Skip to content
Hubstake

Agency · awarded bid prices

Centerville-Washington Park District: awarded unit prices

201 winning bid prices read from 8 source documents, 2022–2026. The table lists the 40 items this agency awarded most often. Winning bids only; every row links to a bid tabulation.

Cost by state › Agencies › Centerville-Washington Park District

ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Removed, As Per Planls7$6,250$35,000$3,000 – $35,000Sep 23, 2026, Open bid tab, bidtabmotcen2602757pdf ↗
Seeding And Mulching, As Per Plansquare yard6$2.62$6.00$2.00 – $16.00Sep 23, 2026, Open bid tab, bidtabmotcen2602757pdf ↗
Stabilized Crushed Aggregatecubic yard6$84.50$82.00$67.00 – $115.00Sep 23, 2026, Open bid tab, bidtabmotcen2602757pdf ↗
4 inch concrete walksquare foot4—$10.00$7.35 – $10.00Sep 23, 2026, Open bid tab, bidtabmotcen2602757pdf ↗
Non-Tracking Tack Coat, 0.06 Gal/S.Y.gallon4—$11.00$5.25 – $11.00Sep 3, 2026, Open bid tab, bidtabmotcen2604pdf-s0 ↗
Embankment Final Grading, As Per Plancubic yard3—$25.00$25.00 – $45.00Sep 3, 2026, Open bid tab, bidtabmotcen2604pdf-s0 ↗
Court surface and court stripels3—$18,150$18,150 – $35,650Sep 3, 2026, Open bid tab, bidtabmotcen2604pdf-s0 ↗
Tennis court assembly installeach3—$4,400$4,400 – $5,000Sep 3, 2026, Open bid tab, bidtabmotcen2604pdf-s0 ↗
Construction Entrancels3—$4,000$2,500 – $4,000Sep 3, 2026, Open bid tab, bidtabmotcen2604pdf-s0 ↗
Asphalt Pavement Removedsquare yard3—$12.50$3.00 – $12.50Sep 3, 2026, Open bid tab, bidtabmotcen2604pdf-s0 ↗
Fence Removedlinear foot3—$6.00$6.00 – $13.00Sep 23, 2026, Open bid tab, bidtabmotcen2602757pdf ↗
Construction Layout Stakes And Surveying, As Per Planls3—$6,944$4,000 – $6,944Sep 7, 2022, Open bid tab, bidtabmotwas2207pdf ↗
Erosion Controleach3—$1.00$1.00Sep 3, 2026, Open bid tab, bidtabmotcen2604pdf-s0 ↗
Subgrade Compactionsquare yard3—$1.00$1.00 – $1.70Sep 3, 2026, Open bid tab, bidtabmotcen2604pdf-s0 ↗
Clearing And Grubbing, As Per Planls3—$15,500$15,500 – $30,012Sep 7, 2022, Open bid tab, bidtabmotwas2207pdf ↗
Fence, 10' Chain Link, As Per Planlinear foot2—$102.00$92.00 – $102.00Sep 3, 2026, Open bid tab, bidtabmotcen2604pdf-s0 ↗
Asphalt Concrete Intermediate Course, Type 1, (449)cubic yard2—$335.00$335.00Sep 3, 2026, Open bid tab, bidtabmotcen2604pdf-s0 ↗
Lvt Asphalt Concrete Surface Course, Pg 58-28, Virgin Asphalt Mix, As Per Plancubic yard2—$396.00$396.00Sep 3, 2026, Open bid tab, bidtabmotcen2604pdf-s0 ↗
Aggregate Base, Limestone, As Per Plancubic yard2—$68.00$61.00 – $68.00Sep 7, 2022, Open bid tab, bidtabmotwas2207pdf ↗
Type 6 Barrier Curb, As Per Planlinear foot2—$38.75$38.75 – $45.00Sep 23, 2026, Open bid tab, bidtabmotcen2602757pdf ↗
Asphalt Concrete Intermediate Course, Type 2, (449)cubic yard2—$266.00$190.00 – $266.00Sep 23, 2026, Open bid tab, bidtabmotcen2602757pdf ↗
Asphalt Concrete Surface Course, Type 1, (449), Pg64-22cubic yard2—$288.00$192.00 – $288.00Sep 23, 2026, Open bid tab, bidtabmotcen2602757pdf ↗
Handicap Symbol Markingeach2—$138.00$65.00 – $138.00Sep 23, 2026, Open bid tab, bidtabmotcen2602757pdf ↗
Excavation of subgrade and structure embankment, as per plancubic yard2—$100.00$66.00 – $100.00Sep 23, 2026, Open bid tab, bidtabmotcen2602757pdf ↗
Curb Removedlinear foot2—$6.50$6.50 – $35.00Sep 23, 2026, Open bid tab, bidtabmotcen2602757pdf ↗
Parking Lot Stall Markinglinear foot2—$1.10$1.10 – $2.10Sep 23, 2026, Open bid tab, bidtabmotcen2602757pdf ↗
Ground Mounted Support, No. 3 Postlinear foot2—$15.50$15.50 – $16.25May 6, 2025, Open bid tab, bidtabmotcen2502pdf ↗
Sign, Flat Sheeteach2—$230.00$100.00 – $230.00Sep 23, 2026, Open bid tab, bidtabmotcen2602757pdf ↗
Curb Ramp, As Per Plansquare foot2—$18.50$18.50 – $26.25Sep 7, 2022, Open bid tab, bidtabmotwas2207pdf ↗
Subgrade Compaction, As Per Plansquare yard2—$1.00$1.00 – $2.00Sep 23, 2026, Open bid tab, bidtabmotcen2602757pdf ↗
Excavation, Including Embankment Construction, As Per Plancubic yard2—$18.00$18.00 – $29.00Sep 3, 2026, Open bid tab, bidtabmotcen2604pdf-s0 ↗
Walk Removedsquare foot2—$1.00$1.00 – $2.50Sep 23, 2026, Open bid tab, bidtabmotcen2602757pdf ↗
Topsoil furnish and placedcubic yard2—$72.00$46.00 – $72.00Sep 3, 2026, Open bid tab, bidtabmotcen2604pdf-s0 ↗
Spec. light pole removeeach1—$3,300$3,300Sep 7, 2022, Open bid tab, bidtabmotwas2207pdf ↗
Spec. Water Fountaineach1—$8,500$8,500Sep 7, 2022, Open bid tab, bidtabmotwas2207pdf ↗
Handicap Symboleach1—$200.00$200.00Sep 7, 2022, Open bid tab, bidtabmotwas2207pdf ↗
Meter Pit Adjusted To Gradeeach1—$230.00$230.00Sep 7, 2022, Open bid tab, bidtabmotwas2207pdf ↗
Pull box, 725.06, 18 incheach1—$2,750$2,750Sep 7, 2022, Open bid tab, bidtabmotwas2207pdf ↗
Sanitary Cleanout Adjusted To Grade & Lid Replacedeach1—$200.00$200.00Sep 7, 2022, Open bid tab, bidtabmotwas2207pdf ↗
2-1/2 inch asphalt concrete surface course, type 1, (449), pg64-22cubic yard1—$254.00$254.00Sep 7, 2022, Open bid tab, bidtabmotwas2207pdf ↗

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.

More prices in Ohio: statewide figures.