| Seeding And Mulching, Class 1, As Per Plan | square yard | 5 | $3.00 | $5.00 | $3.00 – $5.00 | Aug 20, 2026, Open bid tab, bidtabclebet2502pdf ↗ |
| Clearing And Grubbing, As Per Plan | ls | 5 | $2,500 | $5,000 | $500.00 – $20,000 | Aug 20, 2026, Open bid tab, bidtabclebet2502pdf ↗ |
| Maintaining Traffic | ls | 5 | $5,000 | $5,500 | $2,000 – $19,000 | Aug 20, 2026, Open bid tab, bidtabclebet2502pdf ↗ |
| Removed, As Per Plan | ls | 5 | $3,500 | $3,500 | $1,500 – $20,000 | Aug 20, 2026, Open bid tab, bidtabclebet2502pdf ↗ |
| Construction Layout Stakes And Surveying, As Per Plan | ls | 4 | — | $1,780 | $1,500 – $5,000 | Aug 20, 2026, Open bid tab, bidtabclebet2502pdf ↗ |
| Water Works, Misc.: Water Service Line Relocated, As Per Plan | linear foot | 3 | — | $50.00 | $10.00 – $50.00 | Jun 13, 2023, Open bid tab, bidtabclebet2103pdf ↗ |
| Pipe removed, 24 inch and under | linear foot | 3 | — | $30.00 | $20.00 – $30.00 | Aug 20, 2026, Open bid tab, bidtabclebet2502pdf ↗ |
| 8 inch conduit, type b, 707.45, as per plan | linear foot | 3 | — | $30.00 | $5.00 – $30.00 | Jun 13, 2023, Open bid tab, bidtabclebet2103pdf ↗ |
| 6 inch conduit, type b, 707.45, as per plan | linear foot | 3 | — | $25.00 | $4.00 – $25.00 | Jun 13, 2023, Open bid tab, bidtabclebet2103pdf ↗ |
| 4 inch conduit, type b, 707.45, as per plan | linear foot | 3 | — | $20.00 | $3.00 – $20.00 | Jun 13, 2023, Open bid tab, bidtabclebet2103pdf ↗ |
| Asphalt Concrete Base, Pg64-22 | cubic yard | 3 | — | $190.00 | $152.53 – $200.00 | Jun 13, 2023, Open bid tab, bidtabclebet2103pdf ↗ |
| Remove of ground mounted sign and reerection | each | 3 | — | $100.00 | $100.00 | Aug 20, 2026, Open bid tab, bidtabclebet2502pdf ↗ |
| Aggregate Base, As Per Plan | cubic yard | 3 | — | $100.00 | $45.00 – $100.00 | Aug 20, 2026, Open bid tab, bidtabclebet2502pdf ↗ |
| Subgrade Compaction, As Per Plan | square yard | 3 | — | $10.00 | $2.00 – $10.00 | Aug 20, 2026, Open bid tab, bidtabclebet2502pdf ↗ |
| Walk Removed | square foot | 3 | — | $5.00 | $1.00 – $5.00 | Jun 13, 2023, Open bid tab, bidtabclebet2103pdf ↗ |
| Type d - construct a 12 inch reinforced concrete slab, as per plan | square yard | 2 | — | $250.00 | $200.00 – $250.00 | Aug 20, 2026, Open bid tab, bidtabclebet2502pdf ↗ |
| Structure Removed | ls | 2 | — | $5,000 | $3,000 – $5,000 | Aug 20, 2026, Open bid tab, bidtabclebet2502pdf ↗ |
| Water Works, Misc.: Water Main Reconnected, As Per Plan | each | 2 | — | $2,500 | $0.01 – $2,500 | Jun 13, 2023, Open bid tab, bidtabclebet2103pdf ↗ |
| Water Works, Misc.: Water Main Relocated, As Per Plan | linear foot | 2 | — | $200.00 | $0.01 – $200.00 | Jun 13, 2023, Open bid tab, bidtabclebet2103pdf ↗ |
