Construction unit costs in Minnesota

Median awarded unit prices for the 55 most-bid items on Minnesota public projects, from winning bids in agency bid tabulations.

Cost by state › Minnesota

ItemPerMedianMiddle halfWinning bids
Remove Bituminous Pavementsquare yard$5.25$3.90 – $8.36499
Seedingacre$495.88$230.00 – $1,000413
Sawing Bituminous Pavement (Full Depth)linear foot$2.50$2.00 – $5.00411
Storm Drain Inlet Protectioneach$175.00$132.16 – $207.50401
Common Embankment (Cv)cubic yard$10.00$5.98 – $20.00368
Excavation Commoncubic yard$14.90$9.31 – $24.50354
Soil Bed Preparationacre$323.50$200.00 – $619.75352
Fertilizer Type 3pound$1.00$0.95 – $1.45348
Silt Fence, Type MSlinear foot$2.50$2.00 – $3.20343
Remove Pipe Culvertslinear foot$15.00$11.00 – $20.00334
Remove Signeach$50.00$28.07 – $75.00318
6" Solid Line Multi-component Ground IN (wr)linear foot$1.45$1.15 – $2.40281
Rolled Erosion Prevention Category 25square yard$2.00$1.80 – $2.50270
Signsquare foot$85.00$70.00 – $101.25270
Truncated Domessquare foot$65.00$57.75 – $75.00264
Casting Assemblyeach$1,140$919.16 – $1,337262
6" Concrete Walksquare foot$11.00$9.00 – $13.85259
Culvert End Controlseach$150.00$95.75 – $200.00256
Random Riprap Class IIIcubic yard$105.00$85.43 – $135.00250
Grubbingacre$8,500$4,750 – $12,500241
Salvage Signeach$50.00$37.00 – $75.00234
Sawing Concrete Pavement (Full Depth)linear foot$5.50$4.00 – $6.94226
Bituminous Material For Tack Coatgallon$2.88$2.00 – $3.50216
Install Signeach$594.00$340.00 – $905.05215
Excavation Common **P**cubic yard$11.00$6.90 – $16.00211
4" Solid Line Paintlinear foot$0.13$0.11 – $0.4205
Sediment Control Log Type Compostlinear foot$3.50$3.00 – $4.41204
Select Granular Embankment (Cv)cubic yard$26.00$19.34 – $38.00204
Aggregate Surfacing Class 5ton$23.00$19.00 – $33.34202
Interim Pavement Markinglinear foot$0.22$0.15 – $0.34199
Drill and Grout Reinf Bar (Epoxy Coated)each$15.00$11.00 – $20.00198
Grubbingeach$250.00$150.00 – $500.00198
Remove Curb and Gutterlinear foot$6.50$4.06 – $10.00193
Rolled Erosion Prevention Category 20square yard$2.00$1.66 – $2.54190
Traffic Barrier Design Type 31linear foot$34.00$29.50 – $40.20183
Connect to Existing Storm Sewereach$1,300$950.00 – $1,794182
Fine Aggregate Bedding (Cv)cubic yard$44.90$35.00 – $58.00176
24" RC Pipe Aproneach$1,324$1,134 – $1,800173
Reinforcement Bars (Epoxy Coated)pound$1.75$1.60 – $2.00167
Remove Sewer Pipe (Storm)linear foot$20.00$15.00 – $27.00166
Clearingacre$10,000$6,000 – $15,688142
4" Concrete Walksquare foot$8.50$7.03 – $10.97139
Pavement Marking Removallinear foot$1.00$0.8 – $1.80137
Portable Changeable Message Signeach$3,000$2,165 – $4,000119
Motor Graderhour$200.00$127.50 – $220.00110
Sign Panelsquare foot$49.62$38.75 – $62.5092
Mowingacre$150.00$86.06 – $247.5090
Waterthousand gallons$40.00$25.00 – $58.7587
Pavement Marking Removalsquare foot$3.75$3.00 – $5.5065
Pavement Message Paintsquare foot$7.50$6.00 – $11.0064
Remove Fencelinear foot$5.00$3.06 – $9.5750
Remove Catch Basineach$500.00$311.25 – $785.0032
Structural Concretecubic yard$124.62$118.77 – $139.3422
Concrete Collareach$1,101$700.00 – $1,81521
Remove Guardraillinear foot$7.90$5.15 – $11.0019