| Mobilization | ls | 15 | $28,500 | $2,300 | $1,000 – $85,000 | May 4, 2026, Open bid tab, 2026-2 ↗ |
| Traffic Control | ls | 13 | $1,900 | $1,000 | $1,000 – $4,400 | May 4, 2026, Open bid tab, 2026-2 ↗ |
| Shoulder base aggregate class 5 modified | ton | 11 | $27.35 | $24.75 | $18.00 – $50.00 | May 19, 2025, Open bid tab, 2025-2 ↗ |
| Maintenance & restoration of haul roads | ls | 11 | $1.00 | $1.00 | $1.00 | May 19, 2025, Open bid tab, 2025-2 ↗ |
| 6 inch solid line paint | linear foot | 10 | $0.15 | $0.15 | $0.15 | May 19, 2025, Open bid tab, 2025-2 ↗ |
| Quality Management - Intelligent Compaction | ls | 10 | $2,500 | $1,500 | $1,500 – $2,500 | May 19, 2025, Open bid tab, 2025-2 ↗ |
| Quality Management - Thermal Profiling | ls | 10 | $2,500 | $1,500 | $1,500 – $2,500 | May 19, 2025, Open bid tab, 2025-2 ↗ |
| 24 inch solid line paint | linear foot | 10 | $20.00 | $20.00 | $20.00 | May 19, 2025, Open bid tab, 2025-2 ↗ |
| 4 inch solid line paint | linear foot | 10 | $0.12 | $0.12 | $0.12 | May 19, 2025, Open bid tab, 2025-2 ↗ |
| Interim Pavement Marking | ls | 10 | $5,000 | $12,800 | $3,000 – $12,800 | May 19, 2025, Open bid tab, 2025-2 ↗ |
| 4 inch broken line paint | linear foot | 9 | $0.12 | $0.12 | $0.12 | May 19, 2025, Open bid tab, 2025-2 ↗ |
| Type Sp 12.5 Wearing Course Mix (3,B) | ton | 9 | $64.28 | $62.00 | $55.72 – $135.00 | May 19, 2025, Open bid tab, 2025-2 ↗ |
| Milling asphalt surface (1.5 inch) | square yard | 8 | $12.47 | $1.20 | $1.20 – $25.00 | May 19, 2025, Open bid tab, 2025-2 ↗ |
| Type Sp 4.75 Wearing Course Mix (3,B) | ton | 4 | — | $88.00 | $81.00 – $91.97 | May 19, 2025, Open bid tab, 2025-2 ↗ |
| Turf Establishment | ls | 3 | — | $1,320 | $1,320 – $2,000 | May 4, 2026, Open bid tab, 2026-2 ↗ |
| Milling asphalt surface (2.0 inch) | square yard | 3 | — | $20.00 | $10.00 – $20.00 | Feb 27, 2024, Open bid tab, 20241 ↗ |
| Rolled Erosion Prevention Category 74 | square yard | 2 | — | $30.00 | $30.00 | Jun 30, 2025, Open bid tab, 2025-5 ↗ |
| Floor Drain Type B706 Modified | each | 2 | — | $600.00 | $600.00 – $2,400 | Jun 30, 2025, Open bid tab, 2025-5 ↗ |
| Type S (TL-4) Barrier Concrete (3S52) | linear foot | 2 | — | $140.00 | $140.00 | Jun 30, 2025, Open bid tab, 2025-5 ↗ |
| Rapid Stabilization Method 1 | acre | 2 | — | $1,000 | $1,000 | Jun 30, 2025, Open bid tab, 2025-5 ↗ |
| Pile points 12 inch | each | 2 | — | $350.00 | $350.00 | Jun 30, 2025, Open bid tab, 2025-5 ↗ |
| Bridge Slab Concrete (3YHPC-M) | square foot | 2 | — | $45.00 | $45.00 | Jun 30, 2025, Open bid tab, 2025-5 ↗ |
| Aggregate Surfacing (cv) Class 5 | cubic yard | 2 | — | $25.00 | $23.50 – $25.00 | Jun 30, 2025, Open bid tab, 2025-5 ↗ |
| Aggregate base class 5 modified | ton | 2 | — | $17.00 | $15.50 – $17.00 | May 4, 2026, Open bid tab, 2026-2 ↗ |
| C-i-p concrete piling 12 inch | linear foot | 2 | — | $38.00 | $38.00 | Jun 30, 2025, Open bid tab, 2025-5 ↗ |
| Structure concrete (3b52) | cubic yard | 2 | — | $1,200 | $1,100 – $1,200 | Jun 30, 2025, Open bid tab, 2025-5 ↗ |
| Reinforced bars (epoxy coated) | pound | 2 | — | $1.50 | $1.50 | Jun 30, 2025, Open bid tab, 2025-5 ↗ |
| Structure steel (3306) | pound | 2 | — | $7.00 | $7.00 | Jun 30, 2025, Open bid tab, 2025-5 ↗ |
| Slope Preparation | ls | 2 | — | $7,000 | $7,000 – $8,000 | Jun 30, 2025, Open bid tab, 2025-5 ↗ |
| Drainage System Type (B910) | ls | 2 | — | $2,500 | $2,500 | Jun 30, 2025, Open bid tab, 2025-5 ↗ |
| Common Embankment (Cv) | cubic yard | 2 | — | $15.00 | $13.50 – $15.00 | Jun 30, 2025, Open bid tab, 2025-5 ↗ |
| Rolled Erosion Prevention Category 20 | square yard | 2 | — | $2.00 | $2.00 | Jun 30, 2025, Open bid tab, 2025-5 ↗ |
| Flotation Silt Curtain Type Moving Water | linear foot | 2 | — | $15.00 | $15.00 | Jun 30, 2025, Open bid tab, 2025-5 ↗ |
| Remove Existing Bridge | ls | 2 | — | $45,000 | $35,000 – $45,000 | Jun 30, 2025, Open bid tab, 2025-5 ↗ |
| Remove pipe culvert | linear foot | 2 | — | $30.00 | $4.00 – $30.00 | May 4, 2026, Open bid tab, 2026-2 ↗ |
| Geotextile Filter Type 7 | square yard | 2 | — | $3.00 | $3.00 | Jun 30, 2025, Open bid tab, 2025-5 ↗ |
| Silt Fence, Type MS | linear foot | 2 | — | $2.00 | $2.00 | Jun 30, 2025, Open bid tab, 2025-5 ↗ |
| Excavation Common | cubic yard | 2 | — | $15.00 | $4.00 – $15.00 | Jun 30, 2025, Open bid tab, 2025-5 ↗ |
| Structure Excavation | ls | 2 | — | $20,000 | $15,000 – $20,000 | Jun 30, 2025, Open bid tab, 2025-5 ↗ |
| Subgrade Correction | cubic yard | 1 | — | $50.00 | $50.00 | Feb 27, 2024, Open bid tab, 20241 ↗ |