| Thermoplastic, Standard, White | linear foot | $6.67 | $5.00 – $8.00 | 36 | May 20, 2026, Open bid tab, T7610 ↗ |
| Conduit, Furnish & Install | linear foot | $43.81 | $36.75 – $55.00 | 32 | May 20, 2026, Open bid tab, T7610 ↗ |
| Milling Existing Asphalt | square yard | $6.49 | $3.90 – $10.48 | 32 | Sep 30, 2026, Open bid tab, T7622 ↗ |
| Paint pavement marking | linear foot | $2.00 | $1.52 – $2.35 | 31 | Apr 29, 2026, Open bid tab, T7562 ↗ |
| Concrete Sidewalk and | square yard | $98.50 | $80.50 – $128.97 | 28 | Sep 30, 2026, Open bid tab, T7622 ↗ |
| Utility fitting, ductile iron/cast | each | $2,300 | $1,585 – $2,600 | 27 | Apr 29, 2026, Open bid tab, T7562 ↗ |
| Raised Pavement Marker, Type B | each | $5.00 | $4.69 – $5.64 | 25 | Sep 30, 2026, Open bid tab, T7622 ↗ |
| Pull & splice box, f&i, 13 inch x 24 inch | each | $1,588 | $1,300 – $1,992 | 23 | Apr 29, 2026, Open bid tab, T7562 ↗ |
| Thermoplastic, Standard, White | each | $89.50 | $75.00 – $157.50 | 22 | May 20, 2026, Open bid tab, T7610 ↗ |
| Sign Panel, Remove, up to 12 SF | each | $55.00 | $25.00 – $75.00 | 21 | Sep 30, 2026, Open bid tab, T7622 ↗ |
| Pipe Culvert,Optional | linear foot | $261.00 | $182.00 – $300.00 | 21 | May 20, 2026, Open bid tab, T7610 ↗ |
| Conduit, Furnish & Install, Open | linear foot | $27.00 | $24.60 – $30.00 | 21 | May 20, 2026, Open bid tab, T7610 ↗ |
| Superpave asphalt concrete | ton | $216.69 | $185.31 – $266.12 | 20 | Sep 30, 2026, Open bid tab, T7622 ↗ |
| Steel Mast Arm Assembly, Furnish | each | $80,335 | $68,178 – $103,106 | 19 | May 20, 2026, Open bid tab, T7610 ↗ |
| Asphalt Concrete Friction | ton | $251.50 | $211.37 – $315.72 | 18 | Sep 30, 2026, Open bid tab, T7622 ↗ |
| Inlet Protection System | each | $160.59 | $133.23 – $203.68 | 16 | Sep 30, 2026, Open bid tab, T7622 ↗ |
| Remove of existing concrete | square yard | $63.47 | $25.85 – $76.34 | 16 | Sep 30, 2026, Open bid tab, T7622 ↗ |
| Detectable Warnings | square foot | $35.06 | $29.65 – $45.00 | 15 | Sep 30, 2026, Open bid tab, T7622 ↗ |
| Thermoplastic, Preformed | each | $203.00 | $159.56 – $376.83 | 15 | May 20, 2026, Open bid tab, T7610 ↗ |
| Concrete Curb & Gutter, Type F | linear foot | $59.79 | $50.00 – $80.00 | 15 | Sep 30, 2026, Open bid tab, T7622 ↗ |
| Paint pavement marking | square foot | $5.00 | $4.16 – $5.54 | 14 | May 20, 2026, Open bid tab, T7610 ↗ |
| Paint pavement marking | each | $46.25 | $31.50 – $50.00 | 14 | Apr 29, 2026, Open bid tab, T7562 ↗ |
| Thermoplastic, Preformed | linear foot | $16.85 | $16.00 – $18.93 | 14 | May 20, 2026, Open bid tab, T7610 ↗ |
| Traffic Control Officer | hour | $92.89 | $84.00 – $99.09 | 14 | May 20, 2026, Open bid tab, T7610 ↗ |
| Performance Turf, Sod | square yard | $8.73 | $5.51 – $11.81 | 14 | May 20, 2026, Open bid tab, T7610 ↗ |