Construction unit costs in Palm Beach County, FL

Median awarded unit prices for 43 items on public projects in Palm Beach County, from winning bids in agency bid tabulations. Each item page lists its source documents.

Cost by state › Florida › Palm Beach County

ItemPerMedianMiddle halfWinning bidsLatest source document
Thermoplastic, Standard, Whitelinear foot$5.00$3.55 – $6.6059Jul 29, 2026, Open bid tab, T4747 ↗
Conduit, Furnish & Installlinear foot$44.39$35.00 – $50.8454Jul 29, 2026, Open bid tab, T4747 ↗
Paint pavement markinglinear foot$1.91$1.76 – $3.0048Jul 29, 2026, Open bid tab, T4747 ↗
Concrete Sidewalk andsquare yard$90.00$71.96 – $122.5039Jul 29, 2026, Open bid tab, T4747 ↗
Thermoplastic, Preformedeach$215.00$157.65 – $274.4538Jul 29, 2026, Open bid tab, T4747 ↗
Steel Mast Arm Assembly, Furnisheach$83,883$66,831 – $104,91638May 20, 2026, Open bid tab, T4666 ↗
Milling Existing Asphaltsquare yard$3.50$3.00 – $4.6236Jul 29, 2026, Open bid tab, T4747 ↗
Thermoplastic, Standard, Whiteeach$97.70$75.60 – $147.6233May 20, 2026, Open bid tab, T4666 ↗
Conduit, Furnish & Install, Openlinear foot$21.30$15.00 – $29.4430Jul 29, 2026, Open bid tab, T4747 ↗
Pipe Culvert,Optionallinear foot$210.00$172.00 – $332.0029May 20, 2026, Open bid tab, T4666 ↗
Raised Pavement Marker, Type Beach$4.31$4.00 – $5.0029Jul 29, 2026, Open bid tab, T4747 ↗
Pull & splice box, f&i, 13 inch x 24 incheach$1,744$1,497 – $2,12627Jul 29, 2026, Open bid tab, T4747 ↗
Asphalt Concrete Frictionton$203.00$185.00 – $240.0025Jul 29, 2026, Open bid tab, T4747 ↗
Multi-column Ground Signeach$6,500$2,000 – $9,00025May 20, 2026, Open bid tab, T4666 ↗
Paint pavement markingeach$40.61$38.50 – $47.7924May 20, 2026, Open bid tab, T4666 ↗
Prestressed Concrete Pole, F&Ieach$2,946$2,285 – $3,73924Jul 29, 2026, Open bid tab, T4747 ↗
Inlet Protection Systemeach$169.00$138.75 – $249.7822Jul 29, 2026, Open bid tab, T4747 ↗
Lighting Conductors, F&Ilinear foot$3.80$2.66 – $5.3622May 20, 2026, Open bid tab, T4666 ↗
Detectable Warningssquare foot$46.20$44.14 – $50.0021Jul 29, 2026, Open bid tab, T4747 ↗
Remove of existing concretesquare yard$40.00$30.00 – $56.8821Jul 29, 2026, Open bid tab, T4747 ↗
Pull & splice box, f&i, 17 inch x 30 incheach$1,674$1,410 – $2,00021Jul 29, 2026, Open bid tab, T4747 ↗
Concrete Curb & Gutter, Type Flinear foot$53.35$45.00 – $70.0021Jul 29, 2026, Open bid tab, T4747 ↗
Performance Turf, Sodsquare yard$7.75$4.00 – $12.0021May 20, 2026, Open bid tab, T4666 ↗
Fiber Optic Cable, F&Ilinear foot$4.97$4.26 – $6.0020May 20, 2026, Open bid tab, T4666 ↗
Traffic Control Officerhour$89.50$87.25 – $100.6020May 20, 2026, Open bid tab, T4666 ↗
Electrical Service Wire, Furnishlinear foot$11.15$9.43 – $13.0819Jul 29, 2026, Open bid tab, T4747 ↗
Sediment Barrierlinear foot$3.41$2.46 – $4.2219Jul 29, 2026, Open bid tab, T4747 ↗
Embankmentcubic yard$53.50$30.62 – $97.9218May 20, 2026, Open bid tab, T4666 ↗
Junction Box, Furnish & Install,each$1,299$1,041 – $1,30518May 20, 2026, Open bid tab, T4666 ↗
Pole Cable Distribution Systemeach$1,052$807.87 – $1,14318May 20, 2026, Open bid tab, T4666 ↗
Pedestrian Detector, Furnish &each$455.27$370.25 – $644.4818Jul 29, 2026, Open bid tab, T4747 ↗
Pipe Culvert, Opt Materiallinear foot$350.00$255.00 – $400.0017May 20, 2026, Open bid tab, T4666 ↗
Internally Illuminated Signeach$3,768$2,471 – $4,50017May 20, 2026, Open bid tab, T4666 ↗
Fiber Optic Connection, Installeach$70.00$60.00 – $110.0017May 20, 2026, Open bid tab, T4666 ↗
Thermoplastic, Preformedlinear foot$16.59$15.94 – $19.2116Jul 29, 2026, Open bid tab, T4747 ↗
Guardrail End Treatmenteach$3,122$1,739 – $3,51116May 20, 2026, Open bid tab, T4666 ↗
Green Colored Pavementsquare foot$9.59$8.00 – $13.3616May 20, 2026, Open bid tab, T4666 ↗
Aluminum signal pole, pedestaleach$2,743$2,401 – $2,98915Jul 29, 2026, Open bid tab, T4747 ↗
Thermoplastic, Standardlinear foot$4.70$4.48 – $5.0015Jul 29, 2026, Open bid tab, T4747 ↗
Light Pole Complete, F&Ieach$9,836$8,472 – $12,38215May 20, 2026, Open bid tab, T4666 ↗
Aluminum signal pole, removeeach$433.14$300.02 – $508.7114Jul 29, 2026, Open bid tab, T4747 ↗
Superpave asphalt concreteton$210.01$188.48 – $229.6214May 20, 2026, Open bid tab, T4666 ↗
Loop Detector Inductive, F&I,each$537.63$455.17 – $849.1214Jul 29, 2026, Open bid tab, T4747 ↗