| Type 2-3 Catch Basin, As Per Plan | each | 2 | — | $3,000 | $2,500 – $3,000 | Jun 13, 2023, Open bid tab, bidtabclebet2103pdf ↗ |
| 18 inch storm sewer, as per plan | linear foot | 2 | — | $80.00 | $80.00 – $100.00 | Jun 13, 2023, Open bid tab, bidtabclebet2103pdf ↗ |
| Type 2-2B Catch Basin, As Per Plan | each | 2 | — | $2,700 | $1,000 – $2,700 | Jun 13, 2023, Open bid tab, bidtabclebet2103pdf ↗ |
| 24 inch storm sewer, reinforced concrete pipe, as per plan | linear foot | 2 | — | $150.00 | $126.00 – $150.00 | Jun 13, 2023, Open bid tab, bidtabclebet2103pdf ↗ |
| 8 inch storm sewer, as per plan | linear foot | 2 | — | $100.00 | $25.00 – $100.00 | Jun 13, 2023, Open bid tab, bidtabclebet2103pdf ↗ |
| 6 inch storm sewer, as per plan | linear foot | 2 | — | $50.00 | $15.00 – $50.00 | Jun 13, 2023, Open bid tab, bidtabclebet2103pdf ↗ |
| 6 inch non-reinforced concrete pavement, as per plan | square yard | 2 | — | $70.00 | $70.00 – $90.00 | Jul 6, 2022, Open bid tab, bidtabclebet2002pdf ↗ |
| 4 inch concrete walk | square foot | 2 | — | $15.00 | $5.00 – $15.00 | Jun 13, 2023, Open bid tab, bidtabclebet2103pdf ↗ |
| 8 inch conduit, type b, 707.45, storm repair | linear foot | 2 | — | $35.00 | $30.00 – $35.00 | Aug 20, 2026, Open bid tab, bidtabclebet2502pdf ↗ |
| 6 inch conduit, type b, 707.45, storm repair | linear foot | 2 | — | $30.00 | $25.00 – $30.00 | Aug 20, 2026, Open bid tab, bidtabclebet2502pdf ↗ |
| 4 inch conduit, type b, 707.45, storm repair | linear foot | 2 | — | $25.00 | $20.00 – $25.00 | Aug 20, 2026, Open bid tab, bidtabclebet2502pdf ↗ |
| 15 inch storm sewer, as per plan | linear foot | 2 | — | $70.00 | $69.00 – $70.00 | Jun 13, 2023, Open bid tab, bidtabclebet2103pdf ↗ |
| 12 inch storm sewer, as per plan | linear foot | 2 | — | $60.00 | $60.00 – $64.00 | Jun 13, 2023, Open bid tab, bidtabclebet2103pdf ↗ |
| Valve Box Adjusted To Grade | each | 2 | — | $50.00 | $50.00 | Feb 4, 2021, Open bid tab, bidtabclebet1906pdf ↗ |
| Non-Tracking Tack Coat, 0.06 Gal/S.Y. | gallon | 2 | — | $10.00 | $5.00 – $10.00 | Aug 20, 2026, Open bid tab, bidtabclebet2502pdf ↗ |
| Curb And Gutter Removed | linear foot | 2 | — | $10.00 | $5.00 – $10.00 | Jun 13, 2023, Open bid tab, bidtabclebet2103pdf ↗ |
| Aggregate Base | cubic yard | 2 | — | $50.00 | $50.00 – $80.00 | Jun 13, 2023, Open bid tab, bidtabclebet2103pdf ↗ |
| Embankment | cubic yard | 2 | — | $50.00 | $50.00 | Aug 20, 2026, Open bid tab, bidtabclebet2502pdf ↗ |
| Unclassified Excavation | ls | 2 | — | $5,000 | $5,000 | Aug 20, 2026, Open bid tab, bidtabclebet2502pdf ↗ |
| Excavation | cubic yard | 2 | — | $35.00 | $35.00 – $50.00 | Aug 20, 2026, Open bid tab, bidtabclebet2502pdf ↗ |
| Redi-Rock Retaining Wall | ls | 1 | — | $50,000 | $50,000 | Aug 20, 2026, Open bid tab, bidtabclebet2502pdf ↗ |