Agency · awarded bid prices

Village of Lewisburg: awarded unit prices

28 winning bid prices read from 2 source documents, 2025–2026. The table lists the 26 items this agency awarded most often. Winning bids only; every row links to a bid tabulation.

Cost by state › Agencies › Village of Lewisburg

ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Asphalt Concrete Surface Course, Type 1, (449), Pg64-22cubic yard2—$180.00$180.00 – $300.00Mar 3, 2026, Open bid tab, bidtabprelew2502pdf ↗
Maintaining Trafficls2—$4,500$4,500 – $7,000Mar 3, 2026, Open bid tab, bidtabprelew2502pdf ↗
Yellow-paint curblinear foot1—$1.05$1.05Mar 3, 2026, Open bid tab, bidtabprelew2502pdf ↗
Spec. Asphalt Cold Patchcubic yard1—$300.00$300.00Sep 24, 2025, Open bid tab, bidtabprelew2406pdf ↗
12 inch awwa c-900 dr-18 water main, as per planlinear foot1—$80.00$80.00Sep 24, 2025, Open bid tab, bidtabprelew2406pdf ↗
Pavement Repair, As Per Plansquare yard1—$71.00$71.00Mar 3, 2026, Open bid tab, bidtabprelew2502pdf ↗
Pavement milling, asphalt concrete, 1-1/2 inch±square yard1—$1.60$1.60Mar 3, 2026, Open bid tab, bidtabprelew2502pdf ↗
Stop line, 24 inch, type 1linear foot1—$8.00$8.00Mar 3, 2026, Open bid tab, bidtabprelew2502pdf ↗
Non-Tracking Tack Coat, 0.10 Gal/S.Y.gallon1—$1.00$1.00Mar 3, 2026, Open bid tab, bidtabprelew2502pdf ↗
Crosswalk line, 12 inch, type 1linear foot1—$7.00$7.00Mar 3, 2026, Open bid tab, bidtabprelew2502pdf ↗
Asphalt Concrete Base, Pg64-22, (449)cubic yard1—$800.00$800.00Sep 24, 2025, Open bid tab, bidtabprelew2406pdf ↗
Asphalt Concrete Intermediate Course, Type 2, (449)cubic yard1—$300.00$300.00Sep 24, 2025, Open bid tab, bidtabprelew2406pdf ↗
Construction Layout Stakes And Surveying, As Per Planls1—$2,000$2,000Sep 24, 2025, Open bid tab, bidtabprelew2406pdf ↗
Erosion Controleach1—$1.00$1.00Sep 24, 2025, Open bid tab, bidtabprelew2406pdf ↗
Seeding And Mulching, As Per Plansquare yard1—$1.50$1.50Sep 24, 2025, Open bid tab, bidtabprelew2406pdf ↗
6 inch fire hydrant assembly, as per planeach1—$9,500$9,500Sep 24, 2025, Open bid tab, bidtabprelew2406pdf ↗
12 inchx12 inch tapping sleeve and valveeach1—$5,500$5,500Sep 24, 2025, Open bid tab, bidtabprelew2406pdf ↗
Curb And Gutter Replaced (In-Kind)linear foot1—$200.00$200.00Sep 24, 2025, Open bid tab, bidtabprelew2406pdf ↗
8 inch conduit, type b, 707.45, as per planlinear foot1—$22.00$22.00Sep 24, 2025, Open bid tab, bidtabprelew2406pdf ↗
6 inch conduit, type b, 707.45, as per planlinear foot1—$20.00$20.00Sep 24, 2025, Open bid tab, bidtabprelew2406pdf ↗
4 inch conduit, type b, 707.45, as per planlinear foot1—$20.00$20.00Sep 24, 2025, Open bid tab, bidtabprelew2406pdf ↗
Manhole Adjusted To Gradeeach1—$1,400$1,400Mar 3, 2026, Open bid tab, bidtabprelew2502pdf ↗
Non-Tracking Tack Coat, 0.06 Gal/S.Y.gallon1—$50.00$50.00Sep 24, 2025, Open bid tab, bidtabprelew2406pdf ↗
Curb And Gutter Removedlinear foot1—$50.00$50.00Sep 24, 2025, Open bid tab, bidtabprelew2406pdf ↗
Removed, As Per Planls1—$1,500$1,500Sep 24, 2025, Open bid tab, bidtabprelew2406pdf ↗
Aggregate Basecubic yard1—$250.00$250.00Sep 24, 2025, Open bid tab, bidtabprelew2406pdf ↗

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.

More prices in Ohio: statewide figures.