| Traffic Control | ls | 9 | $7,000 | $2,000 | $1,700 – $15,000 | Aug 31, 2026, Open bid tab, 2026-3 ↗ |
| Mobilization | ls | 8 | $30,000 | $3,000 | $3,000 – $140,000 | Aug 31, 2026, Open bid tab, 2026-3 ↗ |
| 4 inch solid line paint | linear foot | 7 | $0.11 | $0.11 | $0.11 – $0.2 | Jun 2, 2025, Open bid tab, 2025-2 ↗ |
| Aggregate Surfacing Class 1 | ton | 6 | $28.45 | $24.00 | $23.50 – $62.50 | Apr 20, 2026, Open bid tab, 2026-2 ↗ |
| 4 inch broken line paint | linear foot | 6 | $0.11 | $0.11 | $0.11 – $0.2 | Jun 2, 2025, Open bid tab, 2025-2 ↗ |
| Interim Pavement Marking | ls | 6 | $4,388 | $5,000 | $4,000 – $8,500 | Apr 20, 2026, Open bid tab, 2026-2 ↗ |
| 6 inch solid line paint | linear foot | 5 | $0.14 | $0.14 | $0.14 – $0.18 | Jun 2, 2025, Open bid tab, 2025-2 ↗ |
| Maintenance & restoration of haul roads | ls | 4 | — | $1.00 | $1.00 | Apr 20, 2026, Open bid tab, 2026-2 ↗ |
| Milling asphalt surface (0.5 inch) | square yard | 3 | — | $0.75 | $0.65 – $0.75 | Jun 2, 2025, Open bid tab, 2025-2 ↗ |
| Type Sp 9.5 Wearing Course Mix (2,B) | ton | 3 | — | $67.15 | $62.65 – $67.15 | Jun 2, 2025, Open bid tab, 2025-2 ↗ |
| Maintenance and restoration of haul roads | ls | 3 | — | $1.00 | $1.00 | Jun 2, 2025, Open bid tab, 2025-2 ↗ |
| Stockpile Aggregate (Sv) Class 1 | cubic yard | 2 | — | $3.21 | $3.21 | Mar 18, 2024, Open bid tab, 2024-02 ↗ |
| Shoulder trench | rdst | 2 | — | $60.00 | $60.00 | Jun 2, 2025, Open bid tab, 2025-2 ↗ |
| Aggregate surfacing class 1 modified | ton | 2 | — | $21.50 | $3.21 – $21.50 | Mar 22, 2024, Open bid tab, 2024-5 ↗ |
| Type Sp 12.5 Wearing Course Mixture (2,C) | ton | 2 | — | $90.00 | $70.98 – $90.00 | Jun 3, 2024, Open bid tab, 2024-6 ↗ |
| Type Sp 12.5 Wearing Course Mix (2,B) | ton | 2 | — | $68.00 | $55.58 – $68.00 | Apr 20, 2026, Open bid tab, 2026-2 ↗ |
| 4 inch broken line paint - yellow | linear foot | 2 | — | $0.15 | $0.15 – $0.8 | Apr 20, 2026, Open bid tab, 2026-2 ↗ |
| 4 inch solid line paint - white | linear foot | 2 | — | $0.15 | $0.15 – $0.8 | Apr 20, 2026, Open bid tab, 2026-2 ↗ |
| Milling asphalt surface (2.0 inch) | square yard | 2 | — | $0.9 | $0.9 – $1.81 | Apr 20, 2026, Open bid tab, 2026-2 ↗ |
| Aggregate Base Class 5 | ton | 2 | — | $25.00 | $15.00 – $25.00 | Jun 3, 2024, Open bid tab, 2024-6 ↗ |
| Full deep reclamation | square yard | 2 | — | $3.75 | $2.50 – $3.75 | Jun 3, 2024, Open bid tab, 2024-6 ↗ |
| Salvaged Aggregate (Ev) | cubic yard | 1 | — | $28.50 | $28.50 | Mar 22, 2024, Open bid tab, 2024-5 ↗ |
| 14x6 precast concrete box culvert end section | each | 1 | — | $26,000 | $26,000 | Aug 31, 2026, Open bid tab, 2026-3 ↗ |
| Type Sp 12.5 Non Wearing Course Mixture (2,C) | ton | 1 | — | $70.98 | $70.98 | Mar 22, 2024, Open bid tab, 2024-5 ↗ |
| Rapid Stabilization Method 1 | acre | 1 | — | $8,400 | $8,400 | Aug 31, 2026, Open bid tab, 2026-3 ↗ |
| 14X6 Precast Concrete Box Culvert | linear foot | 1 | — | $1,950 | $1,950 | Aug 31, 2026, Open bid tab, 2026-3 ↗ |
| Granular Backfill (Cv) | cubic yard | 1 | — | $23.00 | $23.00 | Aug 31, 2026, Open bid tab, 2026-3 ↗ |
| Asphalt seal coat | square yard | 1 | — | $0.65 | $0.65 | Feb 9, 2024, Open bid tab, 2024-4 ↗ |
| Random Riprap Class IV | cubic yard | 1 | — | $85.00 | $85.00 | Aug 31, 2026, Open bid tab, 2026-3 ↗ |
| Aggregate Surfacing (cv) Class 5 | cubic yard | 1 | — | $34.00 | $34.00 | Aug 31, 2026, Open bid tab, 2026-3 ↗ |
| Asphalt material for fog seal | gallon | 1 | — | $2.50 | $2.50 | Feb 9, 2024, Open bid tab, 2024-4 ↗ |
| Common Embankment (Cv) | cubic yard | 1 | — | $5.00 | $5.00 | Aug 31, 2026, Open bid tab, 2026-3 ↗ |
| 4 inch solid line paint - yellow | linear foot | 1 | — | $0.15 | $0.15 | Apr 20, 2026, Open bid tab, 2026-2 ↗ |
| Rolled Erosion Prevention Category 20 | square yard | 1 | — | $2.25 | $2.25 | Aug 31, 2026, Open bid tab, 2026-3 ↗ |
| Flotation Silt Curtain Type Moving Water | linear foot | 1 | — | $28.00 | $28.00 | Aug 31, 2026, Open bid tab, 2026-3 ↗ |
| Remove Existing Bridge | ls | 1 | — | $2,000 | $2,000 | Aug 31, 2026, Open bid tab, 2026-3 ↗ |
| Temporary Sediment Trap | each | 1 | — | $500.00 | $500.00 | Aug 31, 2026, Open bid tab, 2026-3 ↗ |
| Temporary Stream Diversion System | ls | 1 | — | $500.00 | $500.00 | Aug 31, 2026, Open bid tab, 2026-3 ↗ |
| Coarse Aggregate Bedding (cv) | cubic yard | 1 | — | $45.00 | $45.00 | Aug 31, 2026, Open bid tab, 2026-3 ↗ |
| Turf Establishment | ls | 1 | — | $2,250 | $2,250 | Aug 31, 2026, Open bid tab, 2026-3 ↗ |