Street Lighting · awarded bid prices · Broward County
Light Pole Complete, Remove: cost per each in Broward County, FL
The median awarded price is $1,528 per each, from 16 winning bids on 16 public projects in Broward County, FL (2023–2026). Half of the awarded prices fall between $1,089 and $2,494.
Cost by state › Florida › Broward County › Light Pole Complete, Remove
Winning bids only, as printed in the agencies' bid tabulations (FDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $619.34 in 2019 to $1,700 in 2025 (+174%).
| Year | Median per each | Winning bids |
|---|---|---|
| 2019 | $619.34 | 7 |
| 2021 | $608.87 | 6 |
| 2022 | $1,064 | 6 |
| 2023 | $1,095 | 8 |
| 2024 | $1,528 | 6 |
| 2025 | $1,700 | 8 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Aug 26, 2026 | FDOT | 6 EA | $4,830 | Open bid tab, T4757 ↗ |
| Sep 24, 2025 | FDOT | 1 EA | $3,000 | Open bid tab, T4721 ↗ |
| Sep 24, 2025 | FDOT | 2 EA | $3,000 | Open bid tab, T4752 ↗ |
| Aug 27, 2025 | FDOT | 52 EA | $683.11 | Open bid tab, T4688 ↗ |
| Jul 30, 2025 | FDOT | 1 EA | $2,000 | Open bid tab, T4648 ↗ |
See every awarded price for this item on the Light Pole Complete, Remove item page.
Related items in Broward County
- Pull & Splice Box, F&I, 13" x 24": $1,794 per each
- Conduit, Furnish & Install: $43.50 per linear foot
- Conduit, Furnish & Install, Open: $24.23 per linear foot
- Prestressed Concrete Pole, F&I: $3,012 per each
- Light Pole Complete, F&I: $11,000 per each
- Lighting Conductors, F&I: $4.95 per linear foot
- Electrical Service Disconnect: $1,986 per each
- Electrical Service Wire, Furnish: $11.71 per linear foot