| Remove Existing Bridge | ls | 12 | $4,000 | $900.00 | $700.00 – $24,000 | Apr 16, 2026, Open bid tab, 26-03 ↗ |
| Traffic Control | ls | 12 | — | $14,000 | $500.00 – $35,000 | Feb 17, 2026, Open bid tab, 26-02 ↗ |
| Mobilization | ls | 12 | — | $11,500 | $11,500 – $230,000 | Feb 17, 2026, Open bid tab, 26-02 ↗ |
| Aggregate Surfacing Class 5 | ton | 11 | $20.50 | $23.00 | $15.00 – $23.00 | Apr 16, 2026, Open bid tab, 26-03 ↗ |
| Random Riprap Class Iii | ton | 10 | $55.50 | $75.00 | $48.00 – $75.00 | Apr 16, 2026, Open bid tab, 26-03 ↗ |
| Rolled Erosion Prevention Category 25 | square yard | 10 | $2.25 | $2.35 | $1.83 – $2.70 | Apr 16, 2026, Open bid tab, 26-03 ↗ |
| Coarse Filter Aggregate | ton | 7 | $38.00 | $34.00 | $29.50 – $42.00 | Apr 16, 2026, Open bid tab, 26-03 ↗ |
| Turf Establishment (P) | ls | 7 | $700.00 | $700.00 | $500.00 – $750.00 | Apr 16, 2026, Open bid tab, 26-03 ↗ |
| Granular Backfill | ton | 7 | $19.00 | $19.00 | $13.50 – $23.00 | Apr 16, 2026, Open bid tab, 26-03 ↗ |
| Sediment Control Log Type Straw | linear foot | 7 | $3.10 | $3.25 | $3.00 – $3.25 | Apr 16, 2026, Open bid tab, 26-03 ↗ |
| Shoulder Base Aggregate Class 1 | ton | 6 | $22.23 | $21.20 | $16.05 – $33.90 | May 23, 2024, Open bid tab, 24-01 ↗ |
| 4 inch broken line paint | linear foot | 6 | $0.13 | $0.13 | $0.063 – $0.16 | May 23, 2024, Open bid tab, 24-01 ↗ |
| 4 inch solid line paint | linear foot | 6 | $0.13 | $0.13 | $0.063 – $0.16 | May 23, 2024, Open bid tab, 24-01 ↗ |
| Type Sp 4.75 Wearing Course Mix (2,B) | ton | 5 | $84.61 | $84.39 | $64.00 – $105.00 | May 23, 2024, Open bid tab, 24-01 ↗ |
| Type Sp 9.5 Wearing Course Mix (2,B) | ton | 5 | $61.11 | $61.11 | $50.00 – $74.65 | May 23, 2024, Open bid tab, 24-01 ↗ |
| Interim Pavement Marking | linear foot | 5 | $0.1 | $0.1 | $0.1 – $1.00 | May 23, 2024, Open bid tab, 24-01 ↗ |
| Milling asphalt surface (2.0 inch) | square yard | 5 | $5.65 | $5.65 | $2.00 – $15.00 | May 23, 2024, Open bid tab, 24-01 ↗ |
| Silt Fence, Type MS | linear foot | 5 | $2.00 | $2.00 | $2.00 – $2.50 | May 30, 2023, Open bid tab, 23-02 ↗ |
| Pile points 12 inch | each | 4 | — | $231.00 | $231.00 – $300.00 | Sep 29, 2020, Open bid tab, 20-03 ↗ |
| C-i-p concrete piling 12 inch | linear foot | 4 | — | $17.00 | $17.00 – $23.00 | Sep 29, 2020, Open bid tab, 20-03 ↗ |
| Raised Pavement Marker Temporary | each | 4 | — | $4.92 | $4.92 – $5.00 | May 23, 2024, Open bid tab, 24-01 ↗ |
| Slope Preparation | ls | 4 | — | $4,000 | $3,000 – $4,000 | Sep 29, 2020, Open bid tab, 20-03 ↗ |
| 16X6 Precast Concrete Box Culvert | linear foot | 4 | — | $2,050 | $2,050 – $2,150 | Mar 15, 2024, Open bid tab, 23-01 ↗ |
| 16x6 precast concrete box culvert end section | each | 4 | — | $18,000 | $18,000 – $18,500 | Mar 15, 2024, Open bid tab, 23-01 ↗ |
| Excavation Common **P** | cubic yard | 4 | — | $3.00 | $3.00 – $14.90 | Feb 17, 2026, Open bid tab, 26-02 ↗ |
| Turf Establishment | ls | 4 | — | $5,000 | $2,000 – $5,000 | Feb 17, 2026, Open bid tab, 26-02 ↗ |
| Salvage Sign | each | 4 | — | $35.00 | $35.00 – $50.00 | May 30, 2023, Open bid tab, 23-02 ↗ |
| 16x7 precast concrete box culvert end section | each | 3 | — | $22,000 | $22,000 | Mar 15, 2024, Open bid tab, 23-01 ↗ |
| 16X7 Precast Concrete Box Culvert | linear foot | 3 | — | $2,100 | $2,100 | Mar 15, 2024, Open bid tab, 23-01 ↗ |
| Milled Rumble Strips | each | 3 | — | $780.00 | $780.00 | May 23, 2024, Open bid tab, 24-01 ↗ |
| Bridge Slab Concrete (3YHPC-M) | square foot | 3 | — | $34.00 | $23.00 – $34.00 | Sep 29, 2020, Open bid tab, 20-03 ↗ |
| 6 inch solid line paint | linear foot | 3 | — | $0.18 | $0.094 – $0.18 | May 30, 2023, Open bid tab, 23-02 ↗ |
| Structure concrete (3b52) | cubic yard | 3 | — | $592.00 | $592.00 – $700.00 | Sep 29, 2020, Open bid tab, 20-03 ↗ |
| Random Riprap Class Iv | ton | 3 | — | $75.00 | $45.00 – $75.00 | Apr 16, 2026, Open bid tab, 26-03 ↗ |
| Dozer | hour | 3 | — | $165.00 | $110.00 – $165.00 | Sep 29, 2020, Open bid tab, 20-03 ↗ |
| Common Embankment (Cv) | cubic yard | 3 | — | $27.00 | $14.25 – $27.00 | Apr 16, 2026, Open bid tab, 26-03 ↗ |
| Aggregate Surfacing Class 1 | ton | 3 | — | $33.00 | $17.00 – $33.00 | Feb 17, 2026, Open bid tab, 26-02 ↗ |
| Flotation Silt Curtain Type Moving Water | linear foot | 3 | — | $20.00 | $20.00 – $22.00 | Feb 17, 2026, Open bid tab, 26-02 ↗ |
| Remove pipe culvert | linear foot | 3 | — | $14.00 | $10.00 – $15.00 | May 30, 2023, Open bid tab, 23-02 ↗ |
| Rapid Stabilization Method 3 | m gallon | 3 | — | $595.00 | $10.00 – $595.00 | May 30, 2023, Open bid tab, 23-02 ↗ |