| Common Embankment (Cv) | cubic yard | $23.65 | $15.00 – $35.60 | 29 | Jun 10, 2026, Open the source page, contract 260085 |
| Storm Drain Inlet Protection | each | $188.00 | $173.69 – $200.00 | 26 | Jun 10, 2026, Open the source page, contract 260085 |
| Sediment Control Log Type Compost | linear foot | $3.67 | $3.14 – $5.88 | 26 | Jun 10, 2026, Open the source page, contract 260085 |
| Excavation Common | cubic yard | $29.00 | $21.50 – $52.50 | 25 | Jun 10, 2026, Open the source page, contract 260085 |
| Drill and grout reinforced bar (epoxy coated) | each | $13.55 | $10.95 – $20.00 | 24 | Jun 10, 2026, Open the source page, contract 260089 |
| Remove Curb and Gutter | linear foot | $8.00 | $5.58 – $11.30 | 23 | Jun 10, 2026, Open the source page, contract 260085 |
| Remove Guardrail-plate Beam | linear foot | $9.00 | $6.75 – $10.70 | 23 | Jun 10, 2026, Open the source page, contract 260085 |
| Sign | square foot | $90.34 | $78.50 – $108.75 | 22 | Jun 10, 2026, Open the source page, contract 260089 |
| Remove Sign | each | $100.00 | $38.35 – $118.75 | 22 | Jun 10, 2026, Open the source page, contract 260089 |
| Sawing asphalt pavement (full deep) | linear foot | $2.12 | $2.00 – $3.80 | 22 | Jun 10, 2026, Open the source page, contract 260085 |
| Traffic Barrier Design Type 31 | linear foot | $36.85 | $33.00 – $46.31 | 22 | Jun 10, 2026, Open the source page, contract 260085 |
| Casting Assembly | each | $1,175 | $1,000 – $1,350 | 21 | Jun 10, 2026, Open the source page, contract 260085 |
| Remove Energy Absorbing Terminal | each | $600.00 | $540.00 – $695.00 | 21 | Jun 10, 2026, Open the source page, contract 260085 |
| End Treatment-tangent Terminal | each | $4,000 | $3,900 – $4,310 | 21 | Jun 10, 2026, Open the source page, contract 260085 |
| Portable Precast Concrete Barrier Design 8337 | linear foot | $15.60 | $14.50 – $17.00 | 21 | Jun 10, 2026, Open the source page, contract 260085 |
| Remove asphalt pavement | square yard | $10.65 | $8.38 – $18.19 | 20 | Jun 10, 2026, Open the source page, contract 260085 |
| 6 inch concrete walk | square foot | $9.13 | $8.24 – $13.57 | 20 | Jun 10, 2026, Open the source page, contract 260089 |
| Fertilizer Type 3 | pound | $2.00 | $1.22 – $3.00 | 20 | Jun 10, 2026, Open the source page, contract 260085 |
| Remove Anchorage Assembly-plate Beam | each | $325.00 | $230.25 – $703.75 | 20 | Jun 10, 2026, Open the source page, contract 260085 |
| Remove Delineator / Marker | each | $40.50 | $31.50 – $50.76 | 20 | Jun 10, 2026, Open the source page, contract 260104 |
| Reinforced bars (epoxy coated) | pound | $1.80 | $1.65 – $2.11 | 20 | Jun 10, 2026, Open the source page, contract 260089 |
| Portable Barrier Delineator | each | $9.25 | $8.68 – $10.43 | 20 | Jun 10, 2026, Open the source page, contract 260085 |
| Select Granular Embankment (Cv) | cubic yard | $42.00 | $35.00 – $54.75 | 19 | Jun 10, 2026, Open the source page, contract 260085 |
| Fiber Optic Pigtail Termination | each | $1,800 | $1,550 – $2,014 | 19 | Jun 10, 2026, Open the source page, contract 260085 |
| Remove Sewer Pipe (Storm) | linear foot | $28.50 | $22.05 – $41.00 | 19 | Jun 10, 2026, Open the source page, contract 260085 |
| Delineator / Marker | each | $300.00 | $267.57 – $355.00 | 19 | Jun 10, 2026, Open the source page, contract 260089 |
| Delineator / Marker Panel | each | $100.00 | $97.72 – $115.00 | 19 | Jun 10, 2026, Open the source page, contract 260089 |
| 6 inch solid line multi-component ground in (wr) | linear foot | $2.25 | $1.38 – $3.25 | 19 | Jun 10, 2026, Open the source page, contract 260085 |
| 1.5 inch non-metallic conduit | linear foot | $5.90 | $5.00 – $8.62 | 19 | Jun 10, 2026, Open the source page, contract 260085 |
| Pull Vault | each | $2,930 | $2,800 – $3,230 | 19 | Jun 10, 2026, Open the source page, contract 260089 |
| Buried Cable Sign | each | $111.43 | $75.00 – $188.75 | 18 | Jun 10, 2026, Open the source page, contract 260085 |
