ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Erosion Control, As Per Planls4—$500.00$500.00 – $1,800Jan 10, 2024, Open bid tab, 190886 ↗
Mobilizationls4—$5,000$2,500 – $5,000Jan 10, 2024, Open bid tab, 190886 ↗
Clearing and Grubbingls4—$500.00$500.00 – $2,800Jan 10, 2024, Open bid tab, 190886 ↗
Drilled Shafts, 30 Inch Diameter, Plug Piles, As Per Planlinear foot3—$95.00$95.00 – $236.38Jan 10, 2024, Open bid tab, 190886 ↗
Drilled Shafts, 24 Inch Diameter, Above Bedrock, As Per Planlinear foot3—$95.00$95.00 – $200.00Jan 10, 2024, Open bid tab, 190886 ↗
STEEL PILES, MISC.: SOLDIER PILES, HP 10x42linear foot3—$33.00$33.00Jan 10, 2024, Open bid tab, 190886 ↗
Asphalt Concrete Base, Pg64-28cubic yard3—$220.00$220.00 – $295.00Jan 10, 2024, Open bid tab, 190886 ↗
Bonds And Insurances, As Per Planls3—$2,500$2,000 – $2,500Jan 10, 2024, Open bid tab, 190886 ↗
Sawing and seal asphalt concrete pavement jointlinear foot3—$35.00$35.00Jan 10, 2024, Open bid tab, 190886 ↗
Drilled Shafts, 24 Inch Diameter, Into Bedrock, As Per Planlinear foot3—$105.00$105.00 – $144.46Jan 10, 2024, Open bid tab, 190886 ↗
Seeding And Mulching, Class 1square yard3—$20.00$20.00Jan 10, 2024, Open bid tab, 190886 ↗
Proof Rollinghour3—$200.00$200.00Jan 10, 2024, Open bid tab, 190886 ↗
Pavement Removedsquare yard3—$3.50$3.50Jan 10, 2024, Open bid tab, 190886 ↗
Asphalt Concrete Surface Course, Type 1, (448), Pg64-22cubic yard3—$309.00$309.00 – $534.00Jan 10, 2024, Open bid tab, 190886 ↗
Maintaining Traffic, As Per Planls3—$500.00$500.00Jan 10, 2024, Open bid tab, 190886 ↗
Construction Layout Stakes And Surveyingls3—$500.00$500.00Jan 10, 2024, Open bid tab, 190886 ↗
Asphalt Concrete Intermediate Course, Type 2, (448)cubic yard3—$298.00$298.00 – $523.00Jan 10, 2024, Open bid tab, 190886 ↗
Subgrade Compactionsquare yard3—$3.00$3.00Jan 10, 2024, Open bid tab, 190886 ↗
Aggregate Basecubic yard3—$65.00$65.00Jan 10, 2024, Open bid tab, 190886 ↗
Embankmentcubic yard3—$25.00$25.00Jan 10, 2024, Open bid tab, 190886 ↗
Topsoil furnish and placedcubic yard3—$50.00$50.00Jan 10, 2024, Open bid tab, 190886 ↗
Tack Coatgallon3—$116.50$116.50 – $154.00Jan 10, 2024, Open bid tab, 190886 ↗
Excavationcubic yard3—$25.00$25.00Jan 10, 2024, Open bid tab, 190886 ↗
General Constructionls1—$87,000$87,000Jan 15, 2021, Open bid tab, 190420 ↗
Type "c" pavement replace (asphalt), roadway, as per plansquare yard1—$50.00$50.00Jan 15, 2021, Open bid tab, 190420 ↗
Full deep pavement sawinglinear foot1—$14.00$14.00Jan 15, 2021, Open bid tab, 190420 ↗
Anchor Assembly, Type Eeach1—$1,400$1,400Jan 15, 2021, Open bid tab, 190420 ↗
_ Ditch Cleanoutlinear foot1—$8.33$8.33Jan 15, 2021, Open bid tab, 190420 ↗
Guardrail, Type Mgslinear foot1—$26.00$26.00Jan 15, 2021, Open bid tab, 190420 ↗
Headwall Removedeach1—$250.00$250.00Jan 15, 2021, Open bid tab, 190420 ↗
24 inch storm sewer, as per planlinear foot1—$95.00$95.00Jan 15, 2021, Open bid tab, 190420 ↗
Concrete Masonrycubic yard1—$300.00$300.00Jan 15, 2021, Open bid tab, 190420 ↗
Pipe removed, 24 inch and underlinear foot1—$12.50$12.50Jan 15, 2021, Open bid tab, 190420 ↗
Low Strength Mortar Backfillcubic yard1—$150.00$150.00Jan 10, 2024, Open bid tab, 190886 ↗

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.

More prices in Ohio: statewide figures.