Street Lighting · awarded bid prices · Broward County
Light Pole Complete, F&I: cost per each in Broward County, FL
The median awarded price is $11,000 per each, from 45 winning bids on 23 public projects in Broward County, FL (2023–2026). Half of the awarded prices fall between $9,880 and $12,269.
Cost by state › Florida › Broward County › Light Pole Complete, F&I
Winning bids only, as printed in the agencies' bid tabulations (FDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $9,303 in 2022 to $10,146 in 2026 (+9%).
| Year | Median per each | Winning bids |
|---|---|---|
| 2022 | $9,303 | 6 |
| 2023 | $12,000 | 19 |
| 2024 | $10,700 | 20 |
| 2025 | $11,092 | 14 |
| 2026 | $10,146 | 9 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Aug 26, 2026 | FDOT | 11 EA | $9,703 | Open bid tab, T4757 ↗ |
| Mar 25, 2026 | FDOT | 1 EA | $11,950 | Open bid tab, T4753 ↗ |
| Jan 28, 2026 | FDOT | 4 EA | $12,269 | Open bid tab, T4749 ↗ |
| Sep 24, 2025 | FDOT | 14 EA | $12,000 | Open bid tab, T4721 ↗ |
| Sep 24, 2025 | FDOT | 5 EA | $10,530 | Open bid tab, T4741 ↗ |
See every awarded price for this item on the Light Pole Complete, F&I item page.
Related items in Broward County
- Pull & Splice Box, F&I, 13" x 24": $1,794 per each
- Conduit, Furnish & Install: $43.50 per linear foot
- Conduit, Furnish & Install, Open: $24.23 per linear foot
- Prestressed Concrete Pole, F&I: $3,012 per each
- Lighting Conductors, F&I: $4.95 per linear foot
- Electrical Service Disconnect: $1,986 per each
- Electrical Service Wire, Furnish: $11.71 per linear foot
- Pole Cable Distribution System: $915.00 per each