| Paint pavement marking | linear foot | $2.58 | $1.75 – $3.86 | 38 | Mar 31, 2026, Open bid tab, T3845 ↗ |
| Pipe Culvert,Optional | linear foot | $208.50 | $133.81 – $300.00 | 37 | Sep 30, 2026, Open bid tab, T3908 ↗ |
| Steel Mast Arm Assembly, Furnish | each | $108,655 | $91,126 – $127,182 | 34 | Mar 31, 2026, Open bid tab, T3845 ↗ |
| Concrete Sidewalk and | square yard | $131.71 | $94.69 – $162.41 | 28 | Sep 30, 2026, Open bid tab, T3908 ↗ |
| Pipe Culvert, Opt Material | linear foot | $351.23 | $258.50 – $478.28 | 26 | Mar 31, 2026, Open bid tab, T3845 ↗ |
| Conduit, Furnish & Install | linear foot | $33.47 | $25.44 – $40.04 | 26 | Mar 31, 2026, Open bid tab, T3845 ↗ |
| Thermoplastic, Standard, White | each | $189.35 | $127.09 – $245.01 | 26 | Mar 31, 2026, Open bid tab, T3845 ↗ |
| Milling Existing Asphalt | square yard | $4.21 | $2.66 – $8.00 | 25 | Mar 31, 2026, Open bid tab, T3845 ↗ |
| Pipe Culvert, Optional Material | linear foot | $189.00 | $161.00 – $225.00 | 25 | Mar 31, 2026, Open bid tab, T3845 ↗ |
| Performance Turf, Sod | square yard | $5.08 | $4.40 – $9.00 | 25 | Sep 30, 2026, Open bid tab, T3908 ↗ |
| Sediment Barrier | linear foot | $5.12 | $3.87 – $9.43 | 23 | Sep 30, 2026, Open bid tab, T3908 ↗ |
| Pull & splice box, f&i, 13 inch x 24 inch | each | $1,100 | $1,037 – $1,276 | 22 | Mar 31, 2026, Open bid tab, T3845 ↗ |
| Mowing | acre | $100.00 | $81.94 – $400.00 | 21 | Mar 31, 2026, Open bid tab, T3845 ↗ |
| Litter remove | acre | $100.00 | $81.94 – $252.47 | 21 | Mar 31, 2026, Open bid tab, T3845 ↗ |
| Inlet Protection System | each | $306.08 | $251.85 – $772.76 | 20 | Mar 31, 2026, Open bid tab, T3845 ↗ |
| Thermoplastic, Preformed | each | $218.64 | $161.35 – $254.06 | 20 | Mar 31, 2026, Open bid tab, T3845 ↗ |
| Conduit, Furnish & Install, Open | linear foot | $15.88 | $13.87 – $17.40 | 20 | Mar 31, 2026, Open bid tab, T3845 ↗ |
| Remove of existing concrete | square yard | $45.67 | $24.04 – $77.50 | 20 | Sep 30, 2026, Open bid tab, T3908 ↗ |
| Thermoplastic, Standard, White | linear foot | $7.50 | $6.27 – $11.91 | 19 | Mar 31, 2026, Open bid tab, T3845 ↗ |
| Mitered End Section, Optional | each | $3,900 | $3,000 – $5,400 | 17 | Mar 31, 2026, Open bid tab, T3845 ↗ |
| Raised Pavement Marker, Type B | each | $5.80 | $4.58 – $7.47 | 14 | Sep 30, 2026, Open bid tab, T3908 ↗ |