| Mobilization | ls | 38 | — | $700,000 | $2,000 – $5,100,000 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| Remove asphalt pavement | square yard | 29 | $5.00 | $8.42 | $1.55 – $34.70 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| Traffic Control | ls | 29 | — | $40,000 | $750.00 – $512,500 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| Remove Curb & Gutter | linear foot | 27 | $6.00 | $5.00 | $1.50 – $15.00 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| 6 inch concrete walk | square foot | 27 | $13.80 | $18.01 | $9.55 – $22.12 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| Storm Drain Inlet Protection | each | 26 | $150.00 | $150.00 | $100.00 – $401.00 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| Truncated Domes | square foot | 25 | $60.00 | $74.00 | $32.20 – $74.90 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| Concrete Curb & Gutter Design B624 | linear foot | 24 | $38.75 | $45.00 | $16.50 – $71.84 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| Stabilized Construction Exit | ls | 24 | — | $3,824 | $1.00 – $6,600 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| Erosion Control Supervisor | ls | 24 | — | $13,300 | $1.00 – $13,300 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| Adjust Frame & Ring Casting | each | 22 | $757.50 | $620.16 | $230.07 – $2,000 | Jun 23, 2026, Open bid tab, J4739 ↗ |
| Sawing bit pavement (full deep) | linear foot | 21 | $3.00 | $12.00 | $1.00 – $12.00 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| Silt Fence, Type MS | linear foot | 21 | $2.50 | $3.00 | $1.00 – $6.10 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| 5 inch concrete walk | square foot | 17 | $10.47 | $14.00 | $7.20 – $14.15 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| Excavation Common **P** | cubic yard | 16 | $17.50 | $15.00 | $4.62 – $80.00 | Aug 25, 2026, Open bid tab, 7862 ↗ |
| Stabilizing Aggregate (Cv) | cubic yard | 15 | $30.00 | $30.00 | $5.00 – $57.70 | Aug 25, 2026, Open bid tab, 7862 ↗ |
| Aggregate Base (Cv) Class 5 (P) | cubic yard | 15 | $40.00 | $28.00 | $23.00 – $60.00 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| Sawing concrete pavement (full deep) | linear foot | 15 | $5.00 | $12.00 | $2.00 – $12.00 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| 4 inch concrete walk | square foot | 15 | $10.37 | $15.00 | $6.40 – $18.00 | Aug 25, 2026, Open bid tab, 7862 ↗ |
| Remove Concrete Driveway Pavement | square yard | 14 | $10.00 | $6.50 | $5.75 – $15.00 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| Remove Concrete Pavement | square yard | 14 | $10.00 | $7.00 | $5.00 – $77.00 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| Remove Concrete Sidewalk | square foot | 14 | $1.56 | $1.62 | $0.55 – $92.30 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| Connect to Existing Water Main | each | 14 | $2,000 | $3,523 | $900.00 – $5,783 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| Drill & Grout Dowel Bar (Epoxy Coated) | each | 13 | $19.00 | $25.00 | $8.95 – $25.00 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| Grubbing | each | 13 | $500.00 | $560.00 | $125.00 – $1,500 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| 7 inch concrete driveway pavement | square yard | 12 | $104.62 | $120.00 | $78.10 – $135.00 | Jun 18, 2026, Open bid tab, 8915 ↗ |
| Remove Concrete Walk | square foot | 12 | $2.00 | $4.56 | $0.95 – $6.00 | Jun 23, 2026, Open bid tab, J4739 ↗ |
| Aggregate Base (Cv) Class 5 | cubic yard | 12 | $45.25 | $94.00 | $30.00 – $94.00 | Aug 25, 2026, Open bid tab, J4348 ↗ |
| Remove Manhole | each | 12 | $730.00 | $475.00 | $475.00 – $1,900 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| 6 inch pvc pipe drain cleanout | each | 11 | $700.00 | $830.00 | $350.00 – $1,020 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| Remove asphalt walk | square foot | 11 | $1.80 | $2.00 | $0.6 – $5.00 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| Clearing | each | 11 | $725.00 | $3,300 | $125.00 – $3,300 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| Connect to Existing Storm Sewer | each | 11 | $1,170 | $2,900 | $690.00 – $2,900 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| Casting Assembly | each | 11 | $1,000 | $800.00 | $700.00 – $2,190 | Jun 18, 2026, Open bid tab, 8915 ↗ |
| 6 inch perf pvc pipe drain | linear foot | 11 | $20.00 | $17.00 | $15.00 – $114.00 | Sep 9, 2026, Open bid tab, J7829 ↗ |
| Select Granular Embankment (Cv) | cubic yard | 10 | $31.50 | $18.00 | $1.00 – $48.00 | Aug 25, 2026, Open bid tab, 7862 ↗ |
| Common Topsoil Borrow | cubic yard | 10 | $25.00 | $1.00 | $1.00 – $75.00 | Jun 18, 2026, Open bid tab, 8915 ↗ |
| Drill & grout reinforced bar (epoxy coated) | each | 10 | $15.23 | $16.60 | $7.20 – $18.20 | Jun 17, 2025, Open bid tab, J8707C ↗ |
| 3 inch asphalt walk | square foot | 10 | $5.75 | $7.00 | $2.00 – $9.49 | Aug 26, 2025, Open bid tab, 4737 ↗ |
| Dowel Bar | each | 10 | $15.20 | $17.00 | $12.44 – $24.75 | Sep 9, 2026, Open bid tab, J7829 ↗ |