| Traffic Control | ls | 14 | $20,000 | $18,000 | $3,000 – $31,650 | Mar 27, 2025, Open bid tab, SAP 038-602-036 ↗ |
| Mobilization | ls | 14 | $192,161 | $167,000 | $122,000 – $674,506 | Mar 27, 2025, Open bid tab, SAP 038-602-036 ↗ |
| Soil Bed Preparation | acre | 10 | $965.00 | $270.00 | $270.00 – $1,250 | Mar 27, 2025, Open bid tab, SAP 038-602-036 ↗ |
| Random Riprap Class III | cubic yard | 10 | $75.00 | $80.00 | $55.00 – $115.00 | Mar 27, 2025, Open bid tab, SAP 038-602-036 ↗ |
| Asphalt material for tack coat | gallon | 10 | $2.95 | $2.80 | $2.80 – $6.00 | Mar 27, 2025, Open bid tab, SAP 038-602-036 ↗ |
| Water | thousand gallons | 10 | $93.50 | $100.00 | $50.00 – $110.00 | Mar 27, 2025, Open bid tab, SAP 038-602-036 ↗ |
| Seeding | acre | 10 | $315.00 | $270.00 | $110.00 – $665.00 | Mar 27, 2025, Open bid tab, SAP 038-602-036 ↗ |
| Fertilizer Type 3 | pound | 9 | $1.10 | $1.25 | $1.05 – $1.25 | Mar 27, 2025, Open bid tab, SAP 038-602-036 ↗ |
| Aggregate Base (Cv) Class 5 | cubic yard | 9 | $59.00 | $33.65 | $33.65 – $60.00 | Mar 27, 2025, Open bid tab, SAP 038-602-036 ↗ |
| Select Granular Embankment (Cv) | cubic yard | 8 | $38.00 | $38.00 | $22.00 – $38.00 | Mar 14, 2024, Open bid tab, SAP 038-636-001(low) ↗ |
| Remove asphalt pavement | square yard | 8 | $3.60 | $7.25 | $2.00 – $7.25 | Mar 27, 2025, Open bid tab, SAP 038-602-036 ↗ |
| Excavation Common **P** | cubic yard | 7 | $27.00 | $12.40 | $12.40 – $27.00 | Mar 27, 2025, Open bid tab, SAP 038-602-036 ↗ |
| Rapid Stabilization Method 3 | thousand gallons | 7 | $1,625 | $475.00 | $190.00 – $1,625 | Mar 27, 2025, Open bid tab, SAP 038-602-036 ↗ |
| Erosion Control Supervisor | ls | 7 | $500.00 | $1,350 | $500.00 – $1,500 | Mar 27, 2025, Open bid tab, SAP 038-602-036 ↗ |
| Rolled Erosion Prevention Category 20 | square yard | 6 | $2.70 | $2.05 | $2.00 – $3.30 | Mar 27, 2025, Open bid tab, SAP 038-602-036 ↗ |
| Remove pipe culvert | linear foot | 6 | $10.00 | $18.50 | $10.00 – $33.00 | Mar 27, 2025, Open bid tab, SAP 038-602-036 ↗ |
| Stabilized Construction Exit | ls | 6 | $8,500 | $2,500 | $2,500 – $8,500 | Mar 27, 2025, Open bid tab, SAP 038-602-036 ↗ |
| Remove Sign | each | 6 | $78.00 | $53.00 | $40.00 – $120.00 | Mar 27, 2025, Open bid tab, SAP 038-602-036 ↗ |
| Stabilizing Aggregate (Cv) | cubic yard | 5 | $42.00 | $42.00 | $35.00 – $42.00 | Mar 14, 2024, Open bid tab, SAP 038-636-001(low) ↗ |
| Salvage Sign Type C | each | 5 | $52.50 | $78.00 | $26.25 – $78.00 | Mar 14, 2024, Open bid tab, SAP 038-636-001(low) ↗ |
