| Traffic Control | ls | 67 | $4,800 | $4,800 | $1,000 – $25,000 | Mar 20, 2025, Open bid tab, 318 ↗ |
| Mobilization | ls | 67 | $8,900 | $33,000 | $1,000 – $350,000 | Mar 20, 2025, Open bid tab, 318 ↗ |
| Asphalt material for tack coat | gallon | 58 | $2.00 | $2.00 | $1.00 – $2.50 | Mar 20, 2025, Open bid tab, 318 ↗ |
| Maintenance and restoration of haul roads | ls | 45 | $1.00 | $1.00 | $1.00 – $1,500 | Mar 20, 2025, Open bid tab, 318 ↗ |
| Aggregate Surfacing Class 1 | ton | 44 | $22.80 | $31.00 | $16.00 – $40.00 | Mar 20, 2025, Open bid tab, 318 ↗ |
| Type Sp 9.5 Wearing Course Mixture (2,B) | ton | 43 | $57.00 | $57.85 | $49.50 – $104.00 | Mar 20, 2025, Open bid tab, 318 ↗ |
| 4 inch solid line paint | linear foot | 43 | $0.1 | $0.11 | $0.053 – $1.00 | Mar 20, 2025, Open bid tab, 319 ↗ |
| 6 inch solid line paint | linear foot | 42 | $0.14 | $0.15 | $0.075 – $1.00 | Mar 20, 2025, Open bid tab, 319 ↗ |
| Raised Pavement Marker Temporary | each | 40 | $1.88 | $5.00 | $1.00 – $5.00 | Mar 20, 2025, Open bid tab, 318 ↗ |
| 4 inch broken line paint | linear foot | 40 | $0.1 | $0.11 | $0.053 – $1.00 | Mar 20, 2025, Open bid tab, 319 ↗ |
| Milling notches | ls | 38 | $1,500 | $3,900 | $500.00 – $4,500 | Mar 20, 2025, Open bid tab, 318 ↗ |
| Interim Pavement Marking | linear foot | 35 | — | $1.00 | $0.1 – $2.50 | Mar 20, 2025, Open bid tab, 318 ↗ |
| Common Topsoil Borrow | cubic yard | 20 | $30.50 | $39.00 | $20.00 – $65.00 | Mar 20, 2025, Open bid tab, 318 ↗ |
| Soil Bed Preparation | acre | 20 | $500.00 | $500.00 | $20.00 – $995.00 | Mar 20, 2025, Open bid tab, 318 ↗ |
| Full deep reclamation | square yard | 20 | $5.00 | $1.85 | $1.12 – $11.60 | Feb 6, 2025, Open bid tab, 320 ↗ |
| Hydraulic Bonded Fiber Matrix | pound | 19 | $1.75 | $1.50 | $1.50 – $4.00 | Mar 20, 2025, Open bid tab, 318 ↗ |
| Seeding | acre | 19 | $500.00 | $500.00 | $225.00 – $995.00 | Mar 20, 2025, Open bid tab, 318 ↗ |
| Shoulder Preparation | square yard | 18 | $6.00 | $13.00 | $3.00 – $68.00 | Mar 20, 2025, Open bid tab, 319 ↗ |
| Fertilizer Type 3 | pound | 18 | $1.00 | $0.85 | $0.75 – $1.05 | Mar 20, 2025, Open bid tab, 318 ↗ |
| Milling asphalt surface (1.5 inch) | square yard | 18 | $1.77 | $1.25 | $0.8 – $11.81 | Mar 20, 2025, Open bid tab, 319 ↗ |
| Silt Fence, Type MS | linear foot | 18 | $3.00 | $2.10 | $2.10 – $4.22 | Jan 16, 2025, Open bid tab, 317 ↗ |
| Sediment Control Log Type Wood Chip | linear foot | 16 | $3.17 | $6.00 | $2.10 – $6.00 | Feb 6, 2025, Open bid tab, 320 ↗ |
| Crawler Mounted Backhoe | hour | 15 | $250.00 | $250.00 | $200.00 – $375.00 | Jan 16, 2025, Open bid tab, 317 ↗ |
| Rapid Stabilization Method 3 | thousand gallons | 15 | $500.00 | $448.00 | $300.00 – $695.00 | Jan 16, 2025, Open bid tab, 317 ↗ |
| Crushed Rock (Cv) | cubic yard | 14 | $39.00 | $74.00 | $29.00 – $85.00 | Jan 16, 2025, Open bid tab, 317 ↗ |
| Geotextile Filter Type 7 | square yard | 14 | $4.00 | $5.00 | $2.00 – $20.00 | Nov 7, 2024, Open bid tab, 316 ↗ |
| Aggregate Surfacing Class 1 (B) | ton | 13 | $21.00 | $18.00 | $17.00 – $42.00 | Mar 20, 2025, Open bid tab, 319 ↗ |
| Remove Concrete Driveway Pavement | square yard | 13 | $30.00 | $40.00 | $6.00 – $100.00 | Mar 20, 2025, Open bid tab, 318 ↗ |
| Seed Mixture 25-142 | pound | 12 | $5.00 | $5.00 | $3.50 – $6.55 | Nov 7, 2024, Open bid tab, 316 ↗ |
| Culvert Excavation Class U | cubic yard | 12 | $6.25 | $9.50 | $3.50 – $9.50 | Jan 16, 2025, Open bid tab, 317 ↗ |
| Dozer | hour | 12 | $200.00 | $195.00 | $175.00 – $250.00 | Jan 16, 2025, Open bid tab, 317 ↗ |
| 6 inch concrete driveway pavement | square yard | 12 | $107.50 | $170.00 | $60.00 – $250.00 | Mar 20, 2025, Open bid tab, 318 ↗ |
| Random Riprap Class III | cubic yard | 12 | $65.50 | $75.00 | $55.00 – $105.00 | Nov 7, 2024, Open bid tab, 316 ↗ |
| Seed Mixture 21-111 | pound | 11 | $0.95 | $1.00 | $0.65 – $1.00 | Nov 7, 2024, Open bid tab, 316 ↗ |
| Aggregate Surfacing Class 2 | ton | 11 | $40.00 | $60.00 | $25.00 – $60.00 | Feb 8, 2024, Open bid tab, 314 ↗ |
| Remove pipe culvert | linear foot | 11 | $12.00 | $12.65 | $5.00 – $20.00 | Jan 16, 2025, Open bid tab, 317 ↗ |
| Remove asphalt pavement | square yard | 11 | $3.10 | $10.00 | $1.75 – $13.00 | Jan 16, 2025, Open bid tab, 317 ↗ |
| Erosion Control Supervisor | ls | 11 | — | $500.00 | $110.00 – $1,500 | Jan 16, 2025, Open bid tab, 317 ↗ |
| Maintenance & restoration of haul roads | ls | 10 | $1.00 | $1.00 | $1.00 | Mar 20, 2025, Open bid tab, 319 ↗ |
| Geotextile Fabric Type 5 | square yard | 10 | $2.00 | $4.50 | $1.70 – $5.50 | Jan 16, 2025, Open bid tab, 317 ↗ |