| Erosion Control Mat, Type C, As Per Plan | square yard | 1 | — | $1.70 | $1.70 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| 6 inch conduit, type f, 707.45 for underdrain outlets | linear foot | 1 | — | $16.50 | $16.50 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| 6 Inch Unclassified Pipe Underdrain With Geotextile Fabric | linear foot | 1 | — | $12.25 | $12.25 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Temporary Armor Stone, 4 To 6 Ton Stone, As Directed By The Engineer | cubic yard | 1 | — | $146.00 | $146.00 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Preconstruction Video Documentation, As Per Plan | ls | 1 | — | $2,510 | $2,510 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Fence Misc: Temporary Safety Fence - 4' Plastic | linear foot | 1 | — | $4.10 | $4.10 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Bonds And Insurances, As Per Plan | ls | 1 | — | $12,000 | $12,000 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Storm Water Pollution Prevention Inspections | ls | 1 | — | $2,000 | $2,000 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Topsoil Stockpiled | cubic yard | 1 | — | $5.51 | $5.51 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Commercial Fertilizer | ton | 1 | — | $987.00 | $987.00 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Stump removed, 48 inch size | each | 1 | — | $210.00 | $210.00 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Stump removed, 30 inch size | each | 1 | — | $160.00 | $160.00 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Stump removed, 18 inch size | each | 1 | — | $85.00 | $85.00 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Tree removed, 48 inch size | each | 1 | — | $460.00 | $460.00 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Stormwater Pollution Prevention Inspection Software | ls | 1 | — | $1,300 | $1,300 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Tree Removed, 18 Inch Size | each | 1 | — | $185.00 | $185.00 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Tree Removed, 30 Inch Size | each | 1 | — | $360.00 | $360.00 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Fence Removed | linear foot | 1 | — | $6.00 | $6.00 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Embankment, As Per Plan | cubic yard | 1 | — | $1.00 | $1.00 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Manhole Abandoned | each | 1 | — | $750.00 | $750.00 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Soil Analysis Test | each | 1 | — | $85.00 | $85.00 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Placing Stockpiled Topsoil | cubic yard | 1 | — | $8.00 | $8.00 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Manhole Removed | each | 1 | — | $650.00 | $650.00 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Construction Layout Stakes And Surveying | ls | 1 | — | $1,200 | $1,200 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Excavation, As Per Plan | cubic yard | 1 | — | $1.00 | $1.00 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Stormwater Pollution Prevention Plan | ls | 1 | — | $7,500 | $7,500 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Catch Basin Removed | each | 1 | — | $650.00 | $650.00 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Pipe removed, 24 inch and under | linear foot | 1 | — | $3.30 | $3.30 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Erosion Control | each | 1 | — | $3.00 | $3.00 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Maintaining Traffic | ls | 1 | — | $1,400 | $1,400 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Topsoil furnish and placed | cubic yard | 1 | — | $19.00 | $19.00 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Water | thousand gallons | 1 | — | $4,400 | $4,400 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Mobilization | ls | 1 | — | $4,000 | $4,000 | Feb 11, 2021, Open bid tab, 170567 ↗ |
| Clearing and Grubbing | ls | 1 | — | $6,960 | $6,960 | Feb 11, 2021, Open bid tab, 170567 ↗ |