City of North Royalton: awarded unit prices

68 winning bid prices read from 3 source documents, 2021–2025. The table lists the 40 items this agency awarded most often. Winning bids only; every row links to a bid tabulation.

Cost by state › Agencies › City of North Royalton

ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Contingency/Discretionary Allowancels3—$30,000$10,000 – $30,000Feb 21, 2025, Open bid tab, 220923 ↗
Mobilization, Maintaining Traffic, Erosion Control, Bonds And Insurances And Other Overheals2—$6,300$6,300 – $23,771Sep 30, 2022, Open bid tab, 220247 ↗
Rock Channel Protection, Type B With Fabric Filtercubic yard2—$125.00$119.00 – $125.00Feb 21, 2025, Open bid tab, 220923 ↗
Construction Layout Stakes And Surveyingls2—$9,000$4,620 – $9,000Feb 21, 2025, Open bid tab, 220923 ↗
Clearing and Grubbingls2—$2,500$2,500 – $3,500Feb 21, 2025, Open bid tab, 220923 ↗
6 Inch Sanitary Sewer Lateral W/Test Tee/Clean Out Assembly (Long), As Per Planeach1—$2,700$2,700Sep 30, 2022, Open bid tab, 220247 ↗
6 Inch Sanitary Sewer Lateral W/Test Tee/Clean Out Assembly (Short), As Per Planeach1—$2,100$2,100Sep 30, 2022, Open bid tab, 220247 ↗
Geotextile Fabric, 712.09 Type Csquare yard1—$14.00$14.00Jul 9, 2021, Open bid tab, 200950 ↗
16 Inch Steel Pipe Encasement, Open Cutlinear foot1—$145.00$145.00Jul 9, 2021, Open bid tab, 200950 ↗
8 inch water main ductile iron pipe ansi class 52, push-on joint and push-on fittinglinear foot1—$523.00$523.00Jul 9, 2021, Open bid tab, 200950 ↗
84 Inch Storm Manhole, As Per Planeach1—$14,467$14,467Jul 9, 2021, Open bid tab, 200950 ↗
54 inch conduit, type blinear foot1—$379.00$379.00Jul 9, 2021, Open bid tab, 200950 ↗
Rock Channel Protection, Type A With Filtercubic yard1—$116.00$116.00Jul 9, 2021, Open bid tab, 200950 ↗
7 Inch Reinforced Concrete Pavementsquare yard1—$209.00$209.00Jul 9, 2021, Open bid tab, 200950 ↗
Remove misc.: misc. site items removed, stored, and replacedls1—$11,404$11,404Jul 9, 2021, Open bid tab, 200950 ↗
Stone Toe, As Per Planlinear foot1—$47.65$47.65Feb 21, 2025, Open bid tab, 220923 ↗
Deciduous Shrub, 3' Height, As Per Planeach1—$132.00$132.00Feb 21, 2025, Open bid tab, 220923 ↗
Roadway, Misc.: Access Route Including Restorationls1—$3,000$3,000Feb 21, 2025, Open bid tab, 220923 ↗
8 Inch Cutting-In Sleeveeach1—$795.00$795.00Jul 9, 2021, Open bid tab, 200950 ↗
Placing Stockpiled Topsoil, As Per Plancubic yard1—$18.50$18.50Feb 21, 2025, Open bid tab, 220923 ↗
Erosion Control Mat, Type C, As Per Plansquare yard1—$6.50$6.50Feb 21, 2025, Open bid tab, 220923 ↗
Type "A" Sanitary Manhole, As Per Planeach1—$4,000$4,000Sep 30, 2022, Open bid tab, 220247 ↗
Asphalt Concrete Base, Pg64-22, As Per Plancubic yard1—$650.00$650.00Sep 30, 2022, Open bid tab, 220247 ↗
Manhole, Misc.: Connection To Existing Manholeeach1—$2,900$2,900Sep 30, 2022, Open bid tab, 220247 ↗
Rock Channel Protection, Type C With Fabric Filtercubic yard1—$228.00$228.00Jul 9, 2021, Open bid tab, 200950 ↗
Boulder Cross Vanes With Stepseach1—$2,425$2,425Feb 21, 2025, Open bid tab, 220923 ↗
Granular Material, As Per Plancubic yard1—$195.00$195.00Feb 21, 2025, Open bid tab, 220923 ↗
4 inch concrete walk, including remove, as per plansquare foot1—$100.00$100.00Feb 21, 2025, Open bid tab, 220923 ↗
Type "a" pavement replace (concrete), driveway, apron, or parking lot, as per plansquare yard1—$95.00$95.00Sep 30, 2022, Open bid tab, 220247 ↗
48 Inch Storm Manhole, As Per Planeach1—$3,312$3,312Jul 9, 2021, Open bid tab, 200950 ↗
Temporary Sediment And Erosion Control, As Per Planls1—$5,000$5,000Feb 21, 2025, Open bid tab, 220923 ↗
Tree Removed Including Stump, As Per Planeach1—$440.00$440.00Feb 21, 2025, Open bid tab, 220923 ↗
Deer Tree Guardseach1—$83.00$83.00Feb 21, 2025, Open bid tab, 220923 ↗
Live Stakes, As Per Planeach1—$110.00$110.00Feb 21, 2025, Open bid tab, 220923 ↗
Boulder Riffle (Type A Stone), As Per Plancubic yard1—$150.00$150.00Feb 21, 2025, Open bid tab, 220923 ↗
Deciduous Tree, 6' Heighteach1—$308.00$308.00Feb 21, 2025, Open bid tab, 220923 ↗
Seeding And Mulching, As Per Planls1—$13,112$13,112Feb 21, 2025, Open bid tab, 220923 ↗
Fence, Split Rail, As Per Planlinear foot1—$22.00$22.00Feb 21, 2025, Open bid tab, 220923 ↗
Type "c" pavement replace (asphalt), driveway, apron, or parking lotsquare yard1—$230.00$230.00Sep 30, 2022, Open bid tab, 220247 ↗
Excavation Including Embankment Construction, As Per Planls1—$30,000$30,000Feb 21, 2025, Open bid tab, 220923 ↗