| Spl | each | 2 | — | $230.05 | $230.05 – $4,500 | Aug 6, 2021, Open bid tab, sharonvilleeastkemperrdr ↗ |
| Center line, (4 inch) double yellow | mile | 2 | — | $6,372 | $4,400 – $6,372 | Aug 6, 2021, Open bid tab, sharonvilleeastkemperrdr ↗ |
| CURB RAMP w/ DETECTABLE WARNING | each | 2 | — | $1,511 | $475.00 – $1,511 | Aug 6, 2021, Open bid tab, sharonvilleeastkemperrdr ↗ |
| 9 inch non-reinforced concrete pavement (drive apron) | square yard | 2 | — | $79.87 | $79.87 – $96.75 | Aug 6, 2021, Open bid tab, sharonvilleeastkemperrdr ↗ |
| *Pavement Repair, Miscellaneous: Slag Stabilization | cubic yard | 2 | — | $88.97 | $61.00 – $88.97 | Aug 6, 2021, Open bid tab, sharonvilleeastkemperrdr ↗ |
| Mobilization | each | 2 | — | $7,609 | $7,609 – $25,000 | Aug 6, 2021, Open bid tab, sharonvilleeastkemperrdr ↗ |
| Lane line, 4 inch | mile | 2 | — | $3,333 | $1,100 – $3,333 | Aug 6, 2021, Open bid tab, sharonvilleeastkemperrdr ↗ |
| Proof Rolling | hour | 2 | — | $340.16 | $180.00 – $340.16 | Aug 6, 2021, Open bid tab, sharonvilleeastkemperrdr ↗ |
| Crosswalk line, 12 inch | linear foot | 2 | — | $3.32 | $3.32 – $4.00 | Aug 6, 2021, Open bid tab, sharonvilleeastkemperrdr ↗ |
| Non-Tracking Tack Coat | gallon | 2 | — | $3.85 | $3.25 – $3.85 | Aug 6, 2021, Open bid tab, sharonvilleeastkemperrdr ↗ |
| Subgrade Compaction | square yard | 2 | — | $1.26 | $1.26 – $3.00 | Aug 6, 2021, Open bid tab, sharonvilleeastkemperrdr ↗ |
| Lane Arrow | each | 2 | — | $107.00 | $100.00 – $107.00 | Aug 6, 2021, Open bid tab, sharonvilleeastkemperrdr ↗ |
| Channelizing line, 8 inch | linear foot | 2 | — | $1.71 | $1.71 – $3.18 | Aug 6, 2021, Open bid tab, sharonvilleeastkemperrdr ↗ |
| Stop Line | linear foot | 2 | — | $5.46 | $5.46 – $20.00 | Aug 6, 2021, Open bid tab, sharonvilleeastkemperrdr ↗ |
| Maintaining Traffic | ls | 2 | — | $14,194 | $14,194 – $25,000 | Aug 6, 2021, Open bid tab, sharonvilleeastkemperrdr ↗ |
| Walk Removed | square foot | 2 | — | $1.96 | $1.96 – $2.50 | Aug 6, 2021, Open bid tab, sharonvilleeastkemperrdr ↗ |
| Furnishing and laying 12 inch ductile iron pipe and fitting | linear foot | 1 | — | $560.75 | $560.75 | May 13, 2021, Open bid tab, sharonvillesharonroadrig ↗ |
| Atc V6.24 Controller, As Per Plan | each | 1 | — | $8,154 | $8,154 | May 13, 2021, Open bid tab, sharonvillesharonroadrig ↗ |
| Cctv Ip-Camera System, Dome Type, As Per Plan | each | 1 | — | $8,828 | $8,828 | May 13, 2021, Open bid tab, sharonvillesharonroadrig ↗ |
| Fiber Optic Testing, As Per Plan | ls | 1 | — | $1,788 | $1,788 | May 13, 2021, Open bid tab, sharonvillesharonroadrig ↗ |
| Splice Enclosure, In-Line | each | 1 | — | $2,063 | $2,063 | May 13, 2021, Open bid tab, sharonvillesharonroadrig ↗ |
| Fiber Termination Panel, 12 Fiber, As Per Plan | each | 1 | — | $2,008 | $2,008 | May 13, 2021, Open bid tab, sharonvillesharonroadrig ↗ |
| Fiber Optic Patch Cord, 2 Fiber | each | 1 | — | $52.00 | $52.00 | May 13, 2021, Open bid tab, sharonvillesharonroadrig ↗ |
| Drop Cable, 6 Fiber, As Per Plan | linear foot | 1 | — | $3.40 | $3.40 | May 13, 2021, Open bid tab, sharonvillesharonroadrig ↗ |
| Fan Out Kit, 6 Fiber, As Per Plan | each | 1 | — | $229.00 | $229.00 | May 13, 2021, Open bid tab, sharonvillesharonroadrig ↗ |
| Pole, With Mast Arms Tc-81.22 Design 14 And Design 13, As | each | 1 | — | $38,652 | $38,652 | May 13, 2021, Open bid tab, sharonvillesharonroadrig ↗ |
| Pole, With Mast Arms Tc-81.22 Design 13 And Design 12, As | each | 1 | — | $32,052 | $32,052 | May 13, 2021, Open bid tab, sharonvillesharonroadrig ↗ |
| Power Cable, 2 Conductor, No. 6 Awg | linear foot | 1 | — | $4.20 | $4.20 | May 13, 2021, Open bid tab, sharonvillesharonroadrig ↗ |
| Internally Illuminated Fixed Message Sign, As Per Plan | each | 1 | — | $3,008 | $3,008 | May 13, 2021, Open bid tab, sharonvillesharonroadrig ↗ |
| Photoelectric Control | each | 1 | — | $416.00 | $416.00 | May 13, 2021, Open bid tab, sharonvillesharonroadrig ↗ |
| Covering Of Sign | square foot | 1 | — | $7.00 | $7.00 | May 13, 2021, Open bid tab, sharonvillesharonroadrig ↗ |
| Conduit, 4 inch, 725.052 (schedule 80 hdpe) - addendum #1 | linear foot | 1 | — | $12.90 | $12.90 | May 13, 2021, Open bid tab, sharonvillesharonroadrig ↗ |
| Bracket Arm, 30', As Per Plan | each | 1 | — | $1,681 | $1,681 | May 13, 2021, Open bid tab, sharonvillesharonroadrig ↗ |
| Word on pavement (36 inch) "stop" | each | 1 | — | $100.00 | $100.00 | May 13, 2021, Open bid tab, sharonvillesharonroadrig ↗ |
| Construction Layout Staking | each | 1 | — | $8,250 | $8,250 | May 13, 2021, Open bid tab, sharonvillesharonroadrig ↗ |
| Manhole/Utility Box Adjusted To Grade | each | 1 | — | $250.00 | $250.00 | May 13, 2021, Open bid tab, sharonvillesharonroadrig ↗ |
| Catch basin replace, as per plan | each | 1 | — | $1,550 | $1,550 | May 13, 2021, Open bid tab, sharonvillesharonroadrig ↗ |
| Headwall (18 inch) | each | 1 | — | $525.00 | $525.00 | May 13, 2021, Open bid tab, sharonvillesharonroadrig ↗ |
| Curb Inlet, Type 3A | each | 1 | — | $2,000 | $2,000 | May 13, 2021, Open bid tab, sharonvillesharonroadrig ↗ |
| Catch Basin, Type 2-3B | each | 1 | — | $2,250 | $2,250 | May 13, 2021, Open bid tab, sharonvillesharonroadrig ↗ |