| Aggregate Surfacing (Cv) Class 1 | cubic yard | 5 | $46.50 | $62.00 | $46.50 – $62.00 | Feb 20, 2025, Open bid tab, SAP 038-598-009 ↗ |
| Type Sp 12.5 Non Wear Course Mix (3,C) | ton | 5 | $142.00 | $142.00 | $105.00 – $142.00 | Mar 14, 2024, Open bid tab, SAP 038-636-001(low) ↗ |
| Sign Panels Type C | square foot | 5 | $185.00 | $185.00 | $95.00 – $185.00 | Mar 14, 2024, Open bid tab, SAP 038-636-001(low) ↗ |
| Hydraulic Stabilized Fiber Matrix | pound | 5 | $3.00 | $3.00 | $3.00 – $3.40 | Mar 14, 2024, Open bid tab, SAP 038-636-001(low) ↗ |
| Interim Pavement Marking | linear foot | 5 | $0.15 | $0.15 | $0.15 – $0.17 | Mar 27, 2025, Open bid tab, SAP 038-602-036 ↗ |
| 24 inch rc pipe apron | each | 5 | $1,355 | $1,200 | $1,200 – $1,900 | Mar 27, 2025, Open bid tab, SAP 038-602-036 ↗ |
| Asphalt material for shoulder tack | gallon | 5 | $2.90 | $2.45 | $2.45 – $2.90 | Mar 27, 2025, Open bid tab, SAP 038-602-036 ↗ |
| Type Sp 9.5 Wearing Course Mix (3,C) | ton | 5 | $110.00 | $110.00 | $107.00 – $110.00 | Mar 14, 2024, Open bid tab, SAP 038-636-001(low) ↗ |
| Alternate Pedestrian Route | ls | 5 | $15,200 | $15,200 | $15,200 | Mar 14, 2024, Open bid tab, SAP 038-636-001(low) ↗ |
| Common Embankment (Cv) (P) | cubic yard | 5 | $17.00 | $4.60 | $4.60 – $17.00 | Mar 27, 2025, Open bid tab, SAP 038-602-036 ↗ |
| Sawing asphalt pavement (full deep) | linear foot | 5 | $3.40 | $3.00 | $3.00 – $3.50 | Aug 29, 2023, Open bid tab, 038-600-019 ↗ |
| Excavation - Subgrade | cubic yard | 5 | $25.00 | $25.00 | $17.00 – $25.00 | Mar 14, 2024, Open bid tab, SAP 038-636-001(low) ↗ |
| Geotextile Fabric Type 9 | square yard | 5 | $3.00 | $3.00 | $3.00 | Mar 14, 2024, Open bid tab, SAP 038-636-001(low) ↗ |
| Sediment Control Logs Type Compost | linear foot | 4 | — | $4.75 | $4.75 – $7.65 | Aug 8, 2023, Open bid tab, 038-627-003 ↗ |
| Concrete Collar (Manhole) | each | 4 | — | $1,560 | $1,560 | Mar 14, 2024, Open bid tab, SAP 038-636-001(low) ↗ |
| Concrete Collar (Valve Box) | each | 4 | — | $1,200 | $1,200 | Mar 14, 2024, Open bid tab, SAP 038-636-001(low) ↗ |
| 4 inch dble solid line paint | linear foot | 4 | — | $1.05 | $1.05 | Mar 14, 2024, Open bid tab, SAP 038-636-001(low) ↗ |
| Install Sign Type C | each | 4 | — | $128.00 | $128.00 – $600.00 | Aug 29, 2023, Open bid tab, 038-600-019 ↗ |
| Culvert Excavation Class U | cubic yard | 4 | — | $21.00 | $14.90 – $21.00 | Feb 20, 2025, Open bid tab, SAP 038-598-009 ↗ |
| Seed Mixture 25-151 | pound | 4 | — | $9.00 | $9.00 | Mar 14, 2024, Open bid tab, SAP 038-636-001(low) ↗ |