ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Bonds And Insurances, As Per Planls7$2,420$1,100$200.00 – $38,542Jul 29, 2026, Open bid tab, 0000038219 ↗
Contingency/Discretionary Allowancels4—$15,000$15,000 – $200,000Apr 28, 2022, Open bid tab, 20090002 ↗
Mobilizationls4—$5,000$3,000 – $9,000Jul 29, 2026, Open bid tab, 0000038219 ↗
Temporary Sediment And Erosion Control, As Per Planls3—$2,000$2,000 – $18,840Apr 28, 2022, Open bid tab, 20090002 ↗
Preconstruction Video Documentationls3—$500.00$500.00 – $1,400Jul 29, 2026, Open bid tab, 0000038219 ↗
Maintaining Traffic, As Per Planls3—$7,700$7,700 – $13,075Dec 13, 2024, Open bid tab, 242440 ↗
Fence, Ornamental, As Per Planlinear foot2—$213.00$180.00 – $213.00Apr 28, 2022, Open bid tab, 20090002 ↗
12 Inch X 12 Inch Cutting-In Tee W/ Long Sleeve, As Per Planeach2—$2,100$2,100 – $4,949Apr 23, 2021, Open bid tab, 20090005 ↗
24 Inch Gate Valve And Valve Box, As Per Planeach2—$23,700$20,846 – $23,700Apr 23, 2021, Open bid tab, 20090005 ↗
24 inch water main ductile iron pipe ansi class 52, boltless-restrained joint and fitting,linear foot2—$249.00$249.00 – $352.15Apr 23, 2021, Open bid tab, 20090005 ↗
24 inch water main ductile iron pipe ansi class 52, push-on joint and push-on fitting, as pelinear foot2—$134.00$134.00 – $192.23Apr 23, 2021, Open bid tab, 20090005 ↗
Valve Vault, As Per Planeach2—$44,000$42,530 – $44,000Apr 23, 2021, Open bid tab, 20090005 ↗
Blow-Off Assembly With Kupferle Hydrant, As Per Planeach2—$3,000$3,000 – $3,740Apr 23, 2021, Open bid tab, 20090005 ↗
Mobilization, As Per Planls2—$119,520$13,877 – $119,520Apr 23, 2021, Open bid tab, 20090005 ↗
Asphalt Concrete Surface Course, Type 1, (448), Pg64-22, As Per Plancubic yard2—$200.00$200.00Jul 29, 2026, Open bid tab, 0000038219 ↗
12 Inch Gate Valve And Valve Box, As Per Planeach2—$2,650$2,650 – $2,834Apr 23, 2021, Open bid tab, 20090005 ↗
Partial deep pavement repair, as per plansquare yard2—$43.00$38.00 – $43.00Jul 29, 2026, Open bid tab, 0000038219 ↗
Preconstruction Video Documentation, As Per Planls2—$1,458$550.00 – $1,458Apr 23, 2021, Open bid tab, 20090005 ↗
Type "c" pavement replace (asphalt), roadway, as per plansquare yard2—$95.00$95.00 – $167.72Apr 23, 2021, Open bid tab, 20090005 ↗
Tack Coat, Trackless Tackgallon2—$3.05$3.05Jul 29, 2026, Open bid tab, 0000038219 ↗
Pavement milling, asphalt concretesquare yard2—$1.95$1.95 – $3.30Jul 29, 2026, Open bid tab, 0000038219 ↗
Seeding And Mulching, As Per Plansquare yard2—$1.70$1.29 – $1.70Apr 28, 2022, Open bid tab, 20090002 ↗
Stop Linelinear foot2—$19.00$19.00 – $25.00Jul 29, 2026, Open bid tab, 0000038219 ↗
Center Linemile2—$5,100$5,100 – $6,500Jul 29, 2026, Open bid tab, 0000038219 ↗
Maintaining Trafficls2—$19,335$2,659 – $19,335Jul 29, 2026, Open bid tab, 0000038219 ↗
Topsoil Stripped And Stockpiledsquare yard1—$2.00$2.00Apr 23, 2021, Open bid tab, 20090005 ↗
24 Inch X 12 Inch Tapping Sleeve, Valve And Valve Boxeach1—$8,500$8,500Apr 23, 2021, Open bid tab, 20090005 ↗
24 Inch X 24 Inch Cutting-In Tee W/Long Sleeve, As Per Planeach1—$11,140$11,140Apr 23, 2021, Open bid tab, 20090005 ↗
24 Inch Line Stop, As Per Planeach1—$29,200$29,200Apr 23, 2021, Open bid tab, 20090005 ↗
Temporary water main and fittinglinear foot1—$83.00$83.00Apr 23, 2021, Open bid tab, 20090005 ↗
30 inch water main ductile iron pipe ansi class 52, boltless-restrained joint and fittinglinear foot1—$996.00$996.00Apr 23, 2021, Open bid tab, 20090005 ↗
12 inch water main ductile iron pipe ansi class 52, boltless-restrained joint and fittinglinear foot1—$95.00$95.00Apr 23, 2021, Open bid tab, 20090005 ↗
4 inch water main ductile iron pipe ansi class 52, push-on joint and push-on fittinglinear foot1—$258.00$258.00Apr 23, 2021, Open bid tab, 20090005 ↗
Transformer Pad, Concrete, As Per Planeach1—$2,900$2,900Apr 23, 2021, Open bid tab, 20090005 ↗
Pull box, misc.: 24 inch x 30 inch, as per planeach1—$800.00$800.00Apr 23, 2021, Open bid tab, 20090005 ↗
Trench, 36 Inch Deep, As Per Planlinear foot1—$3.00$3.00Apr 23, 2021, Open bid tab, 20090005 ↗
Conduit, Misc.: Pull Wirelinear foot1—$0.5$0.5Apr 23, 2021, Open bid tab, 20090005 ↗
Conduit, Jacked Or Drilled, 725.05, 4 Inch, As Per Planlinear foot1—$16.00$16.00Apr 23, 2021, Open bid tab, 20090005 ↗
Stormwater Detention Capacity With Designed Underground Chamber System, As Per Placubic foot1—$10.00$10.00Apr 23, 2021, Open bid tab, 20090005 ↗
Utility Vault, Precast Concreteeach1—$68,000$68,000Apr 23, 2021, Open bid tab, 20090005 ↗

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.