Agency · awarded bid prices

Chippewa County: awarded unit prices

170 winning bid prices read from 4 source documents, 2024–2025. The table lists the 40 items this agency awarded most often. Winning bids only; every row links to a bid tabulation.

Cost by state › Agencies › Chippewa County

ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Common Embankment (Cv) (P)cubic yard12$6.00$15.00$4.00 – $15.00Mar 19, 2025, Open bid tab, SAP 012-599-119 ↗
Traffic Controlls11$1,200$700.00$700.00 – $3,500Mar 19, 2025, Open bid tab, SAP 012-599-119 ↗
Aggregate base class 5 modifiedton9$20.00$14.00$14.00 – $45.00Mar 19, 2025, Open bid tab, SAP 012-599-119 ↗
Rapid Stabilization Method 4square yard7$2.10$2.10$1.95 – $2.50Mar 19, 2025, Open bid tab, SAP 012-599-119 ↗
Structure Excavation Class U (P)cubic yard7$4.00$4.00$4.00 – $4.50Mar 19, 2025, Open bid tab, SAP 012-599-119 ↗
Sediment Control Log Type Strawlinear foot6$3.75$3.70$3.70 – $4.00Mar 19, 2025, Open bid tab, SAP 012-599-119 ↗
Coarse Filter Aggregate (Cv)cubic yard6$32.00$32.00$15.00 – $40.00Mar 19, 2025, Open bid tab, SAP 012-599-119 ↗
Random Riprap Class Iiiton6$62.00$60.00$60.00 – $90.00Mar 19, 2025, Open bid tab, SAP 012-599-119 ↗
Type sp 12.5 bit mixture for patchton5$100.00$100.00$100.00Jan 23, 2025, Open bid tab, SAP 012-604-021 ↗
Shoulder base aggregate class 5 modifiedton5$22.15$20.25$16.20 – $28.10Jan 23, 2025, Open bid tab, SAP 012-604-021 ↗
4 inch broken line paintlinear foot5$0.12$0.12$0.12Jan 23, 2025, Open bid tab, SAP 012-604-021 ↗
4 inch solid line paintlinear foot5$0.12$0.12$0.12Jan 23, 2025, Open bid tab, SAP 012-604-021 ↗
Mobilizationls5$5,000$100,000$5,000 – $100,000Jan 23, 2025, Open bid tab, SAP 012-604-021 ↗
Interim Pavement Markingls5$1,900$7,000$900.00 – $7,000Jan 23, 2025, Open bid tab, SAP 012-604-021 ↗
Type Sp 12.5 Wearing Course Mix (2,B)ton4—$51.93$47.61 – $58.19Jan 23, 2025, Open bid tab, SAP 012-604-021 ↗
Remove pipe culvertlinear foot4—$10.00$8.00 – $12.00Mar 19, 2025, Open bid tab, SAP 012-599-119 ↗
24 inch gs safety aproneach3—$750.00$400.00 – $900.00Jan 23, 2025, Open bid tab, SAP 012-603-017 ↗
24 inch cs pipe culvertlinear foot3—$50.00$50.00 – $60.00Jan 23, 2025, Open bid tab, SAP 012-603-017 ↗
15 inch gs safety aproneach3—$200.00$200.00 – $285.00Mar 19, 2025, Open bid tab, SAP 012-599-119 ↗
6 inch solid line paintlinear foot3—$0.16$0.16Jan 23, 2025, Open bid tab, SAP 012-604-021 ↗
15 inch cs pipe culvertlinear foot3—$25.00$25.00 – $45.00Mar 19, 2025, Open bid tab, SAP 012-599-119 ↗
24 inch solid line paintlinear foot3—$9.50$9.50Jan 23, 2025, Open bid tab, SAP 012-604-021 ↗
CS Oversleeve With Rodent Guardeach2—$250.00$250.00Jan 23, 2025, Open bid tab, SAP 012-603-017 ↗
Milling asphalt surface (1.75 inch)square yard2—$1.10$1.10 – $1.90Jan 23, 2025, Open bid tab, SAP 012-604-021 ↗
12 inch cs pipe culvertlinear foot2—$35.00$35.00Jan 23, 2025, Open bid tab, SAP 012-603-017 ↗
10'x5' PRECAST CONCRETE BOX CULVERTlinear foot2—$1,273$1,273 – $1,280Mar 19, 2025, Open bid tab, SAP 012-599-119 ↗
10'x5' PRECAST CONCRETE BOX CULVERT END SECTIONeach2—$13,500$13,500Mar 19, 2025, Open bid tab, SAP 012-599-119 ↗
4 inch double solid line paintlinear foot2—$0.24$0.24Jan 23, 2025, Open bid tab, SAP 012-604-021 ↗
Aggregate Surfacing Class 2ton2—$43.00$43.00Jan 23, 2025, Open bid tab, SAP 012-603-017 ↗
Remove Existing Bridgels2—$6,500$5,500 – $6,500Jan 23, 2025, Open bid tab, SAP 012-603-017 ↗
Pavement Message Paintsquare foot2—$11.00$11.00Jan 23, 2025, Open bid tab, SAP 012-604-021 ↗
Remove asphalt pavementsquare yard2—$6.00$6.00Jan 23, 2025, Open bid tab, SAP 012-603-017 ↗
42 inch gs safety aproneach1—$4,600$4,600Jan 23, 2025, Open bid tab, SAP 012-603-017 ↗
Remove Wood Boxeach1—$5,000$5,000Jan 23, 2025, Open bid tab, SAP 012-603-017 ↗
16'x12' PRECAST CONCRETE BOX CULVERTlinear foot1—$2,025$2,025Jan 23, 2025, Open bid tab, SAP 012-603-017 ↗
16'x12' PRECAST CONCRETE BOX CULVERT END SECTIONeach1—$41,000$41,000Jan 23, 2025, Open bid tab, SAP 012-603-017 ↗
Tractor & Diskhour1—$200.00$200.00Jan 23, 2025, Open bid tab, SAP 012-604-021 ↗
10'x4' precast concrete. box culvertlinear foot1—$1,650$1,650Aug 8, 2024, Open bid tab, SAP 012-599-110 ↗
10'x4' precast concrete. box culvert. end sectioneach1—$16,350$16,350Aug 8, 2024, Open bid tab, SAP 012-599-110 ↗
10'x7' precast concrete. box culvertlinear foot1—$1,675$1,675Aug 8, 2024, Open bid tab, SAP 012-599-110 ↗

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.