City of Faribault: awarded unit prices

2,400 winning bid prices read from 38 source documents, 2019–2026. The table lists the 40 items this agency awarded most often. Winning bids only; every row links to a bid tabulation.

Cost by state › Agencies › City of Faribault

ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Mobilizationls42—$26,040$1,750 – $541,000Apr 22, 2026, Open bid tab, 2026-07 ↗
Traffic Controlls38—$6,000$500.00 – $32,000Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
Storm Drain Inlet Protectioneach35$175.00$175.00$75.00 – $300.00Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
Remove Curb & Gutterlinear foot32$5.00$2.00$1.25 – $25.00Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
Concrete Curb & Gutter Design B618linear foot32$33.27$31.50$18.75 – $100.00Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
6 inch concrete walksquare foot30$12.45$9.55$7.30 – $27.00Apr 22, 2026, Open bid tab, 2026-07 ↗
Truncated Domessquare foot30$67.00$65.00$41.50 – $100.00Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
4 inch concrete walksquare foot24$10.30$7.45$6.50 – $18.00Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
Stabilized Construction Exitls23$1,000$1,250$360.00 – $14,250Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
Remove asphalt pavementsquare yard22$4.00$3.40$2.00 – $12.00Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
Silt Fence, Type MSlinear foot22$3.00$3.00$2.00 – $4.00Jun 18, 2025, Open bid tab, 2025-05 ↗
Excavation Common **P**cubic yard20$16.00$25.00$5.00 – $39.00Apr 22, 2026, Open bid tab, 2026-07 ↗
Aggregate Base (Cv) Class 5 (P)cubic yard18$34.08$32.15$24.00 – $63.00Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
Adjust Frame & Ring Castingeach18$823.95$1,000$375.00 – $1,450Jun 18, 2025, Open bid tab, 2025-05 ↗
Remove Sewer Pipe (Storm)linear foot17$8.00$4.50$4.00 – $35.00Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
Excavation - Subgradecubic yard17$9.75$13.30$0.01 – $32.50Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
Adjust Gate Valve BOXeach17$300.00$452.00$125.00 – $500.00Mar 18, 2026, Open bid tab, 2026-02 ↗
Trench Stabilization Material (Cv)cubic yard16—$25.90$0.01 – $30.00Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
Construction drainage structure design specialeach15$2,950$2,749$1,800 – $4,185Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
Common Topsoil Borrowcubic yard15$20.00$51.10$0.01 – $51.10Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
Type Sp 9.5 Wearing Course Mix (3,B)ton15$85.55$82.79$79.50 – $92.00Apr 16, 2025, Open bid tab, 2025-02 ↗
Connect to Existing Water Maineach15$1,500$2,012$700.00 – $10,000Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
Seeding (W/ Topsoil And Fertilizer)linear foot14$4.40$9.50$3.25 – $9.50Mar 18, 2026, Open bid tab, 2026-02 ↗
Sodding Type Lawnsquare yard14$10.00$7.00$7.00 – $24.00Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
Adjust Frame & Ring Casting Sanitaryeach13$675.00$905.00$429.90 – $1,200Mar 18, 2026, Open bid tab, 2026-02 ↗
Remove Concrete Sidewalksquare foot13$1.75$2.00$0.75 – $4.00Jun 18, 2025, Open bid tab, 2025-05 ↗
Milling asphalt surface type 1square yard12$1.69$3.00$1.30 – $3.00Mar 18, 2026, Open bid tab, 2026-02 ↗
Select Granular Embankment (Cv)cubic yard12$23.90$23.90$14.00 – $38.00Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
6 inch gate valve & boxeach12$2,564$2,628$1,365 – $4,200Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
Connect to Existing Storm Sewereach12$837.50$875.00$425.00 – $2,000Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
Concrete Curb & Gutter Design B624linear foot12$35.98$25.60$23.00 – $55.00Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
Ductile iron fittingpound12$12.68$17.10$0.01 – $18.25Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
Pavement mssg multi compsquare foot11$13.40$14.00$8.00 – $19.00Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
4 inch solid line multi complinear foot11$2.60$2.60$0.6 – $3.00Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
Remove Water Mainlinear foot11—$1.00$1.00 – $25.00Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
Connect TO Existing Sanitary Sewereach11$1,305$1,106$550.00 – $5,000Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
6 inch pvc water mainlinear foot11$50.00$48.35$37.00 – $75.00Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
8 inch pvc pipe sewerlinear foot11$54.70$54.70$34.50 – $90.00Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
Remove Catch Basineach11$300.00$250.00$130.00 – $475.00Apr 8, 2026, Open bid tab, 2026-03 & 2026-06 ↗
Repair Drainage Structureeach10$1,400$1,675$257.90 – $1,675Mar 18, 2026, Open bid tab, 2026-02 ↗

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.

More prices in Minnesota: statewide figures.