| Traffic Control | ls | 19 | $4,900 | $4,800 | $500.00 – $17,000 | Apr 21, 2026, Open bid tab, ST-002 2026 ↗ |
| Remove Curb & Gutter | linear foot | 17 | $9.00 | $13.00 | $2.67 – $19.00 | Apr 21, 2026, Open bid tab, ST-002 2026 ↗ |
| 6 inch concrete walk | square foot | 16 | $12.28 | $12.00 | $8.00 – $22.00 | Apr 21, 2026, Open bid tab, ST-002 2026 ↗ |
| Truncated Domes | square foot | 14 | $69.00 | $60.00 | $60.00 – $100.00 | Apr 21, 2026, Open bid tab, ST-002 2026 ↗ |
| 4 inch concrete walk | square foot | 14 | $9.52 | $7.15 | $5.65 – $17.00 | Apr 10, 2026, Open bid tab, ST-020 ↗ |
| Sawing concrete pavement (full deep) | linear foot | 13 | $6.00 | $7.00 | $3.90 – $15.00 | Apr 10, 2026, Open bid tab, ST-020 ↗ |
| Adjust Frame & Ring Casting | each | 13 | $600.00 | $1,050 | $250.00 – $1,075 | Apr 21, 2026, Open bid tab, ST-002 2026 ↗ |
| Concrete Curb & Gutter Design B618 | linear foot | 13 | $42.20 | $43.50 | $21.15 – $83.00 | Apr 21, 2026, Open bid tab, ST-002 2026 ↗ |
| Storm Drain Inlet Protection | each | 13 | $175.00 | $140.00 | $75.00 – $400.00 | Apr 10, 2026, Open bid tab, ST-020 ↗ |
| Mobilization | ls | 13 | $45,535 | $57,500 | $5,000 – $310,000 | Apr 21, 2026, Open bid tab, 139-109-006 - ST-002 ↗ |
| Boulevard Topsoil Borrow | cubic yard | 12 | $45.00 | $55.00 | $18.00 – $115.00 | Apr 10, 2026, Open bid tab, ST-020 ↗ |
| Stabilized Construction Exit | ls | 12 | $1,000 | $1,000 | $1.00 – $1,500 | Apr 10, 2026, Open bid tab, ST-020 ↗ |
| Remove asphalt surfacing | square yard | 12 | $4.00 | $11.00 | $2.50 – $11.00 | Apr 10, 2026, Open bid tab, ST-020 ↗ |
| Common Excavation (P) | cubic yard | 12 | $15.75 | $20.00 | $8.00 – $62.00 | Apr 10, 2026, Open bid tab, ST-020 ↗ |
| Remove Concrete Pavement | square yard | 11 | $11.31 | $15.00 | $8.00 – $24.00 | Apr 10, 2026, Open bid tab, ST-020 ↗ |
| Remove Sidewalk | square foot | 10 | $1.88 | $2.00 | $0.98 – $10.00 | Apr 10, 2026, Open bid tab, ST-020 ↗ |
| Rapid Stabilization Method 3 | thousand gallons | 10 | $263.14 | $500.00 | $150.00 – $850.00 | Apr 10, 2026, Open bid tab, ST-020 ↗ |
| Turf Establishment | ls | 10 | $4,250 | $4,000 | $1,450 – $5,750 | Apr 10, 2026, Open bid tab, ST-020 ↗ |
| Sawing bit pavement (full deep) | linear foot | 10 | $3.25 | $7.00 | $1.86 – $7.00 | Apr 10, 2026, Open bid tab, ST-020 ↗ |
| Geotextile Fabric Type 7 | square yard | 10 | $3.50 | $4.00 | $1.55 – $4.25 | Apr 10, 2026, Open bid tab, ST-020 ↗ |
| 6 inch concrete driveway pavement | square yard | 9 | $80.85 | $85.14 | $46.00 – $110.80 | Apr 10, 2026, Open bid tab, ST-020 ↗ |
| Construction drainage structure design a | each | 9 | $3,000 | $800.00 | $800.00 – $5,578 | Apr 10, 2026, Open bid tab, ST-020 ↗ |
| 7 inch concrete valley gutter | square yard | 8 | $90.00 | $120.50 | $82.00 – $140.00 | Apr 21, 2026, Open bid tab, ST-002 2026 ↗ |
| 8 inch pvc pipe sewer | linear foot | 8 | $62.00 | $60.00 | $55.00 – $75.00 | Apr 10, 2026, Open bid tab, ST-020 ↗ |
| Aggregate Foundation | ton | 8 | $32.50 | $50.00 | $1.00 – $50.00 | Apr 10, 2026, Open bid tab, ST-020 ↗ |
| Aggregate Base (Cv) Class 5 (P) | cubic yard | 8 | $37.00 | $40.00 | $26.00 – $45.00 | Mar 12, 2025, Open bid tab, PK-013 RRFB and Trai ↗ |
| 6 inch pvc water main | linear foot | 7 | $52.00 | $40.00 | $40.00 – $60.00 | Apr 10, 2026, Open bid tab, ST-020 ↗ |
| 48 inch diameter. sanitary sewer manhole | linear foot | 7 | $700.00 | $1,028 | $550.00 – $1,200 | Apr 10, 2026, Open bid tab, ST-020 ↗ |
| 4 inch pvc pipe sewer | linear foot | 7 | $45.00 | $45.00 | $30.00 – $75.00 | Apr 10, 2026, Open bid tab, ST-020 ↗ |
| 8 inchx4 inch pvc wye | each | 7 | $450.00 | $275.00 | $275.00 – $715.00 | Mar 17, 2026, Open bid tab, ST-013 ↗ |
| Subgrade Preparation | square yard | 7 | $1.40 | $2.00 | $0.5 – $2.00 | Apr 10, 2026, Open bid tab, ST-020 ↗ |
| Site Restoration | each | 7 | $600.00 | $600.00 | $571.00 – $1,500 | Apr 21, 2026, Open bid tab, ST-002 2026 ↗ |
| 6 inch gate valve & box | each | 6 | $3,000 | $600.00 | $600.00 – $4,500 | Apr 10, 2026, Open bid tab, ST-020 ↗ |
| 4 inch perf pvc pipe drain | linear foot | 6 | $12.75 | $8.00 | $8.00 – $15.00 | Apr 10, 2026, Open bid tab, ST-020 ↗ |
| 8 inch pvc water main | linear foot | 6 | $65.00 | $58.00 | $49.00 – $100.00 | Feb 12, 2025, Open bid tab, ST-012-2025 ↗ |
| Remove Manhole | each | 6 | $500.00 | $450.00 | $350.00 – $1,100 | Apr 10, 2026, Open bid tab, ST-020 ↗ |
| Adjust Gate Valve BOX | each | 6 | $362.50 | $350.00 | $75.00 – $450.00 | Apr 21, 2026, Open bid tab, ST-002 2026 ↗ |
| Asphalt material for tack coat | gallon | 6 | $3.37 | $4.00 | $3.00 – $4.50 | Apr 21, 2026, Open bid tab, ST-002 2026 ↗ |
| Type Sp 9.5 Wearing Course Mix (3,B) | ton | 6 | $87.06 | $81.00 | $81.00 – $225.00 | Apr 21, 2026, Open bid tab, ST-002 2026 ↗ |
| Remove Catch Basin | each | 6 | $425.00 | $250.00 | $250.00 – $501.75 | Apr 10, 2026, Open bid tab, ST-020 ↗ |