| 6 inch perforated corrugated plastic pipe | linear foot | 10 | $7.50 | $8.00 | $5.00 – $20.00 | May 5, 2026, Open bid tab, contract Swailes-Bridge-02.48-Replacement-Project-Bid-Tab ↗ |
| Unclassified Excavation | ls | 10 | $15,000 | $5,000 | $5,000 – $50,000 | May 5, 2026, Open bid tab, contract Swailes-Bridge-02.48-Replacement-Project-Bid-Tab ↗ |
| Special - Steel Drip Strip | linear foot | 9 | $13.00 | $14.50 | $10.00 – $18.00 | May 5, 2026, Open bid tab, contract Swailes-Bridge-02.48-Replacement-Project-Bid-Tab ↗ |
| Wearing Course Removed | square yard | 9 | $10.00 | $17.00 | $8.00 – $25.00 | May 5, 2026, Open bid tab, contract Swailes-Bridge-02.48-Replacement-Project-Bid-Tab ↗ |
| Guardrail Removed | linear foot | 9 | $3.00 | $10.00 | $2.00 – $10.00 | May 5, 2026, Open bid tab, contract Swailes-Bridge-02.48-Replacement-Project-Bid-Tab ↗ |
| Type 3 Waterproofing | square yard | 9 | $37.50 | $51.00 | $34.00 – $51.00 | Mar 31, 2026, Open bid tab, contract Range-Line-Road-Bridge-No.-03.81-Replacement-Project-Bid-Tab ↗ |
| Asphalt Concrete Surface Course, Type 1, (448), Pg64-22 | cubic yard | 9 | $345.00 | $345.00 | $333.00 – $350.00 | Feb 8, 2022, Open bid tab, contract 2022_Miami_County_Bridge_Package_Bid_Tab ↗ |
| Maintaining Traffic | ls | 9 | $1,500 | $1,500 | $500.00 – $4,500 | Feb 25, 2025, Open bid tab, contract Peterson_Road_Bridge_No._06.12_Bid_Tab ↗ |
| Aggregate Base | cubic yard | 9 | $59.00 | $90.00 | $45.00 – $155.00 | Feb 25, 2025, Open bid tab, contract Peterson_Road_Bridge_No._06.12_Bid_Tab ↗ |
| Tack Coat | gallon | 9 | $20.00 | $16.00 | $16.00 – $25.00 | Oct 10, 2024, Open bid tab, contract Kessler-Frederick_Road_Bridge_No._00.06_Bid_Tab ↗ |
| 6 Inch Non-Perforated Corrugated Plastic Pipe, Including Specials | linear foot | 7 | $7.00 | $9.00 | $5.00 – $25.00 | Mar 31, 2026, Open bid tab, contract Range-Line-Road-Bridge-No.-03.81-Replacement-Project-Bid-Tab ↗ |
| Embankment | cubic yard | 7 | $26.00 | $13.00 | $10.00 – $38.00 | May 5, 2026, Open bid tab, contract Swailes-Bridge-02.48-Replacement-Project-Bid-Tab ↗ |
| Mobilization | ls | 7 | $16,500 | $30,000 | $8,150 – $30,000 | Oct 10, 2024, Open bid tab, contract Kessler-Frederick_Road_Bridge_No._00.06_Bid_Tab ↗ |
| Epoxy coated reinforced steel | pound | 7 | $1.75 | $2.00 | $1.40 – $2.00 | Apr 18, 2023, Open bid tab, contract Tipp-Elizabeth_Road_Bridge_No._04.25_Bid_Tab ↗ |
| Anchor Assembly, Mgs Type A | each | 6 | $1,600 | $1,850 | $1,550 – $1,850 | May 5, 2026, Open bid tab, contract Swailes-Bridge-02.48-Replacement-Project-Bid-Tab ↗ |
| Barrier Reflector, Type 1 (Bidirectional) | each | 6 | $9.75 | $10.50 | $8.00 – $12.00 | May 5, 2026, Open bid tab, contract Swailes-Bridge-02.48-Replacement-Project-Bid-Tab ↗ |
| Porous Backfill With Geotextile Fabric | cubic yard | 6 | $52.50 | $125.00 | $50.00 – $145.00 | Oct 10, 2024, Open bid tab, contract Kessler-Frederick_Road_Bridge_No._00.06_Bid_Tab ↗ |
| Guardrail, Type Mgs | linear foot | 6 | $24.50 | $26.00 | $20.00 – $80.00 | Mar 31, 2026, Open bid tab, contract Range-Line-Road-Bridge-No.-03.81-Replacement-Project-Bid-Tab ↗ |
| Cofferdams And Excavation Bracing | ls | 6 | $7,275 | $17,457 | $2,500 – $40,000 | Apr 18, 2023, Open bid tab, contract Tipp-Elizabeth_Road_Bridge_No._04.25_Bid_Tab ↗ |
| Seal of concrete surfaces (epoxy-urethane) | square yard | 6 | $17.50 | $23.00 | $12.00 – $31.00 | Mar 31, 2026, Open bid tab, contract Range-Line-Road-Bridge-No.-03.81-Replacement-Project-Bid-Tab ↗ |
