| Traffic Control | ls | 42 | $3,125 | $4,000 | $1,300 – $25,000 | May 12, 2026, Open bid tab, SP 004-070-050 ↗ |
| Mobilization | ls | 42 | $18,210 | $20,000 | $2,400 – $295,000 | May 12, 2026, Open bid tab, SP 004-070-050 ↗ |
| 6 inch solid line paint | linear foot | 31 | $0.14 | $0.12 | $0.09 – $0.2 | Mar 10, 2026, Open bid tab, SAP 004-030-016 ↗ |
| 24 inch solid line paint | linear foot | 27 | $6.00 | $10.00 | $3.50 – $10.00 | Apr 14, 2026, Open bid tab, SAP 004-607-026 ↗ |
| 6 inch broken line paint | linear foot | 26 | $0.14 | $0.12 | $0.09 – $0.18 | Mar 10, 2026, Open bid tab, SAP 004-030-016 ↗ |
| Shoulder Base Aggregate Class 1 | ton | 25 | $22.00 | $30.50 | $14.94 – $50.00 | Feb 3, 2026, Open bid tab, 2026-01 ↗ |
| Maintenance and restoration of haul roads | ls | 21 | $1.00 | $500.00 | $1.00 – $500.00 | Apr 14, 2026, Open bid tab, SAP 004-607-026 ↗ |
| 6 inch solid line paint (p) | linear foot | 16 | $0.12 | $0.12 | $0.09 – $0.18 | Mar 10, 2026, Open bid tab, SAP 004-030-016 ↗ |
| Pavement Message Paint | square foot | 15 | $4.00 | $6.00 | $3.50 – $10.00 | Mar 10, 2026, Open bid tab, SAP 004-030-016 ↗ |
| Milled Sinusoidal Rumble Strips-intermittent | linear foot | 14 | $0.17 | $0.17 | $0.16 – $0.25 | Feb 3, 2026, Open bid tab, 2026-01 ↗ |
| Interim Pavement Marking (P) | linear foot | 12 | — | $2.00 | $0.15 – $3.00 | Feb 3, 2026, Open bid tab, 2026-01 ↗ |
| Asphalt material for shoulder tack | gallon | 12 | $3.00 | $2.10 | $2.10 – $10.00 | Mar 18, 2025, Open bid tab, 2025-1 ↗ |
| 4 inch solid line paint | linear foot | 12 | — | $3.00 | $0.07 – $3.00 | Apr 14, 2026, Open bid tab, SAP 004-607-026 ↗ |
| Interim Pavement Marking | linear foot | 11 | $0.24 | $0.15 | $0.15 – $0.24 | Mar 18, 2025, Open bid tab, 2025-1 ↗ |
| Type SP 12.5 Wearing Course Mixture (3,C) | ton | 10 | $61.67 | $62.00 | $55.40 – $350.00 | Feb 3, 2026, Open bid tab, 2026-01 ↗ |
| Relocate Mail BOX Support | each | 9 | $100.00 | $10.00 | $10.00 – $120.00 | Feb 3, 2026, Open bid tab, 2026-01 ↗ |
| Type SP 12.5 Wearing Course Mixture (3,B) | ton | 8 | $54.50 | $62.00 | $42.00 – $62.00 | Feb 3, 2026, Open bid tab, 2026-01 ↗ |
| Aggregate base class 5 modified | ton | 8 | $19.18 | $14.70 | $12.75 – $20.00 | Feb 3, 2026, Open bid tab, 2026-01 ↗ |
| Subgrade Preparation | rdst | 8 | $170.00 | $170.00 | $162.00 – $245.00 | Mar 18, 2025, Open bid tab, 2025-1 ↗ |
| Mail Box Support | each | 8 | $110.00 | $220.00 | $105.00 – $220.00 | May 12, 2026, Open bid tab, SP 004-070-050 ↗ |
