| Maintaining Traffic | ls | 7 | $4,700 | $2,500 | $2,394 – $38,850 | Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗ |
| Seeding And Mulching, Class 1, As Per Plan | square yard | 6 | $4.62 | $12.00 | $3.00 – $12.00 | Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗ |
| Removed, As Per Plan | ls | 6 | $7,268 | $997.00 | $997.00 – $36,750 | Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗ |
| Clearing And Grubbing, As Per Plan | ls | 5 | $2,700 | $6,000 | $1,000 – $11,950 | Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗ |
| 4 inch concrete walk | square foot | 4 | — | $21.00 | $5.50 – $21.00 | Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗ |
| Erosion Control | each | 4 | — | $1.00 | $1.00 | Sep 18, 2023, Open bid tab, bidtabmotbro2218pdf ↗ |
| Valve Box Removed | each | 4 | — | $320.00 | $96.00 – $320.00 | Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗ |
| Aggregate Base, As Per Plan | cubic yard | 4 | — | $95.00 | $49.00 – $95.00 | Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗ |
| 8 inch gate valve | each | 4 | — | $2,395 | $1,675 – $2,395 | Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗ |
| Fire Hydrant Removed And Stored On Site, As Per Plan | each | 3 | — | $995.00 | $192.00 – $995.00 | Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗ |
| 6 inch fire hydrant assembly, as per plan | each | 3 | — | $6,685 | $6,200 – $9,275 | Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗ |
| Subgrade Compaction | square yard | 3 | — | $19.00 | $1.00 – $19.00 | Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗ |
| Non-Tracking Tack Coat, 0.06 Gal/S.Y. | gallon | 3 | — | $15.00 | $11.50 – $15.00 | Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗ |
| Walk Removed | square foot | 3 | — | $3.00 | $0.95 – $3.00 | Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗ |
| Curb And Gutter Removed | linear foot | 3 | — | $10.00 | $10.00 – $34.00 | Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗ |
| 10 inch dip class-51 (min.) water main, as per plan | linear foot | 2 | — | $392.00 | $183.50 – $392.00 | Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗ |
| 8 inch dip class-51 (min.) water main, as per plan | linear foot | 2 | — | $133.00 | $131.00 – $133.00 | Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗ |
| 4 inch dip class-51 (min.) water main, as per plan | linear foot | 2 | — | $270.00 | $210.00 – $270.00 | Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗ |
| Asphalt Concrete Intermediate Course, Type 2, (449) | cubic yard | 2 | — | $365.00 | $365.00 – $432.00 | Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗ |
| Asphalt Concrete Surface Course, Type 1, (449), Pg64-22 | cubic yard | 2 | — | $390.00 | $390.00 – $900.00 | Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗ |
| 1-1/4 inch asphalt concrete surface course, type 1, (449), pg64-22 | cubic yard | 2 | — | $400.00 | $355.00 – $400.00 | Nov 1, 2022, Open bid tab, bidtabmotbro2209pdf ↗ |
| 2-3/4 inch asphalt concrete intermediate course, type 2, (449) | cubic yard | 2 | — | $390.00 | $350.00 – $390.00 | Nov 1, 2022, Open bid tab, bidtabmotbro2209pdf ↗ |
| 1 inch type k copper water service branch, as per plan | linear foot | 2 | — | $72.00 | $65.00 – $72.00 | Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗ |
| 8 inch conduit, type b, 707.45, storm repair, as per plan | linear foot | 2 | — | $44.00 | $15.00 – $44.00 | Sep 18, 2023, Open bid tab, bidtabmotbro2218pdf ↗ |
| 6 inch conduit, type b, 707.45, storm repair, as per plan | linear foot | 2 | — | $34.00 | $15.00 – $34.00 | Sep 18, 2023, Open bid tab, bidtabmotbro2218pdf ↗ |
| 4 inch conduit, type b, 707.45, storm repair, as per plan | linear foot | 2 | — | $23.75 | $15.00 – $23.75 | Sep 18, 2023, Open bid tab, bidtabmotbro2218pdf ↗ |
| 4 inch temporary line stop, as per plan | each | 2 | — | $7,000 | $7,000 – $9,500 | Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗ |
| 1 inch water service branch, as per plan | linear foot | 2 | — | $56.00 | $56.00 – $59.00 | Sep 9, 2021, Open bid tab, bidtabmotbro1901pdf ↗ |
| 8 inch conduit, type b, 707.45, storm repair | linear foot | 2 | — | $9.00 | $9.00 – $25.00 | Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗ |
| 6 inch conduit, type b, 707.45, storm repair | linear foot | 2 | — | $5.00 | $5.00 – $20.00 | Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗ |
| 4 inch conduit, type b, 707.45, storm repair | linear foot | 2 | — | $2.00 | $2.00 – $15.00 | Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗ |
| Special - Bollard | each | 2 | — | $425.00 | $425.00 – $1,600 | Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗ |
| 8 inch conduit, type b, 707.45, as per plan | linear foot | 2 | — | $35.00 | $22.00 – $35.00 | Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗ |
| 6 inch conduit, type b, 707.45, as per plan | linear foot | 2 | — | $35.00 | $16.00 – $35.00 | Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗ |
| Curb Ramp | square foot | 2 | — | $12.50 | $12.50 – $13.35 | Sep 18, 2023, Open bid tab, bidtabmotbro2218pdf ↗ |
| Stop Line | linear foot | 2 | — | $11.25 | $10.80 – $11.25 | Oct 31, 2022, Open bid tab, bidtabmotbro2009pdf ↗ |
| Center Line | mile | 2 | — | $16,060 | $12,960 – $16,060 | Oct 31, 2022, Open bid tab, bidtabmotbro2009pdf ↗ |
| Valve Box Adjusted To Grade | each | 2 | — | $250.00 | $175.00 – $250.00 | Sep 18, 2023, Open bid tab, bidtabmotbro2218pdf ↗ |
| Combination Curb And Gutter, Type 2, As Per Plan | linear foot | 2 | — | $65.00 | $24.75 – $65.00 | Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗ |
| Stabilized Crushed Aggregate | cubic yard | 2 | — | $95.00 | $52.00 – $95.00 | Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗ |