Construction unit costs in Orange County, FL

Median awarded unit prices for 40 items on public projects in Orange County, from winning bids in agency bid tabulations. Each item page lists its source documents.

Cost by state › Florida › Orange County

ItemPerMedianMiddle halfWinning bidsLatest source document
Thermoplastic, Standard, Whitelinear foot$6.90$5.00 – $9.1231Aug 26, 2026, Open bid tab, T5890 ↗
Paint pavement markinglinear foot$2.95$2.21 – $4.0030Aug 26, 2026, Open bid tab, T5890 ↗
Conduit, Furnish & Installlinear foot$39.70$33.63 – $43.2530Aug 26, 2026, Open bid tab, T5890 ↗
Milling Existing Asphaltsquare yard$3.90$2.78 – $12.5027Aug 26, 2026, Open bid tab, T5890 ↗
Pipe Culvert,Optionallinear foot$297.84$186.30 – $533.0326Aug 26, 2026, Open bid tab, T5890 ↗
Signal Priority And Preemptioneach$8,810$7,648 – $9,82224Aug 26, 2026, Open bid tab, T5890 ↗
Concrete Curb & Gutter, Type Flinear foot$60.36$48.09 – $80.9424Aug 26, 2026, Open bid tab, T5890 ↗
Detectable Warningssquare foot$37.95$32.21 – $54.0523Aug 26, 2026, Open bid tab, T5890 ↗
Aluminum signal pole, pedestaleach$2,691$2,175 – $3,01423Aug 26, 2026, Open bid tab, T5890 ↗
Traffic Control Officerhour$108.00$87.41 – $115.5023Aug 26, 2026, Open bid tab, T5890 ↗
Fiber Optic Cable Locatorday$224.00$168.00 – $269.0023Aug 26, 2026, Open bid tab, T5890 ↗
Itsfm Subsurfacemile$3,850$2,300 – $8,13623Aug 26, 2026, Open bid tab, T5890 ↗
Thermoplastic, Preformedeach$245.00$172.00 – $380.0022Aug 26, 2026, Open bid tab, T5890 ↗
Thermoplastic, Standard, Whiteeach$147.00$93.75 – $181.5022Aug 26, 2026, Open bid tab, T5890 ↗
Concrete Sidewalk andsquare yard$95.12$85.00 – $116.0021Aug 26, 2026, Open bid tab, T5890 ↗
Uninterruptible Power Supplyeach$10,526$9,415 – $12,90021Aug 26, 2026, Open bid tab, T5890 ↗
Pipe Culvert, Opt Materiallinear foot$707.36$319.00 – $968.8920Aug 26, 2026, Open bid tab, T5890 ↗
Steel Mast Arm Assembly, Furnisheach$76,678$64,002 – $97,99920Aug 26, 2026, Open bid tab, T5890 ↗
Raised Pavement Marker, Type Beach$5.10$5.00 – $5.5620Aug 26, 2026, Open bid tab, T5890 ↗
Pull & splice box, f&i, 13 inch x 24 incheach$1,700$1,450 – $2,16519Aug 26, 2026, Open bid tab, T5890 ↗
Fiber Optic Cable, F&Ilinear foot$4.50$3.62 – $5.9118Aug 26, 2026, Open bid tab, T5890 ↗
Conduit, Furnish & Install, Openlinear foot$22.31$18.60 – $28.1818Aug 26, 2026, Open bid tab, T5890 ↗
Paint pavement markingeach$75.00$52.50 – $107.0015Aug 26, 2026, Open bid tab, T5890 ↗
Vehicle Detection Systemeach$11,600$10,227 – $13,37615Aug 26, 2026, Open bid tab, T5890 ↗
Fiber Optic Connection, Installeach$56.00$51.25 – $76.5015Aug 26, 2026, Open bid tab, T5890 ↗
Internally Illuminated Signeach$6,483$4,430 – $8,07514Aug 26, 2026, Open bid tab, T5890 ↗
Thermoplastic, Preformedlinear foot$18.25$15.10 – $21.9714Aug 26, 2026, Open bid tab, T5890 ↗
Asphalt Concrete Frictionton$256.00$204.00 – $280.0013Aug 26, 2026, Open bid tab, T5890 ↗
Sign Panel, Furnish & Installeach$889.66$605.00 – $1,05013Aug 26, 2026, Open bid tab, T5890 ↗
Pedestrian Detector, Furnish &each$780.00$512.00 – $1,67013Aug 26, 2026, Open bid tab, T5890 ↗
Itsfm Location Documentationeach$1,760$1,697 – $2,80013Aug 26, 2026, Open bid tab, T5890 ↗
Inlet Protection Systemeach$150.00$136.25 – $216.7512Aug 26, 2026, Open bid tab, T5890 ↗
Mowingacre$98.75$88.50 – $231.2512Aug 26, 2026, Open bid tab, T5890 ↗
Paint pavement markingsquare foot$6.15$5.40 – $12.0012Mar 25, 2026, Open bid tab, T5878 ↗
Pull & splice box, f&i, 24 inch x 36 incheach$3,081$2,805 – $3,29212Aug 26, 2026, Open bid tab, T5890 ↗
Prestressed Concrete Pole, F&Ieach$2,530$2,385 – $3,18412Aug 26, 2026, Open bid tab, T5890 ↗
Remove of existing concretesquare yard$33.50$25.87 – $44.4212Aug 26, 2026, Open bid tab, T5890 ↗
Electrical Service Wire, Furnishlinear foot$7.70$6.26 – $10.0012Aug 26, 2026, Open bid tab, T5890 ↗
Performance Turf, Sodsquare yard$8.75$7.15 – $13.2012Aug 26, 2026, Open bid tab, T5890 ↗
Litter removeacre$65.44$53.75 – $98.1212Aug 26, 2026, Open bid tab, T5890 ↗