Cost by county

Construction unit costs in Escambia County, FL

Median awarded unit prices for 32 items on public projects in Escambia County, from winning bids in agency bid tabulations. Each item page lists its source documents.

Cost by state › Florida › Escambia County

ItemPerMedianMiddle halfWinning bidsLatest source document
Paint pavement markinglinear foot$3.84$3.25 – $4.7843Dec 3, 2025, Open bid tab, T3993 ↗
Milling Existing Asphaltsquare yard$2.85$2.33 – $3.5842Jan 28, 2026, Open bid tab, T3954 ↗
Thermoplastic, Standard, Whitelinear foot$7.68$5.90 – $10.0039Dec 3, 2025, Open bid tab, T3993 ↗
Raised Pavement Marker, Type Beach$5.25$5.00 – $5.6129Jan 28, 2026, Open bid tab, T3954 ↗
Thermoplastic, Standard, Whiteeach$140.20$98.00 – $194.1427Dec 3, 2025, Open bid tab, T3993 ↗
Sign Panel, Furnish & Installeach$703.88$362.22 – $1,14025Aug 27, 2025, Open bid tab, T3930 ↗
Paint pavement markingeach$74.00$53.99 – $83.9825Dec 3, 2025, Open bid tab, T3993 ↗
Concrete Sidewalk andsquare yard$115.50$95.35 – $131.5624Jan 28, 2026, Open bid tab, T3954 ↗
Asphalt Concrete Frictionton$195.50$171.88 – $240.2823Jan 28, 2026, Open bid tab, T3954 ↗
Thermoplastic, Preformedeach$192.68$181.26 – $480.0022Dec 3, 2025, Open bid tab, T3993 ↗
Steel Mast Arm Assembly, Furnisheach$107,172$88,042 – $149,99322Aug 27, 2025, Open bid tab, T3930 ↗
Regular Excavationcubic yard$40.91$29.51 – $48.5622Jan 28, 2026, Open bid tab, T3954 ↗
Pipe Culvert,Optionallinear foot$251.97$160.27 – $395.9620Dec 3, 2025, Open bid tab, T3993 ↗
Mitered End Section, Optionaleach$3,628$3,312 – $4,51820Jan 28, 2026, Open bid tab, T3954 ↗
Superpave asphalt concreteton$169.25$156.16 – $253.7920Jan 28, 2026, Open bid tab, T3954 ↗
Concrete Curb & Gutter, Type Flinear foot$57.56$51.64 – $65.0020Aug 27, 2025, Open bid tab, T3930 ↗
Miscellaneous Asphalt Pavementton$522.62$350.00 – $741.4020Jan 28, 2026, Open bid tab, T3954 ↗
Mowingacre$95.50$64.77 – $120.8518Dec 3, 2025, Open bid tab, T3993 ↗
Litter removeacre$70.99$58.56 – $119.2018Dec 3, 2025, Open bid tab, T3993 ↗
Conduit, Furnish & Installlinear foot$47.99$40.00 – $60.0017Jan 28, 2026, Open bid tab, T3954 ↗
Performance Turf, Sodsquare yard$5.05$3.32 – $10.0017Jan 28, 2026, Open bid tab, T3954 ↗
Pull & splice box, f&i, 13 inch x 24 incheach$1,806$1,652 – $1,93316Aug 27, 2025, Open bid tab, T3930 ↗
Remove of existing concretesquare yard$36.99$32.09 – $64.2516Jan 28, 2026, Open bid tab, T3954 ↗
Inlet Protection Systemeach$272.15$237.17 – $310.0015Dec 3, 2025, Open bid tab, T3993 ↗
Conduit, Furnish & Install, Openlinear foot$24.15$18.00 – $26.0015Dec 3, 2025, Open bid tab, T3993 ↗
Sediment Barrierlinear foot$6.50$3.46 – $9.9015Jan 28, 2026, Open bid tab, T3954 ↗
Guardrail End Treatmenteach$3,800$2,593 – $4,18715Jan 28, 2026, Open bid tab, T3954 ↗
Borrow Excavation, Truckcubic yard$48.39$38.25 – $74.0014Jan 28, 2026, Open bid tab, T3954 ↗
Traffic Control Officerhour$79.72$77.00 – $93.9414Dec 3, 2025, Open bid tab, T3993 ↗
Detectable Warningssquare foot$30.27$27.44 – $36.5012Aug 27, 2025, Open bid tab, T3930 ↗
Thermoplastic, Preformedlinear foot$15.20$14.05 – $18.1912Dec 3, 2025, Open bid tab, T3993 ↗
Pipe Culvert, Optional Materiallinear foot$233.10$167.28 – $364.1812Jan 28, 2026, Open bid tab, T3954 ↗