| Bonds And Insurances, As Per Plan | ls | 1 | — | $1,900 | $1,900 | May 29, 2024, Open bid tab, 24000704 ↗ |
| Pavement milling, asphalt concrete | square yard | 1 | — | $4.30 | $4.30 | May 29, 2024, Open bid tab, 24000704 ↗ |
| Asphalt Concrete Surface Course, Type 1, (448), Pg64-22 | cubic yard | 1 | — | $213.70 | $213.70 | May 29, 2024, Open bid tab, 24000704 ↗ |
| Combination Curb And Gutter, Type 2 | linear foot | 1 | — | $31.00 | $31.00 | May 29, 2024, Open bid tab, 24000704 ↗ |
| Seeding And Mulching, As Per Plan | square yard | 1 | — | $4.00 | $4.00 | May 29, 2024, Open bid tab, 24000704 ↗ |
| Curb Ramp | square foot | 1 | — | $35.00 | $35.00 | May 29, 2024, Open bid tab, 24000704 ↗ |
| Asphalt Concrete Intermediate Course, Type 2, (448) | cubic yard | 1 | — | $228.85 | $228.85 | May 29, 2024, Open bid tab, 24000704 ↗ |
| Lane Arrow | each | 1 | — | $150.00 | $150.00 | May 29, 2024, Open bid tab, 24000704 ↗ |
| Channelizing line, 8 inch | linear foot | 1 | — | $2.75 | $2.75 | May 29, 2024, Open bid tab, 24000704 ↗ |
| Crosswalk Line | linear foot | 1 | — | $9.25 | $9.25 | May 29, 2024, Open bid tab, 24000704 ↗ |
| Stop Line | linear foot | 1 | — | $9.00 | $9.00 | May 29, 2024, Open bid tab, 24000704 ↗ |
| Center Line | mile | 1 | — | $12,750 | $12,750 | May 29, 2024, Open bid tab, 24000704 ↗ |
| Maintaining Traffic | ls | 1 | — | $27,500 | $27,500 | May 29, 2024, Open bid tab, 24000704 ↗ |
| Walk Removed | square foot | 1 | — | $13.00 | $13.00 | May 29, 2024, Open bid tab, 24000704 ↗ |
| Curb And Gutter Removed | linear foot | 1 | — | $11.00 | $11.00 | May 29, 2024, Open bid tab, 24000704 ↗ |
| Tack Coat | gallon | 1 | — | $3.75 | $3.75 | May 29, 2024, Open bid tab, 24000704 ↗ |
| Mobilization | ls | 1 | — | $10,000 | $10,000 | May 29, 2024, Open bid tab, 24000704 ↗ |