Agency · awarded bid prices

Clay County: awarded unit prices

447 winning bid prices read from 16 source documents, 2022–2026. The table lists the 40 items this agency awarded most often. Winning bids only; every row links to a bid tabulation.

Cost by state › Agencies › Clay County

ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Mobilizationls22—$85,000$5,000 – $222,000Apr 7, 2026, Open bid tab, 526 ↗
Traffic Controlls20—$4,600$2,000 – $85,000Apr 7, 2026, Open bid tab, 526 ↗
Type Sp 12.5 Wearing Course Mix (3,B)ton9—$63.50$46.97 – $318.00Feb 24, 2026, Open bid tab, 126 ↗
4 inch broken line multi complinear foot7$0.4$0.45$0.34 – $5.25Apr 7, 2026, Open bid tab, 526 ↗
Granular Embankment (cv)cubic yard7$28.00$18.00$18.00 – $76.00Jun 3, 2025, Open bid tab, 925 ↗
Remove asphalt pavementsquare yard7$9.25$9.00$9.00 – $50.00Jul 1, 2025, Open bid tab, 1025 ↗
6 inch solid line multi complinear foot6$0.49$0.5$0.47 – $0.51Apr 7, 2026, Open bid tab, 526 ↗
4 inch solid line multi complinear foot6$0.4$0.45$0.34 – $0.45Apr 7, 2026, Open bid tab, 526 ↗
Remove Existing Bridgels6—$18,000$6,000 – $656,000Jun 3, 2025, Open bid tab, 925 ↗
Turf Establishmentls6$2,975$1,565$1,550 – $5,000May 6, 2025, Open bid tab, 325 ↗
Milling asphalt surface (2.0 inch)square yard6$1.38$1.20$1.20 – $3.00Apr 7, 2026, Open bid tab, 526 ↗
24 inch solid line multi complinear foot5$12.00$12.00$6.30 – $39.00Apr 7, 2026, Open bid tab, 526 ↗
Temporary Raised Pavement Markersls5$3,500$2,800$2,500 – $5,000Apr 7, 2026, Open bid tab, 526 ↗
Sediment Control Log Type Strawlinear foot5$4.00$5.00$4.00 – $5.00Jun 3, 2025, Open bid tab, 925 ↗
Sawing asphalt pavementlinear foot5$12.00$2.50$2.25 – $12.00Apr 7, 2026, Open bid tab, 526 ↗
Aggregate Base (Cv) Class 5 (P)cubic yard5$49.50$60.00$49.50 – $85.00Jul 1, 2025, Open bid tab, 1025 ↗
Interim Pavement Markingls5$4,600$6,500$2,500 – $15,625Apr 7, 2026, Open bid tab, 526 ↗
Pavement mssg multi compsquare foot4—$13.00$8.40 – $18.00Apr 7, 2026, Open bid tab, 526 ↗
Remove Metal Culvertlinear foot4—$16.00$16.00 – $20.00Jun 3, 2025, Open bid tab, 925 ↗
Milled Rumble Stripseach4—$750.00$750.00 – $4,375Apr 7, 2026, Open bid tab, 526 ↗
Aggregate Base (Lv) Class 5cubic yard4—$45.00$32.75 – $75.00Mar 18, 2025, Open bid tab, 523 ↗
Concrete Curb & Gutter Design B624linear foot4—$65.00$65.00 – $87.00Jul 2, 2024, Open bid tab, 724 ↗
Rapid Stabilization Method 3thousand gallons4—$1,200$250.00 – $1,200Mar 25, 2025, Open bid tab, 425 ↗
Remove Curb & Gutterlinear foot4—$21.50$11.00 – $21.50May 6, 2025, Open bid tab, 325 ↗
Concrete Box Culvert Transition Sectioneach3—$5,500$5,500 – $8,000Jul 2, 2024, Open bid tab, 724 ↗
Rr Protective Liability Insurancels3—$6,300$5,000 – $7,500Apr 7, 2026, Open bid tab, 526 ↗
Aggregate Surfacing (cv) Class 5cubic yard3—$30.00$30.00Mar 25, 2025, Open bid tab, 425 ↗
Aggregate Surfacing (lv), Class 5cubic yard3—$30.50$30.50 – $65.00Apr 7, 2026, Open bid tab, 526 ↗
Granular Bedding (Cv) (P)cubic yard3—$43.00$43.00Jul 2, 2024, Open bid tab, 724 ↗
Silt Fence, Type HIlinear foot3—$12.00$12.00Jul 2, 2024, Open bid tab, 724 ↗
8 inch concrete driveway pavementsquare yard3—$158.00$118.00 – $159.00Jul 1, 2025, Open bid tab, 1025 ↗
Random Riprap Class IIcubic yard3—$125.00$125.00Mar 25, 2025, Open bid tab, 425 ↗
Rapid Stabilization Method 2acre3—$1.00$1.00Mar 25, 2025, Open bid tab, 425 ↗
Structure Excavation Class U (P)cubic yard3—$12.50$12.50Jul 2, 2024, Open bid tab, 724 ↗
Soil Bed Preparationacre3—$400.00$400.00Mar 25, 2025, Open bid tab, 425 ↗
Granular Backfill (Cv) (P)cubic yard3—$43.00$43.00Jul 2, 2024, Open bid tab, 724 ↗
Milling asphalt surface (3.0 inch)square yard3—$1.70$1.70 – $3.10Apr 7, 2026, Open bid tab, 526 ↗
Random Riprap Class IIIcubic yard3—$235.00$155.00 – $235.00Jul 1, 2025, Open bid tab, 1025 ↗
Concrete Curb & Gutter Design B618linear foot3—$27.00$27.00 – $75.00Jul 1, 2025, Open bid tab, 1025 ↗
Seedingacre3—$777.00$777.00 – $10,000Jul 1, 2025, Open bid tab, 1025 ↗

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.

More prices in Minnesota: statewide figures.