ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Catch Basin Removedeach2—$214.61$214.61 – $400.00Apr 21, 2022, Open bid tab, bidtabharken2101pdf ↗
Pipe removed, 24 inch and underlinear foot2—$9.68$5.00 – $9.68Apr 21, 2022, Open bid tab, bidtabharken2101pdf ↗
Erosion Controleach2—$1.00$1.00Apr 21, 2022, Open bid tab, bidtabharken2101pdf ↗
Low Strength Mortar Backfillcubic yard2—$127.45$127.45 – $195.00Apr 21, 2022, Open bid tab, bidtabharken2101pdf ↗
Curb Removedlinear foot2—$2.47$2.47 – $4.00Apr 21, 2022, Open bid tab, bidtabharken2101pdf ↗
Clearing And Grubbing, As Per Planls2—$14,015$500.00 – $14,015Apr 21, 2022, Open bid tab, bidtabharken2101pdf ↗
Maintaining Trafficls2—$47,795$4,000 – $47,795Apr 21, 2022, Open bid tab, bidtabharken2101pdf ↗
Aggregate Base, As Per Plancubic yard2—$86.62$30.00 – $86.62Apr 21, 2022, Open bid tab, bidtabharken2101pdf ↗
Walk Removedsquare foot2—$1.02$1.02 – $1.50Apr 21, 2022, Open bid tab, bidtabharken2101pdf ↗
Removed, As Per Planls2—$42,796$500.00 – $42,796Apr 21, 2022, Open bid tab, bidtabharken2101pdf ↗
Water Service Branch, As Per Planlinear foot1—$27.06$27.06Apr 21, 2022, Open bid tab, bidtabharken2101pdf ↗
Remove of ground mounted posteach1—$58.44$58.44Apr 21, 2022, Open bid tab, bidtabharken2101pdf ↗
Remove of ground mount sign and reerectioneach1—$58.44$58.44Apr 21, 2022, Open bid tab, bidtabharken2101pdf ↗
6 inch storm sewer lateral, pvc sdr-35linear foot1—$71.44$71.44Apr 21, 2022, Open bid tab, bidtabharken2101pdf ↗
24 inch cpslp storm sewerlinear foot1—$96.00$96.00Apr 21, 2022, Open bid tab, bidtabharken2101pdf ↗
1-3/4 inch asphalt concrete intermediate course, type 2, pg 64-22 (449)cubic yard1—$249.00$249.00Apr 21, 2022, Open bid tab, bidtabharken2101pdf ↗
Storm Storage Vault Removed, As Per Planls1—$2,480$2,480Apr 21, 2022, Open bid tab, bidtabharken2101pdf ↗
6 inch conduit, type b, 707.45, storm laterallinear foot1—$20.00$20.00Jun 30, 2020, Open bid tab, bidtabharfor1902pdf ↗
Concrete Walk Replaced, In Kindsquare foot1—$10.00$10.00Jun 30, 2020, Open bid tab, bidtabharfor1902pdf ↗
Type 2 Storm Cleanouteach1—$140.24$140.24Apr 21, 2022, Open bid tab, bidtabharken2101pdf ↗
1-1/4 inch asphalt concrete surface course, type 1, (449)cubic yard1—$311.26$311.26Apr 21, 2022, Open bid tab, bidtabharken2101pdf ↗
9 inch asphalt concrete base, pg64-22cubic yard1—$300.00$300.00Jun 30, 2020, Open bid tab, bidtabharfor1902pdf ↗
Type 6 Barrier Curblinear foot1—$15.37$15.37Apr 21, 2022, Open bid tab, bidtabharken2101pdf ↗
10 inch storm sewer, as per planlinear foot1—$100.00$100.00Jun 30, 2020, Open bid tab, bidtabharfor1902pdf ↗
Type 2 Storm Cleanout, As Per Planeach1—$100.00$100.00Jun 30, 2020, Open bid tab, bidtabharfor1902pdf ↗
Non-Tracking Tack Coat, 0.09 Gal/S.Y.gallon1—$4.00$4.00Jun 30, 2020, Open bid tab, bidtabharfor1902pdf ↗
15 inch cpslp storm sewerlinear foot1—$60.36$60.36Apr 21, 2022, Open bid tab, bidtabharken2101pdf ↗
12 inch cpslp storm sewerlinear foot1—$52.20$52.20Apr 21, 2022, Open bid tab, bidtabharken2101pdf ↗
Type 2-3 Catch Basineach1—$1,250$1,250Jun 30, 2020, Open bid tab, bidtabharfor1902pdf ↗
15 inch cpslp storm sewer, as per planlinear foot1—$55.00$55.00Jun 30, 2020, Open bid tab, bidtabharfor1902pdf ↗
30 inch cpslp storm sewer, as per planlinear foot1—$95.00$95.00Jun 30, 2020, Open bid tab, bidtabharfor1902pdf ↗
24 inch cpslp storm sewer, as per planlinear foot1—$75.00$75.00Jun 30, 2020, Open bid tab, bidtabharfor1902pdf ↗
18 inch cpslp storm sewer, as per planlinear foot1—$60.00$60.00Jun 30, 2020, Open bid tab, bidtabharfor1902pdf ↗
12 inch cpslp storm sewer, as per planlinear foot1—$45.00$45.00Jun 30, 2020, Open bid tab, bidtabharfor1902pdf ↗
Type 3 Storm Sewer Manhole, As Per Planeach1—$1,400$1,400Jun 30, 2020, Open bid tab, bidtabharfor1902pdf ↗
Yard Drain, As Per Planeach1—$150.00$150.00Jun 30, 2020, Open bid tab, bidtabharfor1902pdf ↗
Type 2-2B Catch Basin, As Per Planeach1—$850.00$850.00Jun 30, 2020, Open bid tab, bidtabharfor1902pdf ↗
Concrete Curb Rampsquare foot1—$7.69$7.69Apr 21, 2022, Open bid tab, bidtabharken2101pdf ↗
Asphalt Concrete Surface Course, Type 1, Pg. 64-22 (448)cubic yard1—$325.00$325.00Jun 30, 2020, Open bid tab, bidtabharfor1902pdf ↗
8 inch storm sewer, as per planlinear foot1—$43.50$43.50Jun 30, 2020, Open bid tab, bidtabharfor1902pdf ↗