Skip to content
Hubstake

Agency · awarded bid prices

City of Brookville: awarded unit prices

246 winning bid prices read from 8 source documents, 2021–2026. The table lists the 40 items this agency awarded most often. Winning bids only; every row links to a bid tabulation.

Cost by state › Agencies › City of Brookville

ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Maintaining Trafficls7$4,700$2,500$2,394 – $38,850Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗
Seeding And Mulching, Class 1, As Per Plansquare yard6$4.62$12.00$3.00 – $12.00Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗
Removed, As Per Planls6$7,268$997.00$997.00 – $36,750Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗
Clearing And Grubbing, As Per Planls5$2,700$6,000$1,000 – $11,950Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗
4 inch concrete walksquare foot4—$21.00$5.50 – $21.00Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗
Erosion Controleach4—$1.00$1.00Sep 18, 2023, Open bid tab, bidtabmotbro2218pdf ↗
Valve Box Removedeach4—$320.00$96.00 – $320.00Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗
Aggregate Base, As Per Plancubic yard4—$95.00$49.00 – $95.00Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗
8 inch gate valveeach4—$2,395$1,675 – $2,395Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗
Fire Hydrant Removed And Stored On Site, As Per Planeach3—$995.00$192.00 – $995.00Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗
6 inch fire hydrant assembly, as per planeach3—$6,685$6,200 – $9,275Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗
Subgrade Compactionsquare yard3—$19.00$1.00 – $19.00Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗
Non-Tracking Tack Coat, 0.06 Gal/S.Y.gallon3—$15.00$11.50 – $15.00Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗
Walk Removedsquare foot3—$3.00$0.95 – $3.00Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗
Curb And Gutter Removedlinear foot3—$10.00$10.00 – $34.00Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗
10 inch dip class-51 (min.) water main, as per planlinear foot2—$392.00$183.50 – $392.00Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗
8 inch dip class-51 (min.) water main, as per planlinear foot2—$133.00$131.00 – $133.00Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗
4 inch dip class-51 (min.) water main, as per planlinear foot2—$270.00$210.00 – $270.00Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗
Asphalt Concrete Intermediate Course, Type 2, (449)cubic yard2—$365.00$365.00 – $432.00Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗
Asphalt Concrete Surface Course, Type 1, (449), Pg64-22cubic yard2—$390.00$390.00 – $900.00Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗
1-1/4 inch asphalt concrete surface course, type 1, (449), pg64-22cubic yard2—$400.00$355.00 – $400.00Nov 1, 2022, Open bid tab, bidtabmotbro2209pdf ↗
2-3/4 inch asphalt concrete intermediate course, type 2, (449)cubic yard2—$390.00$350.00 – $390.00Nov 1, 2022, Open bid tab, bidtabmotbro2209pdf ↗
1 inch type k copper water service branch, as per planlinear foot2—$72.00$65.00 – $72.00Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗
8 inch conduit, type b, 707.45, storm repair, as per planlinear foot2—$44.00$15.00 – $44.00Sep 18, 2023, Open bid tab, bidtabmotbro2218pdf ↗
6 inch conduit, type b, 707.45, storm repair, as per planlinear foot2—$34.00$15.00 – $34.00Sep 18, 2023, Open bid tab, bidtabmotbro2218pdf ↗
4 inch conduit, type b, 707.45, storm repair, as per planlinear foot2—$23.75$15.00 – $23.75Sep 18, 2023, Open bid tab, bidtabmotbro2218pdf ↗
4 inch temporary line stop, as per planeach2—$7,000$7,000 – $9,500Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗
1 inch water service branch, as per planlinear foot2—$56.00$56.00 – $59.00Sep 9, 2021, Open bid tab, bidtabmotbro1901pdf ↗
8 inch conduit, type b, 707.45, storm repairlinear foot2—$9.00$9.00 – $25.00Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗
6 inch conduit, type b, 707.45, storm repairlinear foot2—$5.00$5.00 – $20.00Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗
4 inch conduit, type b, 707.45, storm repairlinear foot2—$2.00$2.00 – $15.00Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗
Special - Bollardeach2—$425.00$425.00 – $1,600Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗
8 inch conduit, type b, 707.45, as per planlinear foot2—$35.00$22.00 – $35.00Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗
6 inch conduit, type b, 707.45, as per planlinear foot2—$35.00$16.00 – $35.00Nov 3, 2023, Open bid tab, bidtabmotbro2210pdf ↗
Curb Rampsquare foot2—$12.50$12.50 – $13.35Sep 18, 2023, Open bid tab, bidtabmotbro2218pdf ↗
Stop Linelinear foot2—$11.25$10.80 – $11.25Oct 31, 2022, Open bid tab, bidtabmotbro2009pdf ↗
Center Linemile2—$16,060$12,960 – $16,060Oct 31, 2022, Open bid tab, bidtabmotbro2009pdf ↗
Valve Box Adjusted To Gradeeach2—$250.00$175.00 – $250.00Sep 18, 2023, Open bid tab, bidtabmotbro2218pdf ↗
Combination Curb And Gutter, Type 2, As Per Planlinear foot2—$65.00$24.75 – $65.00Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗
Stabilized Crushed Aggregatecubic yard2—$95.00$52.00 – $95.00Jan 14, 2026, Open bid tab, bidtabmotbro2406pdf ↗

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.

More prices in Ohio: statewide figures.