Street Lighting · awarded bid prices · Broward County
Lighting Conductors, F&I: cost per linear foot in Broward County, FL
The median awarded price is $4.95 per linear foot, from 39 winning bids on 27 public projects in Broward County, FL (2023–2026). Half of the awarded prices fall between $3.45 and $6.00.
Cost by state › Florida › Broward County › Lighting Conductors, F&I
Winning bids only, as printed in the agencies' bid tabulations (FDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $2.50 in 2021 to $4.75 in 2026 (+90%).
| Year | Median per linear foot | Winning bids |
|---|---|---|
| 2021 | $2.50 | 11 |
| 2022 | $3.60 | 19 |
| 2023 | $5.00 | 13 |
| 2024 | $4.95 | 17 |
| 2025 | $4.86 | 15 |
| 2026 | $4.75 | 6 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Aug 26, 2026 | FDOT | 61946 LF | $1.83 | Open bid tab, T4757 ↗ |
| Mar 25, 2026 | FDOT | 738 LF | $9.99 | Open bid tab, T4734 ↗ |
| Mar 25, 2026 | FDOT | 2321 LF | $5.25 | Open bid tab, T4753 ↗ |
| Jan 28, 2026 | FDOT | 3202 LF | $3.59 | Open bid tab, T4749 ↗ |
| Sep 24, 2025 | FDOT | 17711 LF | $3.00 | Open bid tab, T4721 ↗ |
See every awarded price for this item on the Lighting Conductors, F&I item page.
Related items in Broward County
- Pull & Splice Box, F&I, 13" x 24": $1,794 per each
- Conduit, Furnish & Install: $43.50 per linear foot
- Conduit, Furnish & Install, Open: $24.23 per linear foot
- Prestressed Concrete Pole, F&I: $3,012 per each
- Light Pole Complete, F&I: $11,000 per each
- Electrical Service Disconnect: $1,986 per each
- Electrical Service Wire, Furnish: $11.71 per linear foot
- Pole Cable Distribution System: $915.00 per each