| Asphalt material for fog seal | gallon | 7 | $3.25 | $5.80 | $2.10 – $5.80 | Mar 10, 2026, Open bid tab, SAP 004-030-016 ↗ |
| Rolled Erosion Prevention Category 25 | square yard | 7 | $2.50 | $4.00 | $1.49 – $4.00 | Apr 14, 2026, Open bid tab, SAP 004-607-026 ↗ |
| Silt Fence, Type MS | linear foot | 7 | $3.00 | $3.00 | $2.00 – $4.00 | Apr 14, 2026, Open bid tab, SAP 004-607-026 ↗ |
| Concrete Curb and Gutter Design B624 | linear foot | 6 | $32.88 | $43.75 | $19.85 – $85.00 | Apr 14, 2026, Open bid tab, SAP 004-607-026 ↗ |
| Type SP 9.5 Wearing Course Mixture (3,C) | ton | 6 | $62.30 | $110.85 | $57.10 – $110.85 | Apr 14, 2026, Open bid tab, SAP 004-607-026 ↗ |
| Common Embankment (Cv) (P) | cubic yard | 6 | $2.50 | $19.83 | $1.20 – $19.83 | Apr 14, 2026, Open bid tab, SAP 004-607-026 ↗ |
| Excavation Common **P** | cubic yard | 6 | $13.80 | $15.00 | $3.95 – $15.00 | Apr 14, 2026, Open bid tab, SAP 004-607-026 ↗ |
| Remove Curb and Gutter | linear foot | 6 | $5.00 | $5.00 | $5.00 – $15.34 | Apr 14, 2026, Open bid tab, SAP 004-607-026 ↗ |
| Stabilized full deep reclamation (p) | square yard | 5 | $1.58 | $1.30 | $1.30 – $3.15 | Mar 18, 2025, Open bid tab, 2025-1 ↗ |
| Seeding (P) | acre | 5 | $500.00 | $79.00 | $79.00 – $500.00 | Feb 3, 2026, Open bid tab, 2026-01 ↗ |
| Milled Sinusoidal Rumble Strips-Interm | linear foot | 5 | $0.15 | $0.1 | $0.1 – $0.3 | May 3, 2022, Open bid tab, 2022-3 ↗ |
| Remove asphalt pavement (p) | square yard | 5 | $3.55 | $1.95 | $1.95 – $4.25 | Feb 3, 2026, Open bid tab, 2026-01 ↗ |
| Remove Concrete Driveway Pavement | square yard | 5 | $20.00 | $10.00 | $10.00 – $40.00 | Feb 3, 2026, Open bid tab, 2026-01 ↗ |
| Sediment Control Log Type Compost | linear foot | 5 | $5.00 | $3.00 | $3.00 – $5.00 | Apr 14, 2026, Open bid tab, SAP 004-607-026 ↗ |
| Flotation Silt Curtain Type Moving Water | linear foot | 5 | $20.00 | $17.00 | $17.00 – $25.00 | Feb 3, 2026, Open bid tab, 2026-01 ↗ |
| Remove pipe culvert | linear foot | 5 | $10.00 | $15.00 | $8.00 – $15.00 | Apr 14, 2026, Open bid tab, SAP 004-607-026 ↗ |
| Fertilizer Type 3 | pound | 5 | $1.00 | $0.79 | $0.79 – $1.00 | Feb 3, 2026, Open bid tab, 2026-01 ↗ |
| Turf Establishment | ls | 5 | $2,000 | $850.00 | $850.00 – $5,675 | Jul 30, 2024, Open bid tab, SP 004-612-023 ↗ |
| Erosion Control Supervisor | ls | 5 | $2,000 | $1,500 | $1,000 – $10,000 | Apr 14, 2026, Open bid tab, SAP 004-607-026 ↗ |
| Water | thousand gallons | 5 | $35.00 | $25.00 | $25.00 – $35.00 | Feb 3, 2026, Open bid tab, 2026-01 ↗ |