| Pipe, type 4, circular, 12 inch, 907.21 | linear foot | 4 | — | $21.22 | $19.38 – $24.15 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Pipe, type 4, circular, 10 inch, 907.21 | linear foot | 4 | — | $21.89 | $20.20 – $21.89 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Pipe, type 4, circular, 8 inch, 907.21 | linear foot | 4 | — | $17.57 | $12.86 – $17.57 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Pipe, type 4, circular, 6 inch, 907.21 | linear foot | 4 | — | $14.32 | $10.09 – $14.32 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Pipe, type 4, circular, 4 inch, 907.21 | linear foot | 4 | — | $10.00 | $7.57 – $10.00 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Construction Engineering, As Per Plan | ls | 4 | — | $25,000 | $5,980 – $31,522 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Excavation, Common, As Per Plan | cubic yard | 4 | — | $22.30 | $22.30 – $33.09 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Mulched Seeding, Grass, Type 2, As Per Plan | square yard | 4 | — | $5.08 | $3.95 – $6.55 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Compaction aggregate, no. 53, base, as per plan | ton | 4 | — | $21.01 | $15.54 – $21.50 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Remove of ground mounted sign and reerection | each | 4 | — | $297.30 | $262.60 – $297.30 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Maintaining Traffic | ls | 4 | — | $18,108 | $13,650 – $18,108 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Erosion Control | ls | 4 | — | $25,000 | $11,085 – $25,000 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Mobilization and Demobilization | ls | 4 | — | $53,050 | $39,786 – $207,922 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Clearing and Grubbing | ls | 4 | — | $25,419 | $25,419 – $26,637 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Gas Pipeline Crossing | ls | 3 | — | $5,216 | $4,551 – $5,216 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Grinder Pump Station | each | 3 | — | $14,035 | $14,035 – $14,489 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Lift Station Electric Service (Allowance) | ls | 3 | — | $30,000 | $30,000 – $40,000 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Pressure Sewer Discharge Connection To Sanitary Manhole | each | 3 | — | $5,390 | $5,390 – $7,074 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Standby Generator | ls | 3 | — | $72,230 | $62,352 – $72,230 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Low Pressure Forcemain End Cleanout Chamber, As Per Plan | each | 3 | — | $5,764 | $5,764 – $6,308 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Forcemain Air Release Valve Chamber, As Per Plan | each | 3 | — | $13,180 | $13,180 – $18,371 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Type C Drop Sanitary Sewer Manhole, As Per Plan | each | 3 | — | $13,120 | $11,004 – $13,120 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Type C, Sanitary Sewer Manhole, As Per Plan | each | 3 | — | $7,649 | $6,744 – $7,649 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| 2 inch grinder pump station forcemain install, trenchless, hdd, as per plan | linear foot | 3 | — | $15.79 | $14.38 – $15.79 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| 1/1/2 inch grinder pump station forcemain install, trenchless, hdd, as per plan | linear foot | 3 | — | $15.57 | $14.91 – $20.51 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| 6 inch sanitary sewer forcemain install, trenchless, hdd, as per plan | linear foot | 3 | — | $29.88 | $29.88 – $32.65 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| 6 inch sanitary sewer forcemain install, open cut, as per plan | linear foot | 3 | — | $45.72 | $45.72 – $72.68 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| 2 inch sanitary sewer forcemain install, open cut, as per plan | linear foot | 3 | — | $40.43 | $38.78 – $58.45 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| 2 inch sanitary sewer forcemain install, trenchless, hdd, as per plan | linear foot | 3 | — | $15.32 | $15.32 – $16.48 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| 8 inch pvc sdr-21 sanitary sewer, as per plan | linear foot | 3 | — | $146.90 | $84.62 – $154.24 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| 4 inch sanitary sewer lateral, type 1, as per plan | linear foot | 3 | — | $77.11 | $71.01 – $77.11 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| 8 inch pvc sdr-35, storm sewer repair, as per plan | linear foot | 3 | — | $37.78 | $28.76 – $43.86 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| 6 inch pvc sdr-35, storm sewer repair, as per plan | linear foot | 3 | — | $28.41 | $23.78 – $30.34 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Pre-Construction Video | ls | 3 | — | $6,530 | $5,837 – $6,530 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| 2-1/2 inch - 19mm, type b, hot mix asphalt intermediate, pg64-22 | ton | 3 | — | $250.81 | $250.81 – $343.48 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Scada System | ls | 3 | — | $9,324 | $8,086 – $9,324 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Subgrade Treatment, Type 1 | square yard | 3 | — | $15.48 | $15.06 – $23.22 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| 1-1/2 inch - 9.5mm type b hot mix asphalt surface, pg64-22 | ton | 3 | — | $352.82 | $332.95 – $523.59 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Mailbox Removed And Reset, As Per Plan | each | 3 | — | $182.43 | $173.77 – $327.60 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |
| Lift Station | ls | 3 | — | $488,532 | $463,960 – $488,532 | Oct 8, 2025, Open bid tab, bidtabinwellan2101tocsin ↗ |