| Construction Layout Stakes And Surveying | ls | 6 | $5,500 | $13,500 | $2,500 – $13,500 | May 5, 2026, Open bid tab, contract Swailes-Bridge-02.48-Replacement-Project-Bid-Tab ↗ |
| Asphalt Concrete Surface Course, Type 1, (449), Pg64-22 | cubic yard | 6 | $305.00 | $300.00 | $295.00 – $700.00 | Mar 31, 2026, Open bid tab, contract Range-Line-Road-Bridge-No.-03.81-Replacement-Project-Bid-Tab ↗ |
| Erosion Control | each | 6 | $1.00 | $2.00 | $1.00 – $2.00 | May 5, 2026, Open bid tab, contract Swailes-Bridge-02.48-Replacement-Project-Bid-Tab ↗ |
| Subgrade Compaction | square yard | 6 | $1.00 | $10.00 | $1.00 – $10.00 | Oct 10, 2024, Open bid tab, contract Kessler-Frederick_Road_Bridge_No._00.06_Bid_Tab ↗ |
| Subgrade Compaction, As Per Plan | square yard | 6 | $2.00 | $5.00 | $1.50 – $7.00 | May 5, 2026, Open bid tab, contract Swailes-Bridge-02.48-Replacement-Project-Bid-Tab ↗ |
| Clearing and Grubbing | ls | 6 | $4,479 | $20,000 | $1,000 – $20,000 | Feb 25, 2025, Open bid tab, contract Peterson_Road_Bridge_No._06.12_Bid_Tab ↗ |
| Rock Channel Protection, Type B, With Filter | cubic yard | 5 | $70.00 | $68.00 | $68.00 – $90.00 | Dec 20, 2022, Open bid tab, contract Owens_Road_Bridge_No._1.67_Replacement_Project_Bid_Tabulation ↗ |
| Class Qc2 Concrete, Superstructure | cubic yard | 5 | $450.00 | $333.33 | $333.33 – $720.00 | May 5, 2026, Open bid tab, contract Swailes-Bridge-02.48-Replacement-Project-Bid-Tab ↗ |
| Pile Driving Equipment Mobilization | ls | 5 | $15,000 | $37,000 | $11,000 – $37,000 | May 5, 2026, Open bid tab, contract Swailes-Bridge-02.48-Replacement-Project-Bid-Tab ↗ |
| Asphalt Concrete Intermediate Course, Type 2, (448), Pg 64-22 | cubic yard | 5 | $333.00 | $345.00 | $300.00 – $345.00 | Feb 8, 2022, Open bid tab, contract 2022_Miami_County_Bridge_Package_Bid_Tab ↗ |
| Commercial Fertilizer | ton | 5 | $600.00 | $1,500 | $600.00 – $1,500 | Oct 10, 2024, Open bid tab, contract Kessler-Frederick_Road_Bridge_No._00.06_Bid_Tab ↗ |
| Inter-seeding | square yard | 5 | $3.00 | $3.00 | $2.00 – $5.00 | Oct 10, 2024, Open bid tab, contract Kessler-Frederick_Road_Bridge_No._00.06_Bid_Tab ↗ |
| Repair Seeding And Mulching | square yard | 5 | $3.00 | $3.00 | $2.00 – $5.00 | Oct 10, 2024, Open bid tab, contract Kessler-Frederick_Road_Bridge_No._00.06_Bid_Tab ↗ |
| Lime | acre | 5 | $100.00 | $10.00 | $10.00 – $100.00 | Oct 10, 2024, Open bid tab, contract Kessler-Frederick_Road_Bridge_No._00.06_Bid_Tab ↗ |
| Elastomeric Bearing With Internal Laminates Only (Neoprene) | each | 5 | $185.00 | $185.00 | $145.00 – $320.00 | Mar 31, 2026, Open bid tab, contract Range-Line-Road-Bridge-No.-03.81-Replacement-Project-Bid-Tab ↗ |
| Seeding And Mulching, Class 2, As Per Plan | square yard | 5 | $3.00 | $3.00 | $2.00 – $5.50 | Mar 31, 2026, Open bid tab, contract Range-Line-Road-Bridge-No.-03.81-Replacement-Project-Bid-Tab ↗ |
| Seeding And Mulching | square yard | 5 | $7.00 | $10.00 | $5.00 – $10.00 | Oct 10, 2024, Open bid tab, contract Kessler-Frederick_Road_Bridge_No._00.06_Bid_Tab ↗ |
| Center Line, Type 1 | mile | 5 | $34,600 | $75,000 | $22,750 – $75,000 | Oct 10, 2024, Open bid tab, contract Kessler-Frederick_Road_Bridge_No._00.06_Bid_Tab ↗ |
| Pavement Removed | square yard | 5 | $10.00 | $50.00 | $9.00 – $50.00 | Oct 10, 2024, Open bid tab, contract Kessler-Frederick_Road_Bridge_No._00.06_Bid_Tab ↗ |
| Asphalt Concrete Intermediate Course, Type 2, (449) | cubic yard | 5 | $274.00 | $254.00 | $254.00 – $540.00 | Mar 31, 2026, Open bid tab, contract Range-Line-Road-Bridge-No.-03.81-Replacement-Project-Bid-Tab ↗ |