| Milling Existing Asphalt | square yard | $3.17 | $2.26 – $4.63 | 66 | Jul 29, 2026, Open bid tab, T5889 ↗ |
| Paint pavement marking | linear foot | $1.90 | $1.50 – $3.50 | 41 | Jul 29, 2026, Open bid tab, T5889 ↗ |
| Thermoplastic, Standard, White | linear foot | $6.38 | $4.57 – $8.55 | 36 | Jul 29, 2026, Open bid tab, T5889 ↗ |
| Conduit, Furnish & Install | linear foot | $47.53 | $30.82 – $58.35 | 34 | Jul 29, 2026, Open bid tab, T5891 ↗ |
| Sign Panel, Furnish & Install | each | $1,082 | $424.38 – $1,900 | 30 | Jul 29, 2026, Open bid tab, T5889 ↗ |
| Superpave asphalt concrete | ton | $148.00 | $119.50 – $192.11 | 25 | Jul 29, 2026, Open bid tab, T5891 ↗ |
| Pull & splice box, f&i, 13 inch x 24 inch | each | $1,843 | $1,574 – $1,984 | 25 | Jul 29, 2026, Open bid tab, T5891 ↗ |
| Raised Pavement Marker, Type B | each | $4.73 | $4.60 – $5.53 | 24 | Jul 29, 2026, Open bid tab, T5889 ↗ |
| Internally Illuminated Sign | each | $4,148 | $2,310 – $4,997 | 23 | May 20, 2026, Open bid tab, T5882 ↗ |
| Remove of existing concrete | square yard | $38.65 | $27.75 – $59.00 | 23 | Jul 29, 2026, Open bid tab, T5891 ↗ |
| Fiber Optic Cable, F&I | linear foot | $4.20 | $3.79 – $4.46 | 22 | Jul 29, 2026, Open bid tab, T5891 ↗ |
| Conduit, Furnish & Install, Open | linear foot | $24.16 | $15.82 – $31.22 | 22 | Jul 29, 2026, Open bid tab, T5891 ↗ |
| Traffic Control Officer | hour | $85.00 | $80.67 – $99.25 | 22 | Jul 29, 2026, Open bid tab, T5889 ↗ |
| Regular Excavation | cubic yard | $32.00 | $19.99 – $45.84 | 22 | Jul 29, 2026, Open bid tab, T5891 ↗ |
| Detectable Warnings | square foot | $33.84 | $31.00 – $39.96 | 21 | Jul 29, 2026, Open bid tab, T5891 ↗ |
| Asphalt Concrete Friction | ton | $191.25 | $176.32 – $200.00 | 21 | Jul 29, 2026, Open bid tab, T5889 ↗ |
| Paint pavement marking | each | $57.50 | $46.52 – $75.00 | 21 | Jul 29, 2026, Open bid tab, T5891 ↗ |
| Mitered End Section, Optional | each | $3,000 | $2,500 – $6,000 | 21 | May 20, 2026, Open bid tab, T5882 ↗ |
| Electrical Service Wire, Furnish | linear foot | $9.36 | $8.13 – $10.70 | 21 | Jul 29, 2026, Open bid tab, T5891 ↗ |
| Sediment Barrier | linear foot | $3.40 | $1.50 – $5.70 | 21 | Jul 29, 2026, Open bid tab, T5891 ↗ |
| Fiber Optic Cable Locator | day | $200.00 | $80.85 – $287.50 | 21 | Jul 29, 2026, Open bid tab, T5889 ↗ |
| Thermoplastic, Preformed | linear foot | $16.50 | $14.69 – $19.91 | 20 | Jul 29, 2026, Open bid tab, T5891 ↗ |
| Fiber Optic Connection, Install | each | $50.00 | $46.26 – $53.66 | 20 | Jul 29, 2026, Open bid tab, T5891 ↗ |
| Managed Field Ethernet Switch | each | $5,404 | $4,142 – $6,820 | 20 | May 20, 2026, Open bid tab, T5882 ↗ |
| Concrete Curb & Gutter, Type F | linear foot | $49.80 | $37.41 – $83.75 | 20 | Jul 29, 2026, Open bid tab, T5891 ↗ |
| Thermoplastic, Standard, White | each | $115.00 | $105.00 – $152.50 | 18 | Jul 29, 2026, Open bid tab, T5891 ↗ |
| Steel Mast Arm Assembly, Furnish | each | $89,140 | $72,080 – $104,712 | 17 | May 20, 2026, Open bid tab, T5882 ↗ |
| Pipe Culvert,Optional | linear foot | $235.69 | $179.02 – $415.14 | 15 | May 20, 2026, Open bid tab, T5882 ↗ |
| Thermoplastic, Preformed | each | $210.00 | $160.94 – $230.00 | 15 | Jul 29, 2026, Open bid tab, T5889 ↗ |
| Superpave asphalt concrete | ton | $154.90 | $138.19 – $172.50 | 15 | Jul 29, 2026, Open bid tab, T5889 ↗ |
| Guardrail End Treatment | each | $2,344 | $1,677 – $3,907 | 15 | Jul 29, 2026, Open bid tab, T5889 ↗ |
| Concrete Sidewalk and | square yard | $105.33 | $83.23 – $132.50 | 14 | Jul 29, 2026, Open bid tab, T5891 ↗ |
| Uninterruptible Power Supply | each | $13,141 | $8,112 – $14,352 | 14 | Jul 29, 2026, Open bid tab, T5891 ↗ |
| Performance Turf, Sod | square yard | $5.76 | $4.00 – $6.95 | 14 | Jul 29, 2026, Open bid tab, T5889 ↗ |
| Inlet Protection System | each | $150.78 | $125.00 – $200.00 | 13 | Jul 29, 2026, Open bid tab, T5889 ↗ |
| Embankment | cubic yard | $51.24 | $30.00 – $59.20 | 13 | Jul 29, 2026, Open bid tab, T5891 ↗ |
| Itsfm Location Documentation | each | $2,184 | $1,920 – $2,551 | 13 | Jul 29, 2026, Open bid tab, T5891 ↗ |
| Mowing | acre | $63.00 | $41.81 – $85.95 | 12 | Jul 29, 2026, Open bid tab, T5889 ↗ |
| Electrical Service Disconnect | each | $1,531 | $1,224 – $2,725 | 12 | Jul 29, 2026, Open bid tab, T5891 ↗ |
| Prestressed Concrete Pole, F&I | each | $2,253 | $2,238 – $2,414 | 12 | Jul 29, 2026, Open bid tab, T5891 ↗ |
| Litter remove | acre | $33.50 | $25.03 – $46.74 | 12 | Jul 29, 2026, Open bid tab, T5889 ↗ |