Construction unit costs in Broward County, FL

Median awarded unit prices for 73 items on public projects in Broward County, from winning bids in agency bid tabulations. Each item page lists its source documents.

Cost by state › Florida › Broward County

ItemPerMedianMiddle halfWinning bidsLatest source document
Thermoplastic, Standard, Whitelinear foot$4.80$3.55 – $6.4175Aug 26, 2026, Open bid tab, T4757 ↗
Pull & splice box, f&i, 13 inch x 24 incheach$1,794$1,650 – $2,00073Aug 26, 2026, Open bid tab, T4757 ↗
Conduit, Furnish & Installlinear foot$43.50$32.48 – $51.0271Aug 26, 2026, Open bid tab, T4757 ↗
Paint pavement markinglinear foot$1.94$1.21 – $2.1658Aug 27, 2025, Open bid tab, T4688 ↗
Milling Existing Asphaltsquare yard$3.38$2.50 – $5.4057Aug 26, 2026, Open bid tab, T4757 ↗
Conduit, Furnish & Install, Openlinear foot$24.23$19.16 – $30.0052Aug 26, 2026, Open bid tab, T4757 ↗
Concrete Sidewalk andsquare yard$90.00$70.00 – $110.0048Jun 10, 2026, Open bid tab, T4766 ↗
Prestressed Concrete Pole, F&Ieach$3,012$2,525 – $3,91546Aug 26, 2026, Open bid tab, T4757 ↗
Light Pole Complete, F&Ieach$11,000$9,880 – $12,26945Aug 26, 2026, Open bid tab, T4757 ↗
Sign Panel, Furnish & Installeach$1,060$882.50 – $2,19043Mar 25, 2026, Open bid tab, T4734 ↗
Thermoplastic, Standard, Whiteeach$120.90$83.47 – $162.8242Jun 10, 2026, Open bid tab, T4766 ↗
Raised Pavement Marker, Type Beach$5.04$4.30 – $5.9342Aug 26, 2026, Open bid tab, T4757 ↗
Lighting Conductors, F&Ilinear foot$4.95$3.45 – $6.0039Aug 26, 2026, Open bid tab, T4757 ↗
Thermoplastic, Preformedeach$271.00$165.00 – $395.5038Sep 24, 2025, Open bid tab, T4741 ↗
Asphalt Concrete Frictionton$218.50$184.70 – $270.0037Aug 26, 2026, Open bid tab, T4757 ↗
Steel Mast Arm Assembly, Furnisheach$77,400$66,251 – $93,72137Mar 25, 2026, Open bid tab, T4734 ↗
Electrical Service Disconnecteach$1,986$813.04 – $3,80536Aug 26, 2026, Open bid tab, T4757 ↗
Electrical Service Wire, Furnishlinear foot$11.71$8.25 – $15.4036Aug 26, 2026, Open bid tab, T4757 ↗
Superpave asphalt concreteton$237.19$179.00 – $297.5035Aug 26, 2026, Open bid tab, T4757 ↗
Pipe Culvert,Optionallinear foot$269.13$217.66 – $416.1435Sep 24, 2025, Open bid tab, T4741 ↗
Remove of existing concretesquare yard$36.75$30.00 – $53.0035Aug 26, 2026, Open bid tab, T4757 ↗
Inlet Protection Systemeach$154.00$130.00 – $260.5033Jun 10, 2026, Open bid tab, T4766 ↗
Paint pavement markingeach$50.00$44.00 – $66.7532Aug 27, 2025, Open bid tab, T4688 ↗
Pole Cable Distribution Systemeach$915.00$700.00 – $1,08929Aug 26, 2026, Open bid tab, T4757 ↗
Performance Turf, Sodsquare yard$7.25$5.40 – $12.6929Jun 10, 2026, Open bid tab, T4766 ↗
Traffic Control Officerhour$86.00$76.78 – $94.8528Aug 26, 2026, Open bid tab, T4757 ↗
Vehicle Detection System- Videoeach$6,538$2,814 – $10,78528Jun 10, 2026, Open bid tab, T4766 ↗
Traffic Separator Concretelinear foot$69.80$41.75 – $104.9926Sep 24, 2025, Open bid tab, T4741 ↗
Valve Boxes, Adjusteach$731.09$598.75 – $825.0026Aug 27, 2025, Open bid tab, T4688 ↗
Concrete Curb & Gutter, Type Flinear foot$51.41$41.24 – $59.5026Jun 10, 2026, Open bid tab, T4766 ↗
Detectable Warningssquare foot$41.75$35.00 – $51.0025Jun 10, 2026, Open bid tab, T4766 ↗
Sediment Barrierlinear foot$3.44$2.75 – $6.0025Aug 26, 2026, Open bid tab, T4757 ↗
Guardrail End Treatmenteach$3,000$1,700 – $3,45025Jan 28, 2026, Open bid tab, T4749 ↗
Type B Stabilizationsquare yard$14.66$6.13 – $28.5324Aug 26, 2026, Open bid tab, T4757 ↗
Thermoplastic, Standardlinear foot$4.00$3.60 – $4.9523Aug 27, 2025, Open bid tab, T4688 ↗
