49 winning bid prices read from 1 source documents, 2024. The table lists the 40 items this agency awarded most often. Winning bids only; every row links to a bid tabulation.

Cost by state › Agencies › City of Tipp City

ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Reflective Cracking Pavement Interlayerlinear foot1—$35.00$35.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
Valve Closed And Valve Box Filled With Concreteeach1—$295.00$295.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
Modular retaining wall for private underground water service branch install, as per plansquare foot1—$72.00$72.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
Concrete steps, type b, for private underground water service branch install, as per planlinear foot1—$166.00$166.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
4 inch concrete walk for private underground water service branch install, as per plansquare foot1—$15.00$15.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
Non-Tracking Tack Coat, Surface Course, Applied @ 0.06 Gal./S.Y.gallon1—$10.80$10.80Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
4 inch pavement milling, asphalt concretesquare yard1—$31.85$31.85Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
8 inch d.i.p. class-52 water main, as per planlinear foot1—$135.00$135.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
Meter Pit Removedeach1—$375.00$375.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
Type 3 Storm Manholeeach1—$3,640$3,640Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
3/4 inch type k copper water service branch, as per planlinear foot1—$84.00$84.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
10 inchx8 inch tapping sleeve and valveeach1—$7,250$7,250Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
4 inch sanitary sewer lateral repair, as per planlinear foot1—$67.00$67.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
Barrier Curb Removedlinear foot1—$8.00$8.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
Type 6 Barrier Curb, As Per Planlinear foot1—$45.00$45.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
Interior Private Water Service, As Per Planlinear foot1—$77.00$77.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
8 inch non-reinforced concrete pavement, as per plansquare yard1—$116.00$116.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
Asphalt Concrete Intermediate Course, Type 2, (449)cubic yard1—$337.00$337.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
Asphalt Concrete Surface Course, Type 1, (449), Pg64-22cubic yard1—$442.00$442.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
Cut And Plug, Type 2, As Per Planeach1—$1,775$1,775Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
6 inch non-reinforced concrete pavement, as per plansquare yard1—$225.00$225.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
Private Underground Water Service Branch, As Per Planlinear foot1—$71.00$71.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
6 inch line stop, as per planeach1—$7,100$7,100Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
1 inch type k copper water service branch, as per planlinear foot1—$375.00$375.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
Seeding And Mulching, Class 1, As Per Plansquare yard1—$7.10$7.10Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
Construction Layout Stakes And Surveying, As Per Planls1—$4,150$4,150Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
6 inch fire hydrant assembly, as per planeach1—$8,950$8,950Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
Curb And Gutter Replaced (In-Kind)linear foot1—$52.00$52.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
Valve Box Removedeach1—$275.00$275.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
8 inch conduit, type b, 707.45, as per planlinear foot1—$27.00$27.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
6 inch conduit, type b, 707.45, as per planlinear foot1—$26.00$26.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
4 inch conduit, type b, 707.45, as per planlinear foot1—$25.00$25.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
Clearing And Grubbing, As Per Planls1—$22,995$22,995Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
Center Linemile1—$129,855$129,855Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
Remove of ground mounted sign and reerectioneach1—$300.00$300.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
Maintaining Trafficls1—$7,750$7,750Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
Curb Ramp, As Per Plansquare foot1—$32.00$32.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
4 inch concrete walk, as per plansquare foot1—$9.75$9.75Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
Stabilized Crushed Aggregatecubic yard1—$90.00$90.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗
Aggregate Base, As Per Plancubic yard1—$66.00$66.00Feb 22, 2024, Open bid tab, bidtabmiatci2302pdf ↗

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.