Agency · awarded bid prices

Wilkin County: awarded unit prices

107 winning bid prices read from 5 source documents, 2024–2026. The table lists the 40 items this agency awarded most often. Winning bids only; every row links to a bid tabulation.

Cost by state › Agencies › Wilkin County

ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Traffic Controlls7$4,000$2,000$1,900 – $6,000May 20, 2026, Open bid tab, SP 014-598-080, SP 084-620-007 & SAP 084-604-021 ↗
Mobilizationls7—$4,000$4,000 – $50,000May 20, 2026, Open bid tab, SP 014-598-080, SP 084-620-007 & SAP 084-604-021 ↗
Asphalt material for tack coatgallon5—$0.01$0.01 – $15.00Mar 18, 2026, Open bid tab, 2026-001 ↗
6 inch solid line paintlinear foot4—$0.12$0.12 – $0.16Mar 18, 2026, Open bid tab, 2026-001 ↗
Type Sp 9.5 Wearing Course Mix (2,C)ton4—$69.25$62.60 – $69.25Mar 18, 2026, Open bid tab, 2026-001 ↗
Maintenance & restoration of haul roadsls4—$1.00$1.00Mar 18, 2026, Open bid tab, 2026-001 ↗
Motor Graderhour4—$300.00$140.00 – $300.00Mar 18, 2026, Open bid tab, 2026-001 ↗
4 inch broken line paintlinear foot4—$0.1$0.1 – $0.12Mar 18, 2026, Open bid tab, 2026-001 ↗
4 inch solid line paintlinear foot4—$0.1$0.1 – $0.12Mar 18, 2026, Open bid tab, 2026-001 ↗
Interim Pavement Markingls4—$3,000$2,000 – $5,000Mar 18, 2026, Open bid tab, 2026-001 ↗
Aggregate Surfacing (cv) Class 5cubic yard3—$36.45$36.45 – $44.55May 20, 2026, Open bid tab, SP 014-598-080, SP 084-620-007 & SAP 084-604-021 ↗
Granular Embankment (cv)cubic yard3—$29.73$29.73 – $39.16May 20, 2026, Open bid tab, SP 014-598-080, SP 084-620-007 & SAP 084-604-021 ↗
Salvage Aggregate Shouldering (P)square yard2—$2.10$1.10 – $2.10Mar 19, 2025, Open bid tab, 2025-001 ↗
12X10 Precast Concrete BOX Culvertlinear foot2—$2,000$1,500 – $2,000May 20, 2026, Open bid tab, SP 014-598-080, SP 084-620-007 & SAP 084-604-021 ↗
12x10 precast concrete box culvert end sectioneach2—$20,000$20,000 – $31,750May 20, 2026, Open bid tab, SP 014-598-080, SP 084-620-007 & SAP 084-604-021 ↗
Random Riprap Class IVcubic yard2—$120.00$93.00 – $120.00May 20, 2026, Open bid tab, SP 014-598-080, SP 084-620-007 & SAP 084-604-021 ↗
Aggregate surfacing class 1 modifiedton2—$12.20$12.20 – $20.00Mar 19, 2025, Open bid tab, 2025-001 ↗
Type Sp 12.5 Non Wear Course Mix (2,B)ton2—$53.35$53.35 – $61.00Mar 19, 2025, Open bid tab, 2025-001 ↗
Aggregate Surfacing Class 1ton2—$29.15$29.15Mar 18, 2026, Open bid tab, 2026-001 ↗
Coarse Aggregate Bedding (cv)cubic yard2—$82.55$82.55 – $94.50May 20, 2026, Open bid tab, SP 014-598-080, SP 084-620-007 & SAP 084-604-021 ↗
Turf Establishmentls2—$3,460$3,460 – $4,000May 20, 2026, Open bid tab, SP 014-598-080, SP 084-620-007 & SAP 084-604-021 ↗
12x11 precast concrete box culvert end sectioneach1—$35,000$35,000May 20, 2026, Open bid tab, SP 014-598-080, SP 084-620-007 & SAP 084-604-021 ↗
Remove Existing Bridge Cls1—$6,000$6,000May 20, 2026, Open bid tab, SP 014-598-080, SP 084-620-007 & SAP 084-604-021 ↗
12X4 Precast Concrete Box Culvertlinear foot1—$1,500$1,500May 20, 2026, Open bid tab, SP 014-598-080, SP 084-620-007 & SAP 084-604-021 ↗
12x4 precast concrete box culvert end sectioneach1—$12,000$12,000May 20, 2026, Open bid tab, SP 014-598-080, SP 084-620-007 & SAP 084-604-021 ↗
Remove Existing Bridge Bls1—$10,000$10,000May 20, 2026, Open bid tab, SP 014-598-080, SP 084-620-007 & SAP 084-604-021 ↗
Milling asphalt surface (5.0 inch) (p)square yard1—$3.30$3.30Mar 19, 2025, Open bid tab, 2025-001 ↗
Stabilized full deep reclamation (8 inch) (p)square yard1—$1.70$1.70Mar 19, 2025, Open bid tab, 2025-001 ↗
Type Sp 9.5 Non Wear Course Mix (2,C)ton1—$67.00$67.00Mar 20, 2024, Open bid tab, 2024-001 ↗
Stabilized full deep reclamation (6.0 inch) (p)square yard1—$2.00$2.00Mar 20, 2024, Open bid tab, 2024-001 ↗
Type Sp 9.5 Bit Mixture Productionton1—$65.00$65.00Mar 20, 2024, Open bid tab, 2024-001 ↗
Cement Grout (P)cubic yard1—$200.00$200.00Apr 16, 2025, Open bid tab, 2025-002 ↗
Random Riprap Class Iv (P)cubic yard1—$65.00$65.00Apr 16, 2025, Open bid tab, 2025-002 ↗
12x12 precast concrete box culvert end sectioneach1—$32,750$32,750Apr 16, 2025, Open bid tab, 2025-002 ↗
12X12 Precast Concrete BOX Culvertlinear foot1—$1,500$1,500Apr 16, 2025, Open bid tab, 2025-002 ↗
Milling asphalt surface (2.0 inch) (p)square yard1—$1.75$1.75Mar 20, 2024, Open bid tab, 2024-001 ↗
12X11 Precast Concrete Box Culvertlinear foot1—$2,000$2,000May 20, 2026, Open bid tab, SP 014-598-080, SP 084-620-007 & SAP 084-604-021 ↗
2.0 Cu Yd Shovelhour1—$250.00$250.00Apr 16, 2025, Open bid tab, 2025-002 ↗
Type Sp 9.5 Wearing Course Mix (2,B)ton1—$125.00$125.00Mar 20, 2024, Open bid tab, 2024-001 ↗
Granular Backfill (Lv)cubic yard1—$21.00$21.00Apr 16, 2025, Open bid tab, 2025-002 ↗

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.