25 | $4.25 – $4.50 | Mar 17, 2022, Open bid tab, 210427 ↗ |
| Subgrade Compaction, As Per Plan | square yard | 2 | — | $1.00 | $1.00 | Mar 17, 2022, Open bid tab, 210427 ↗ |
| 18 inch prefabricated edge underdrain | linear foot | 1 | — | $20.50 | $20.50 | Mar 17, 2022, Open bid tab, 210427 ↗ |
| Inlet basin/catch basin clean, as per plan | each | 1 | — | $550.00 | $550.00 | Mar 17, 2022, Open bid tab, 210427 ↗ |
| Roadway, Misc.: Excavation Of Existing Stone Running Track | cubic yard | 1 | — | $75.00 | $75.00 | Mar 17, 2022, Open bid tab, 210427 ↗ |
| Pavement removed, as per plan (driveway) | square yard | 1 | — | $3.25 | $3.25 | Mar 17, 2022, Open bid tab, 210427 ↗ |
| Special - Concrete Parking Block | each | 1 | — | $136.00 | $136.00 | Mar 17, 2022, Open bid tab, 210427 ↗ |
| Lawn Restoration Incl. Lineal Grading & Topsoil, As Per Plan | ls | 1 | — | $17,500 | $17,500 | Mar 17, 2022, Open bid tab, 210427 ↗ |
| Traffic Paint, As Per Plan | ls | 1 | — | $1,750 | $1,750 | Mar 17, 2022, Open bid tab, 210427 ↗ |
| Contingency/Discretionary Allowance | ls | 1 | — | $20,000 | $20,000 | Mar 17, 2022, Open bid tab, 210427 ↗ |
| Temporary Sediment And Erosion Control, As Per Plan | ls | 1 | — | $7,000 | $7,000 | Mar 17, 2022, Open bid tab, 210427 ↗ |
| Sign, Flat Sheet, With Mounting Post | each | 1 | — | $325.00 | $325.00 | Mar 17, 2022, Open bid tab, 210427 ↗ |
| Walk Removed, As Per Plan | square foot | 1 | — | $3.00 | $3.00 | Mar 17, 2022, Open bid tab, 210427 ↗ |
| Bonds And Insurances, As Per Plan | ls | 1 | — | $4,000 | $4,000 | Mar 17, 2022, Open bid tab, 210427 ↗ |
| Preconstruction Video Documentation | ls | 1 | — | $1,750 | $1,750 | Mar 17, 2022, Open bid tab, 210427 ↗ |
| Excavation, As Per Plan | cubic yard | 1 | — | $52.00 | $52.00 | Mar 17, 2022, Open bid tab, 210427 ↗ |
| 4 inch concrete walk, as per plan | square foot | 1 | — | $14.25 | $14.25 | Mar 17, 2022, Open bid tab, 210427 ↗ |
| Aggregate Base, As Per Plan | cubic yard | 1 | — | $90.00 | $90.00 | Mar 17, 2022, Open bid tab, 210427 ↗ |
| Excavation, Including Embankment Construction, As Per Plan | cubic yard | 1 | — | $52.00 | $52.00 | Mar 17, 2022, Open bid tab, 210427 ↗ |
| Mobilization | ls | 1 | — | $4,500 | $4,500 | Mar 17, 2022, Open bid tab, 210427 ↗ |