MnDOT: awarded unit prices

145,390 winning bid prices read from 1,753 source documents, 2016–2026. The table lists the 40 items this agency awarded most often. Winning bids only; every row links to a bid tabulation.

Cost by state › Agencies › MnDOT

ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Traffic Controlls1,606—$2,062$1.00 – $11,031,300Oct 28, 2026, Open the source page, contract 260353
Mobilizationls1,575—$20,000$1,650 – $16,502,000Oct 28, 2026, Open the source page, contract 260353
Excavation Commoncubic yard992$12.45$15.00$1.00 – $450.00Sep 23, 2026, Open the source page, contract 260109
Common Embankment (Cv)cubic yard981$8.50$12.00$0.01 – $650.00Sep 23, 2026, Open the source page, contract 260109
As Builtls976$5,700$12,000$5.00 – $348,600Sep 23, 2026, Open the source page, contract 260113
Maintenance and restoration of haul roadsls948—$1.00$0.01 – $231,990Sep 23, 2026, Open the source page, contract 260113
Sawing asphalt pavement (full deep)linear foot921$2.25$4.00$0.01 – $33.00Sep 23, 2026, Open the source page, contract 260109
Storm Drain Inlet Protectioneach874$172.25$156.00$1.00 – $3,367Sep 23, 2026, Open the source page, contract 260109
Seedingacre860$315.00$542.50$1.00 – $25,000Oct 28, 2026, Open the source page, contract 260353
Remove asphalt pavementsquare yard816$5.08$5.00$0.01 – $220.62Sep 23, 2026, Open the source page, contract 260109
Soil Bed Preparationacre747$250.00$1,085$1.00 – $62,700Oct 28, 2026, Open the source page, contract 260353
Culvert End Controlseach725$150.00$95.00$10.00 – $2,500Sep 23, 2026, Open the source page, contract 260113
Casting Assemblyeach722$900.00$1,332$102.06 – $4,500Sep 23, 2026, Open the source page, contract 260109
Fertilizer Type 3pound702$0.95$2.00$0.25 – $143.00Sep 23, 2026, Open the source page, contract 260109
Sediment Control Log Type Compostlinear foot660$3.40$3.26$0.9 – $25.00Oct 28, 2026, Open the source page, contract 260353
Stabilized Construction Exitls626$2,295$1,000$0.01 – $775,000Sep 23, 2026, Open the source page, contract 260109
Remove Curb and Gutterlinear foot595$6.00$7.00$1.20 – $1,000Sep 23, 2026, Open the source page, contract 260109
End Treatment-tangent Terminaleach546$3,000$4,000$60.00 – $13,550Sep 23, 2026, Open the source page, contract 260113
Fine Aggregate Bedding (Cv)cubic yard543$40.00$51.60$0.01 – $470.36Sep 23, 2026, Open the source page, contract 260113
Select Granular Embankment (Cv)cubic yard536$21.35$24.05$0.01 – $121.00Sep 23, 2026, Open the source page, contract 260113
Truncated Domessquare foot531$55.00$55.00$23.76 – $150.00Sep 23, 2026, Open the source page, contract 260109
Remove Guardrail-plate Beamlinear foot529$5.33$12.50$1.05 – $82.00Sep 23, 2026, Open the source page, contract 260117
Remove pipe culvertlinear foot527$15.00$27.00$2.79 – $894.78Sep 23, 2026, Open the source page, contract 260109
Silt Fence, Type MSlinear foot520$2.19$2.00$0.5 – $14.78Sep 23, 2026, Open the source page, contract 260113
Aggregate Base (Cv) Class 6cubic yard516$37.50$35.44$8.65 – $240.00Sep 23, 2026, Open the source page, contract 260117
Reinforced bars (epoxy coated)pound500$1.65$2.00$0.9 – $55.00Aug 26, 2026, Open the source page, contract 260115
Drill and grout reinforced bar (epoxy coated)each499$15.00$33.00$0.01 – $150.00Sep 23, 2026, Open the source page, contract 260109
Traffic Barrier Design Type 31linear foot498$28.05$50.00$1.75 – $260.00Sep 23, 2026, Open the source page, contract 260113
Sawing concrete pavement (full deep)linear foot493$5.00$6.00$0.01 – $30.00Sep 23, 2026, Open the source page, contract 260109
4 inch solid line multi-component ground in (wr)linear foot488$0.9$0.9$0.42 – $100.00Sep 23, 2026, Open the source page, contract 260113
Mobile Retroreflectometer Measurementslinear foot488—$0.01$0.01 – $3.95Sep 23, 2026, Open the source page, contract 260113
Random Riprap Class IIIcubic yard485$100.00$104.00$30.00 – $1,110Sep 23, 2026, Open the source page, contract 260109
Guide Post Type Beach471$70.00$135.00$28.50 – $500.00Aug 26, 2026, Open the source page, contract 260123
6 inch solid line multi-component ground in (wr)linear foot463$1.36$2.20$0.57 – $25.00Sep 23, 2026, Open the source page, contract 260109
6 inch concrete walksquare foot451$10.00$12.10$4.75 – $75.00Sep 23, 2026, Open the source page, contract 260109
Interim Pavement Markingls450$12,017$12,655$0.01 – $301,500Aug 26, 2026, Open the source page, contract 260351
Concrete Curb and Gutter Design B424linear foot429$32.55$41.70$12.51 – $303.00Sep 23, 2026, Open the source page, contract 260113
Grubbingacre421$6,729$50,000$320.00 – $57,000Sep 23, 2026, Open the source page, contract 260113
Asphalt patch mixtureton419$188.00$160.00$0.01 – $5,000Sep 23, 2026, Open the source page, contract 260113
Concrete Curb and Gutter Design B624linear foot413$32.20$24.20$0.44 – $210.00Sep 23, 2026, Open the source page, contract 260109

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.

More prices in Minnesota: statewide figures.