| Armored fiber optic pigtail cable 6small | linear foot | $2.42 | $1.86 – $2.97 | 18 | Jun 10, 2026, Open the source page, contract 260085 |
| 2 inch, non-metallic, conduit | linear foot | $8.88 | $6.57 – $11.65 | 18 | Jun 10, 2026, Open the source page, contract 260089 |
| Connect to Existing Storm Sewer | each | $1,307 | $1,202 – $1,500 | 18 | Jun 10, 2026, Open the source page, contract 260089 |
| Anchorage Assembly - Type 31 | each | $3,740 | $3,329 – $3,912 | 18 | Jun 10, 2026, Open the source page, contract 260085 |
| 1.5 inch bored conduit | linear foot | $20.00 | $18.30 – $25.00 | 17 | Jun 10, 2026, Open the source page, contract 260089 |
| Mulching material type 9 | cubic yard | $200.00 | $140.00 – $277.00 | 17 | Jun 10, 2026, Open the source page, contract 260085 |
| Remove Chain Link Fence | linear foot | $11.00 | $8.00 – $25.00 | 17 | Jun 10, 2026, Open the source page, contract 260089 |
| Sawing concrete pavement (full deep) | linear foot | $5.50 | $4.77 – $8.00 | 17 | Jun 10, 2026, Open the source page, contract 260089 |
| Truncated Domes | square foot | $62.00 | $56.70 – $68.04 | 17 | Jun 10, 2026, Open the source page, contract 260089 |
| Aggregate Base (Cv) Class 5 | cubic yard | $65.75 | $54.00 – $104.00 | 17 | Jun 10, 2026, Open the source page, contract 260085 |
| Adjust Frame and Ring Casting | each | $1,000 | $650.00 – $1,287 | 17 | Jun 10, 2026, Open the source page, contract 260089 |
| Joint Adhesive | linear foot | $0.925 | $0.395 – $1.02 | 16 | Jun 10, 2026, Open the source page, contract 260085 |
| Remove Concrete Walk | square foot | $2.83 | $1.50 – $6.88 | 16 | Jun 10, 2026, Open the source page, contract 260085 |
| Remove Drainage Structure | each | $837.50 | $663.75 – $967.50 | 16 | Jun 10, 2026, Open the source page, contract 260085 |
| Pavement marking remove | linear foot | $0.825 | $0.7 – $1.00 | 16 | Jun 10, 2026, Open the source page, contract 260085 |
| Concrete Curb Ramp Walk | square foot | $16.10 | $15.38 – $19.05 | 16 | Jun 10, 2026, Open the source page, contract 260089 |
| Concrete Curb and Gutter Design B624 | linear foot | $44.10 | $37.42 – $49.50 | 16 | Jun 10, 2026, Open the source page, contract 260089 |
| Supplemental Description | linear foot | $80.00 | $41.00 – $135.00 | 15 | May 7, 2025, Open the source page, contract 250045 |
| 4 inch concrete walk | square foot | $11.50 | $9.01 – $13.14 | 15 | Jun 10, 2026, Open the source page, contract 260085 |
| Salvage Sign | each | $80.00 | $38.35 – $105.88 | 14 | Jun 10, 2026, Open the source page, contract 260085 |
| Remove Handhole | each | $322.50 | $300.00 – $488.75 | 14 | Jun 10, 2026, Open the source page, contract 260085 |
| Grubbing | each | $265.00 | $196.25 – $495.00 | 14 | Jun 10, 2026, Open the source page, contract 260085 |
| Install Sign | each | $607.23 | $477.50 – $706.25 | 14 | Jun 10, 2026, Open the source page, contract 260085 |
| Remove Casting | each | $250.00 | $231.25 – $357.50 | 14 | Jun 10, 2026, Open the source page, contract 260085 |
| Connect into Existing Drainage Structure | each | $1,451 | $1,200 – $1,975 | 14 | Jun 10, 2026, Open the source page, contract 260085 |
| Relocate Portable Precast Concrete Barrier Design 8337 | linear foot | $4.50 | $3.75 – $6.56 | 14 | Jun 10, 2026, Open the source page, contract 260085 |
| Grubbing | acre | $11,500 | $7,100 – $20,000 | 13 | Jun 10, 2026, Open the source page, contract 260089 |
| Culvert End Controls | each | $175.00 | $144.00 – $200.00 | 13 | Jun 10, 2026, Open the source page, contract 260085 |
| Sign Panel Overlay | square foot | $22.00 | $16.00 – $26.50 | 13 | Jun 10, 2026, Open the source page, contract 260089 |
| Extruded Panel | square foot | $34.00 | $32.65 – $34.90 | 13 | Jun 10, 2026, Open the source page, contract 260089 |
| Rolled Erosion Prevention Category 20 | square yard | $2.10 | $1.75 – $2.75 | 12 | Jun 10, 2026, Open the source page, contract 260085 |
| Electrical Ground | each | $348.71 | $287.50 – $534.38 | 12 | Jun 10, 2026, Open the source page, contract 260089 |