Pease Township Trustees: awarded unit prices

55 winning bid prices read from 3 source documents, 2025. The table lists the 29 items this agency awarded most often. Winning bids only; every row links to a bid tabulation.

Cost by state › Agencies › Pease Township Trustees

ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Seeding And Mulching, Class 2square yard3—$25.00$16.00 – $50.00Sep 3, 2025, Open bid tab, 0000030443 ↗
Guardrail, Type Mgs, As Per Planlinear foot3—$85.00$50.00 – $126.00Sep 3, 2025, Open bid tab, 0000030443 ↗
Bonds And Insurances, As Per Planls3—$3,500$3,000 – $12,500Sep 3, 2025, Open bid tab, 0000030443 ↗
Erosion Control, As Per Planls3—$4,500$1,200 – $5,000Sep 3, 2025, Open bid tab, 0000030443 ↗
Anchor Assembly, Mgs Type Aeach3—$2,300$2,000 – $2,300Sep 3, 2025, Open bid tab, 0000030443 ↗
Drilled Shafts, 30 Inch Diameter, Into Bedrock, As Per Planlinear foot3—$135.00$117.00 – $135.00Sep 3, 2025, Open bid tab, 0000030443 ↗
Drilled Shafts, 30 Inch Diameter, Above Bedrock, As Per Planlinear foot3—$130.00$85.00 – $130.00Sep 3, 2025, Open bid tab, 0000030443 ↗
Construction Layout Stakes And Surveyingls3—$1,500$1,000 – $1,500Sep 3, 2025, Open bid tab, 0000030443 ↗
Subgrade Compaction, As Per Plansquare yard3—$20.00$14.00 – $20.00Sep 3, 2025, Open bid tab, 0000030443 ↗
Aggregate Basecubic yard3—$175.00$175.00 – $417.00Sep 3, 2025, Open bid tab, 0000030443 ↗
Mobilizationls3—$10,000$6,000 – $20,000Sep 3, 2025, Open bid tab, 0000030443 ↗
Clearing and Grubbingls3—$13,500$7,000 – $13,500Sep 3, 2025, Open bid tab, 0000030443 ↗
STEEL PILES, MISC.: SOLDIER PILES - HP14x89linear foot2—$87.00$87.00 – $93.00Jun 25, 2025, Open bid tab, 0000030441 ↗
Maintaining Traffic, As Per Planls2—$3,850$1,500 – $3,850Jun 25, 2025, Open bid tab, 0000030441 ↗
Asphalt Concrete Surface Course, Type 1, (448), As Per Plancubic yard1—$500.00$500.00Sep 3, 2025, Open bid tab, 0000030443 ↗
Rock Channel Protection, Type D With Fabric Filtercubic yard1—$1,462$1,462Jun 25, 2025, Open bid tab, 0000030441 ↗
Concrete misc.: 8 inch x 24 inch x 54 inch precast concrete laggingeach1—$937.00$937.00Jun 25, 2025, Open bid tab, 0000030441 ↗
Class Qc1 Concrete, Footing, As Per Plancubic yard1—$652.00$652.00Jun 25, 2025, Open bid tab, 0000030441 ↗
Geotextile Fabric, As Per Plansquare yard1—$4.00$4.00Sep 3, 2025, Open bid tab, 0000030443 ↗
Porous Backfill With Geotextile Fabric, As Per Plancubic yard1—$174.00$174.00Jun 25, 2025, Open bid tab, 0000030441 ↗
STEEL PILES, MISC.: SOLDIER PILES - HP14x117linear foot1—$120.00$120.00Sep 3, 2025, Open bid tab, 0000030443 ↗
6 Inch Non-Perforated Corrugated Plastic Pipe, Including Specialslinear foot1—$11.00$11.00Jun 25, 2025, Open bid tab, 0000030441 ↗
6 inch perforated corrugated plastic pipelinear foot1—$4.00$4.00Jun 25, 2025, Open bid tab, 0000030441 ↗
Ditch Erosion Protectionsquare yard1—$55.00$55.00Jun 25, 2025, Open bid tab, 0000030441 ↗
_ Ditch Cleanoutlinear foot1—$27.00$27.00Jun 25, 2025, Open bid tab, 0000030441 ↗
15 inch storm sewer, as per planlinear foot1—$330.00$330.00Jun 25, 2025, Open bid tab, 0000030441 ↗
Asphalt Concrete Base, Pg64-22cubic yard1—$450.00$450.00Sep 3, 2025, Open bid tab, 0000030443 ↗
Maintaining Trafficls1—$5,000$5,000Sep 3, 2025, Open bid tab, 0000030443 ↗
Geotextile Fabricsquare yard1—$5.00$5.00Apr 9, 2025, Open bid tab, 0000026078 ↗

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.