Thermoplastic, Preformedlinear foot$19.00$17.75 – $20.9023Jun 10, 2026, Open bid tab, T4766 ↗
Prestressed Concrete Poleeach$2,538$1,241 – $4,41523Mar 25, 2026, Open bid tab, T4734 ↗
Embankmentcubic yard$49.75$29.26 – $70.1422Sep 24, 2025, Open bid tab, T4741 ↗
Pedestrian Detector, Furnish &each$569.29$463.79 – $775.0022Jun 10, 2026, Open bid tab, T4766 ↗
Manhole, p-7, <10'each$8,700$6,055 – $9,91522Sep 24, 2025, Open bid tab, T4741 ↗
Luminaire, F&I- Replace Existingeach$1,864$1,496 – $2,20022Aug 26, 2026, Open bid tab, T4757 ↗
Temporary Barrier, Relocatelinear foot$18.09$13.90 – $28.5822Aug 26, 2026, Open bid tab, T4757 ↗
Sign Panel, Remove, up to 12 SFeach$90.00$77.00 – $155.0921Jun 10, 2026, Open bid tab, T4766 ↗
Fiber Optic Connection, Installeach$65.00$54.50 – $90.0021Dec 3, 2025, Open bid tab, T4717 ↗
Aluminum signal pole, pedestaleach$2,737$2,131 – $3,27820Jun 10, 2026, Open bid tab, T4766 ↗
Paint pavement markingsquare foot$2.74$2.04 – $4.4120Jun 10, 2026, Open bid tab, T4766 ↗
Internally Illuminated Signeach$4,057$3,357 – $4,74420Mar 25, 2026, Open bid tab, T4734 ↗
Fiber Optic Cable, F&Ilinear foot$4.95$4.50 – $5.8420Dec 3, 2025, Open bid tab, T4717 ↗
Pipe Culvert, Optional Materiallinear foot$275.00$187.98 – $604.0020Jul 30, 2025, Open bid tab, T4648 ↗
Guardrail removelinear foot$2.27$1.91 – $5.1220Jan 28, 2026, Open bid tab, T4749 ↗
Manhole, Adjusteach$959.82$857.51 – $1,10220Jun 10, 2026, Open bid tab, T4766 ↗
Enhanced Highway Sign Assemblyeach$8,296$5,951 – $14,50720Aug 26, 2026, Open bid tab, T4757 ↗
Tree Protection Barrierlinear foot$7.70$5.75 – $11.5920Mar 25, 2026, Open bid tab, T4734 ↗
Regular Excavationcubic yard$37.64$27.69 – $58.6520Jun 10, 2026, Open bid tab, T4766 ↗
Manhole, Adjust, Utilitieseach$1,000$850.00 – $1,14320Aug 27, 2025, Open bid tab, T4728 ↗
Object Marker, Type 1each$278.30$229.27 – $306.0820Jul 30, 2025, Open bid tab, T4648 ↗
Tree Root And Branch Pruningeach$1,000$650.00 – $2,75019Jan 28, 2026, Open bid tab, T4749 ↗
Pull & splice box, f&i, 24 inch x 36 incheach$3,270$3,023 – $3,50017Jun 10, 2026, Open bid tab, T4766 ↗
Fiber Optic Cable Locatorday$190.00$145.00 – $260.0017Aug 26, 2026, Open bid tab, T4757 ↗
Load Center, F&I, Secondaryeach$16,418$15,060 – $19,85016Aug 26, 2026, Open bid tab, T4757 ↗
Concrete Curb Type Dlinear foot$47.34$36.73 – $77.0416Jun 10, 2026, Open bid tab, T4766 ↗
Light Pole Complete, Removeeach$1,528$1,089 – $2,49416Aug 26, 2026, Open bid tab, T4757 ↗
Aluminum signal pole, removeeach$500.00$291.03 – $633.6415Jun 10, 2026, Open bid tab, T4766 ↗
Pipe Culvert, Opt Materiallinear foot$565.00$384.00 – $860.0015Sep 24, 2025, Open bid tab, T4741 ↗
Managed Field Ethernet Switcheach$6,500$4,890 – $7,87415Mar 25, 2026, Open bid tab, T4734 ↗
Green Colored Pavementsquare foot$10.00$9.45 – $11.0015Aug 27, 2025, Open bid tab, T4688 ↗
Traffic Monitoring Siteeach$2,883$2,193 – $4,00014Jun 10, 2026, Open bid tab, T4766 ↗
Temporary Barrier, F&I, Lowlinear foot$48.15$37.06 – $58.9214Jun 10, 2026, Open bid tab, T4766 ↗
Miscellaneous Asphalt Pavementton$283.30$220.29 – $511.2714Jan 28, 2026, Open bid tab, T4749 ↗
Pedestrian Detector, Removeeach$118.50$101.26 – $155.0913Jun 10, 2026, Open bid tab, T4766 ↗
Traffic Monitoring Site Vehicleeach$2,316$2,153 – $3,40013Jun 10, 2026, Open bid tab, T4766 ↗
Lighting Conductors, Remove &linear foot$0.885$0.472 – $1.3912Mar 25, 2026, Open bid tab, T4753 ↗
Inlet, curb, type p-5, <10'each$11,000$9,592 – $13,69612Aug 27, 2025, Open bid tab, T4688 ↗