| Mobilization | ls | 7 | $15,000 | $15,000 | $4,080 – $45,000 | Mar 10, 2026, Open bid tab, 26-01 ↗ |
| Asphalt seal coat | square yard | 4 | — | $0.7 | $0.7 – $0.8 | Mar 10, 2026, Open bid tab, 26-01 ↗ |
| Asphalt material for fog seal | gallon | 4 | — | $3.50 | $3.50 – $4.00 | Mar 10, 2026, Open bid tab, 26-01 ↗ |
| Asphalt material for seal coat | gallon | 4 | — | $3.00 | $3.00 – $3.23 | Mar 10, 2026, Open bid tab, 26-01 ↗ |
| Traffic Control | ls | 4 | — | $10,000 | $1,677 – $15,000 | Mar 10, 2026, Open bid tab, 26-01 ↗ |
| Remove asphalt pavement | square yard | 3 | — | $3.75 | $3.75 – $14.15 | May 1, 2024, Open bid tab, 24-01 ↗ |
| Silt Fence, Type MS | linear foot | 3 | — | $2.50 | $2.50 | May 1, 2024, Open bid tab, 24-01 ↗ |
| Aggregate Base Class 5 | ton | 3 | — | $21.50 | $21.50 – $22.50 | May 1, 2024, Open bid tab, 24-01 ↗ |
| Common Excavation (P) | cubic yard | 3 | — | $12.25 | $12.25 – $28.00 | May 1, 2024, Open bid tab, 24-01 ↗ |
| Clearing & Grubbing | each | 3 | — | $625.00 | $625.00 | May 1, 2024, Open bid tab, 24-01 ↗ |
| Geotextile Fabric Type 5 | square yard | 3 | — | $3.15 | $3.15 – $5.65 | May 1, 2024, Open bid tab, 24-01 ↗ |
| Seeding | acre | 3 | — | $4,000 | $4,000 | May 1, 2024, Open bid tab, 24-01 ↗ |
| 4 inch broken line multi comp | linear foot | 2 | — | $2.40 | $1.90 – $2.40 | Apr 10, 2024, Open bid tab, 24-02 ↗ |
| 4 inch dble solid line multi comp | linear foot | 2 | — | $4.80 | $3.80 – $4.80 | Apr 10, 2024, Open bid tab, 24-02 ↗ |
| 4 inch solid line multi comp | linear foot | 2 | — | $2.40 | $1.90 – $2.40 | Apr 10, 2024, Open bid tab, 24-02 ↗ |
| Type Sp 9.5 Wearing Course Mixture (2,C) | ton | 2 | — | $125.00 | $90.00 – $125.00 | Apr 10, 2024, Open bid tab, 23-08 ↗ |
| Sawing asphalt pavement (full deep) | linear foot | 2 | — | $3.55 | $3.55 | Apr 10, 2024, Open bid tab, 23-08 ↗ |
| Concrete Curb & Gutter Design B618 | linear foot | 2 | — | $38.85 | $38.85 – $42.25 | May 1, 2024, Open bid tab, 24-01 ↗ |
| Install Handicap Sign (Include Sign Post) | each | 2 | — | $130.00 | $120.00 – $130.00 | May 1, 2024, Open bid tab, 24-01 ↗ |
| Type Sp 9.5 Wearing Course Mix (3,B) | ton | 2 | — | $94.40 | $89.55 – $94.40 | May 1, 2024, Open bid tab, 24-01 ↗ |
| Aggregate Base Class 5 Modified | ton | 2 | — | $22.50 | $22.50 – $30.50 | May 1, 2024, Open bid tab, 24-01 ↗ |
| Remove tree | each | 2 | — | $625.00 | $625.00 | May 1, 2024, Open bid tab, 24-01 ↗ |
| Storm Drain Inlet Protection | each | 2 | — | $145.00 | $145.00 | May 1, 2024, Open bid tab, 24-01 ↗ |
| 4 inch concrete walk | square foot | 2 | — | $7.45 | $7.45 | May 1, 2024, Open bid tab, 24-01 ↗ |
| Remove Concrete Curb & Gutter | linear foot | 2 | — | $4.85 | $4.85 – $6.10 | May 1, 2024, Open bid tab, 24-01 ↗ |
| Crosswalk Multi Comp | square foot | 1 | — | $7.40 | $7.40 | Apr 10, 2024, Open bid tab, 24-02 ↗ |
| Pavement Message Multi-Component | square foot | 1 | — | $11.00 | $11.00 | Apr 10, 2024, Open bid tab, 24-02 ↗ |
| Grubbing | each | 1 | — | $1,176 | $1,176 | Apr 10, 2024, Open bid tab, 23-08 ↗ |
| Clearing | each | 1 | — | $1,176 | $1,176 | Apr 10, 2024, Open bid tab, 23-08 ↗ |
| 50,30,20 Amp Rv Pedestal With Pad Mount | each | 1 | — | $2,005 | $2,005 | May 1, 2024, Open bid tab, 24-01 ↗ |
| Water Spigot Rv Fixture | each | 1 | — | $1,151 | $1,151 | May 1, 2024, Open bid tab, 24-01 ↗ |
| Watermain Cleanout | each | 1 | — | $1,605 | $1,605 | May 1, 2024, Open bid tab, 24-01 ↗ |
| Flexible Copper Pipe | linear foot | 1 | — | $26.50 | $26.50 | May 1, 2024, Open bid tab, 24-01 ↗ |
| Water Main | linear foot | 1 | — | $35.10 | $35.10 | May 1, 2024, Open bid tab, 24-01 ↗ |
| 5 inch concrete pedestal pad | square foot | 1 | — | $20.00 | $20.00 | May 1, 2024, Open bid tab, 24-01 ↗ |
| Concrete Curb and Gutter Design B618 | linear foot | 1 | — | $38.85 | $38.85 | May 1, 2024, Open bid tab, 24-01 ↗ |
| Remove & Relocate 50,30,20 Amp Rv Pedestal | each | 1 | — | $800.00 | $800.00 | May 1, 2024, Open bid tab, 24-01 ↗ |
| Remove & Relocate Water Spigot | each | 1 | — | $2,500 | $2,500 | May 1, 2024, Open bid tab, 24-01 ↗ |
| Install 2 inch caliper tree | each | 1 | — | $700.00 | $700.00 | May 1, 2024, Open bid tab, 24-01 ↗ |
| Pipe and tube aluminum rail | linear foot | 1 | — | $344.00 | $344.00 | May 1, 2024, Open bid tab, 24-01 ↗ |