Village of Fort Loramie: awarded unit prices

304 winning bid prices read from 9 source documents, 2021–2025. The table lists the 40 items this agency awarded most often. Winning bids only; every row links to a bid tabulation.

Cost by state › Agencies › Village of Fort Loramie

ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Maintaining Trafficls7$6,166$4,429$1,000 – $10,000Jun 4, 2025, Open bid tab, bidtabsheflo2107pdf ↗
Removed, As Per Planls6$8,645$10,290$1,577 – $40,389Jul 16, 2025, Open bid tab, bidtabsheflo2501pdf ↗
Asphalt Concrete Surface Course, Type 1, (449), Pg64-22cubic yard5$360.00$273.50$228.50 – $1,199Jul 16, 2025, Open bid tab, bidtabsheflo2501pdf ↗
6 inch non-reinforced concrete pavement, as per plansquare yard5$100.00$68.90$68.90 – $169.34Jun 4, 2025, Open bid tab, bidtabsheflo2107pdf ↗
Non-Tracking Tack Coatgallon5$11.57$11.57$4.50 – $164.01Jun 4, 2025, Open bid tab, bidtabsheflo2107pdf ↗
Seeding And Mulching, Class 1, As Per Plansquare yard5$2.62$1.53$1.53 – $6.77Jul 16, 2025, Open bid tab, bidtabsheflo2501pdf ↗
Aggregate Basecubic yard5$53.70$81.28$39.00 – $97.00Feb 24, 2025, Open bid tab, bidtabsheflo2301pdf ↗
Detour Signing, As Per Planls4—$7,165$5,000 – $13,757Jun 4, 2025, Open bid tab, bidtabsheflo2107pdf ↗
Asphalt Concrete Intermediate Course, Type 2, (449)cubic yard4—$205.12$205.12 – $400.00Jul 16, 2025, Open bid tab, bidtabsheflo2501pdf ↗
Erosion Controleach4—$1.00$1.00Jul 16, 2025, Open bid tab, bidtabsheflo2501pdf ↗
6 inch fire hydrant assembly, as per planeach4—$8,550$8,065 – $10,547Jul 16, 2025, Open bid tab, bidtabsheflo2501pdf ↗
Walk Removedsquare foot4—$1.42$0.53 – $5.00Jun 4, 2025, Open bid tab, bidtabsheflo2107pdf ↗
12 inch awwa c-900 dr-18 water main, as per planlinear foot3—$92.08$92.08 – $117.79Jul 16, 2025, Open bid tab, bidtabsheflo2501pdf ↗
Storm Sewer Cleanout (Out Of Pavement), As Per Planeach3—$227.89$227.89 – $425.57Jun 4, 2025, Open bid tab, bidtabsheflo2107pdf ↗
6 inch storm sewer lateral, as per planlinear foot3—$47.02$44.51 – $75.00Jun 4, 2025, Open bid tab, bidtabsheflo2107pdf ↗
Catch Basin, Type 1, As Per Planeach3—$3,267$2,188 – $3,267Jul 16, 2025, Open bid tab, bidtabsheflo2501pdf ↗
Asphalt Concrete Base, Pg64-22, (449)cubic yard3—$184.08$184.08 – $383.00Jul 16, 2025, Open bid tab, bidtabsheflo2501pdf ↗
Storm Sewer Manhole, No. 3, As Per Planeach3—$5,617$3,951 – $7,000Jul 16, 2025, Open bid tab, bidtabsheflo2501pdf ↗
8 inch conduit, type b, 707.45, storm repair, as per planlinear foot3—$19.49$19.49 – $25.98Jun 4, 2025, Open bid tab, bidtabsheflo2107pdf ↗
6 inch conduit, type b, 707.45, storm repair, as per planlinear foot3—$11.73$11.73 – $21.62Jun 4, 2025, Open bid tab, bidtabsheflo2107pdf ↗
4 inch conduit, type b, 707.45, storm repair, as per planlinear foot3—$5.68$5.68 – $18.31Jun 4, 2025, Open bid tab, bidtabsheflo2107pdf ↗
8 inch conduit, type b, 707.45, storm repairlinear foot3—$30.01$30.01 – $46.62Jul 16, 2025, Open bid tab, bidtabsheflo2501pdf ↗
6 inch conduit, type b, 707.45, storm repairlinear foot3—$22.29$22.29 – $36.95Jul 16, 2025, Open bid tab, bidtabsheflo2501pdf ↗
4 inch conduit, type b, 707.45, storm repairlinear foot3—$18.17$18.17 – $29.71Jul 16, 2025, Open bid tab, bidtabsheflo2501pdf ↗
Subgrade Compactionsquare yard3—$1.00$0.45 – $1.00Jan 27, 2023, Open bid tab, bidtabsheflo2203pdf ↗
Remove of ground mounted sign and reerectioneach3—$72.74$72.74 – $88.56Jun 4, 2025, Open bid tab, bidtabsheflo2107pdf ↗
Stabilized Crushed Aggregatecubic yard3—$89.65$54.03 – $160.00Jun 4, 2025, Open bid tab, bidtabsheflo2107pdf ↗
Subgrade Compaction, As Per Plansquare yard3—$0.52$0.52 – $0.81Jul 16, 2025, Open bid tab, bidtabsheflo2501pdf ↗
36 inch cpslp storm sewer, with lsm type 1 backfill, as per planlinear foot2—$400.00$196.71 – $400.00May 26, 2022, Open bid tab, bidtabsheflo2103pdf ↗
36 inch cpslp storm sewer, as per planlinear foot2—$122.00$79.48 – $122.00May 26, 2022, Open bid tab, bidtabsheflo2103pdf ↗
8 inch pvc sdr-35 storm sewer, as per planlinear foot2—$105.00$30.77 – $105.00May 26, 2022, Open bid tab, bidtabsheflo2103pdf ↗
Water Works, Misc.: Water Service Line Relocated, As Per Planlinear foot2—$29.90$25.90 – $29.90Jun 4, 2025, Open bid tab, bidtabsheflo2107pdf ↗
Non-Tracking Tack Coat, 0.09 Gal/S.Y.gallon2—$5.00$5.00 – $5.50Mar 25, 2024, Open bid tab, bidtabsheflo2401pdf ↗
24 inch reinforced concrete pipe class-iii storm sewer, as per planlinear foot2—$300.00$158.01 – $300.00May 26, 2022, Open bid tab, bidtabsheflo2103pdf ↗
Pavement milling, asphalt concrete, 1-1/2 inch±square yard2—$2.75$2.75 – $3.00Mar 25, 2024, Open bid tab, bidtabsheflo2401pdf ↗
18 inch cpslp storm sewer, as per planlinear foot2—$300.00$74.93 – $300.00May 26, 2022, Open bid tab, bidtabsheflo2103pdf ↗
10 inch pvc sdr-35 storm sewer, as per planlinear foot2—$220.00$135.90 – $220.00May 26, 2022, Open bid tab, bidtabsheflo2103pdf ↗
12 inch cpslp storm sewer, as per planlinear foot2—$70.00$34.68 – $70.00May 26, 2022, Open bid tab, bidtabsheflo2103pdf ↗
9 inch non-reinforced concrete pavement, as per plansquare yard2—$87.72$87.72 – $289.28Jun 4, 2025, Open bid tab, bidtabsheflo2107pdf ↗
Yard Drain, As Per Planeach2—$1,506$957.18 – $1,506Jun 4, 2025, Open bid tab, bidtabsheflo2107pdf ↗

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.

More prices in Ohio: statewide figures.