Construction unit costs in Volusia County, FL

Median awarded unit prices for 24 items on public projects in Volusia County, from winning bids in agency bid tabulations. Each item page lists its source documents.

Cost by state › Florida › Volusia County

ItemPerMedianMiddle halfWinning bidsLatest source document
Thermoplastic, Standard, Whitelinear foot$6.25$4.90 – $8.3041Sep 30, 2026, Open bid tab, T5893 ↗
Conduit, Furnish & Installlinear foot$34.34$24.79 – $43.3836Sep 30, 2026, Open bid tab, T5893 ↗
Milling Existing Asphaltsquare yard$2.71$1.94 – $3.8528Sep 30, 2026, Open bid tab, T5893 ↗
Concrete Sidewalk andsquare yard$78.20$58.50 – $94.6726Sep 30, 2026, Open bid tab, T5893 ↗
Fiber Optic Cable, F&Ilinear foot$4.03$3.62 – $4.8226Jun 15, 2026, Open bid tab, T5885 ↗
Conduit, Furnish & Install, Openlinear foot$18.39$13.12 – $23.1126Sep 30, 2026, Open bid tab, T5893 ↗
Paint pavement markinglinear foot$2.23$1.67 – $2.7124Sep 30, 2026, Open bid tab, T5893 ↗
Thermoplastic, Standard, Whiteeach$131.04$104.75 – $180.3924Sep 30, 2026, Open bid tab, T5893 ↗
Pull & splice box, f&i, 13 inch x 24 incheach$1,492$1,259 – $1,90922Sep 30, 2026, Open bid tab, T5893 ↗
Steel Mast Arm Assembly, Furnisheach$76,224$64,695 – $89,33322Sep 30, 2026, Open bid tab, T5893 ↗
Pipe Culvert,Optionallinear foot$169.25$110.00 – $260.2721Sep 30, 2026, Open bid tab, T5893 ↗
Raised Pavement Marker, Type Beach$5.00$4.75 – $6.0021Sep 30, 2026, Open bid tab, T5893 ↗
Sign Panel, Furnish & Installeach$1,101$360.50 – $1,64019Sep 30, 2026, Open bid tab, T5893 ↗
Mitered End Section, Optionaleach$4,155$3,688 – $7,75719Jun 15, 2026, Open bid tab, T5885 ↗
Enhanced Highway Sign Assemblyeach$10,300$8,880 – $10,71019Jun 15, 2026, Open bid tab, T5885 ↗
Asphalt Concrete Frictionton$182.15$155.07 – $205.3418Sep 30, 2026, Open bid tab, T5893 ↗
Pipe Culvert, Opt Materiallinear foot$307.45$201.50 – $399.3917Sep 30, 2026, Open bid tab, T5893 ↗
Litter removeacre$64.00$34.50 – $154.4015Sep 30, 2026, Open bid tab, T5893 ↗
Embankmentcubic yard$18.42$13.66 – $32.9414Sep 30, 2026, Open bid tab, T5893 ↗
Mowingacre$117.50$71.49 – $280.5714Sep 30, 2026, Open bid tab, T5893 ↗
Performance Turf, Sodsquare yard$4.72$3.99 – $5.8314Sep 30, 2026, Open bid tab, T5893 ↗
Detectable Warningssquare foot$29.50$25.00 – $40.0013Sep 30, 2026, Open bid tab, T5893 ↗
Superpave asphalt concreteton$129.15$120.00 – $170.0013Jun 15, 2026, Open bid tab, T5885 ↗
Regular Excavationcubic yard$15.00$6.55 – $20.0013Sep 30, 2026, Open bid tab, T5893 ↗