| Paint pavement marking | linear foot | $3.84 | $3.25 – $4.78 | 43 | Dec 3, 2025, Open bid tab, T3993 ↗ |
| Milling Existing Asphalt | square yard | $2.85 | $2.33 – $3.58 | 42 | Jan 28, 2026, Open bid tab, T3954 ↗ |
| Thermoplastic, Standard, White | linear foot | $7.68 | $5.90 – $10.00 | 39 | Dec 3, 2025, Open bid tab, T3993 ↗ |
| Raised Pavement Marker, Type B | each | $5.25 | $5.00 – $5.61 | 29 | Jan 28, 2026, Open bid tab, T3954 ↗ |
| Thermoplastic, Standard, White | each | $140.20 | $98.00 – $194.14 | 27 | Dec 3, 2025, Open bid tab, T3993 ↗ |
| Sign Panel, Furnish & Install | each | $703.88 | $362.22 – $1,140 | 25 | Aug 27, 2025, Open bid tab, T3930 ↗ |
| Paint pavement marking | each | $74.00 | $53.99 – $83.98 | 25 | Dec 3, 2025, Open bid tab, T3993 ↗ |
| Concrete Sidewalk and | square yard | $115.50 | $95.35 – $131.56 | 24 | Jan 28, 2026, Open bid tab, T3954 ↗ |
| Asphalt Concrete Friction | ton | $195.50 | $171.88 – $240.28 | 23 | Jan 28, 2026, Open bid tab, T3954 ↗ |
| Thermoplastic, Preformed | each | $192.68 | $181.26 – $480.00 | 22 | Dec 3, 2025, Open bid tab, T3993 ↗ |
| Steel Mast Arm Assembly, Furnish | each | $107,172 | $88,042 – $149,993 | 22 | Aug 27, 2025, Open bid tab, T3930 ↗ |
| Regular Excavation | cubic yard | $40.91 | $29.51 – $48.56 | 22 | Jan 28, 2026, Open bid tab, T3954 ↗ |
| Pipe Culvert,Optional | linear foot | $251.97 | $160.27 – $395.96 | 20 | Dec 3, 2025, Open bid tab, T3993 ↗ |
| Mitered End Section, Optional | each | $3,628 | $3,312 – $4,518 | 20 | Jan 28, 2026, Open bid tab, T3954 ↗ |
| Superpave asphalt concrete | ton | $169.25 | $156.16 – $253.79 | 20 | Jan 28, 2026, Open bid tab, T3954 ↗ |
| Concrete Curb & Gutter, Type F | linear foot | $57.56 | $51.64 – $65.00 | 20 | Aug 27, 2025, Open bid tab, T3930 ↗ |
| Miscellaneous Asphalt Pavement | ton | $522.62 | $350.00 – $741.40 | 20 | Jan 28, 2026, Open bid tab, T3954 ↗ |
| Mowing | acre | $95.50 | $64.77 – $120.85 | 18 | Dec 3, 2025, Open bid tab, T3993 ↗ |
| Litter remove | acre | $70.99 | $58.56 – $119.20 | 18 | Dec 3, 2025, Open bid tab, T3993 ↗ |
| Conduit, Furnish & Install | linear foot | $47.99 | $40.00 – $60.00 | 17 | Jan 28, 2026, Open bid tab, T3954 ↗ |
| Performance Turf, Sod | square yard | $5.05 | $3.32 – $10.00 | 17 | Jan 28, 2026, Open bid tab, T3954 ↗ |
| Pull & splice box, f&i, 13 inch x 24 inch | each | $1,806 | $1,652 – $1,933 | 16 | Aug 27, 2025, Open bid tab, T3930 ↗ |
| Remove of existing concrete | square yard | $36.99 | $32.09 – $64.25 | 16 | Jan 28, 2026, Open bid tab, T3954 ↗ |
| Inlet Protection System | each | $272.15 | $237.17 – $310.00 | 15 | Dec 3, 2025, Open bid tab, T3993 ↗ |
| Conduit, Furnish & Install, Open | linear foot | $24.15 | $18.00 – $26.00 | 15 | Dec 3, 2025, Open bid tab, T3993 ↗ |
| Sediment Barrier | linear foot | $6.50 | $3.46 – $9.90 | 15 | Jan 28, 2026, Open bid tab, T3954 ↗ |
| Guardrail End Treatment | each | $3,800 | $2,593 – $4,187 | 15 | Jan 28, 2026, Open bid tab, T3954 ↗ |
| Borrow Excavation, Truck | cubic yard | $48.39 | $38.25 – $74.00 | 14 | Jan 28, 2026, Open bid tab, T3954 ↗ |
| Traffic Control Officer | hour | $79.72 | $77.00 – $93.94 | 14 | Dec 3, 2025, Open bid tab, T3993 ↗ |
| Detectable Warnings | square foot | $30.27 | $27.44 – $36.50 | 12 | Aug 27, 2025, Open bid tab, T3930 ↗ |
| Thermoplastic, Preformed | linear foot | $15.20 | $14.05 – $18.19 | 12 | Dec 3, 2025, Open bid tab, T3993 ↗ |
| Pipe Culvert, Optional Material | linear foot | $233.10 | $167.28 – $364.18 | 12 | Jan 28, 2026, Open bid tab, T3954 ↗ |